Attachment D to I.M. 6.000
June 12, 2024
Local Public Agency Construction Contract Administration Guidance
This Attachment is only to be used for Local Public Agency (LPA) administered
projects. For projects administered by the Iowa DOT, refer to Chapter 2 of the
Iowa DOT Construction Manual. The Appendices for this Attachment can be
found in Chapter 2 of the Iowa DOT Construction Manual.
Chapters 1 and 3 through 12 are available in the Iowa DOT Construction Manual.
Local Systems recommends referencing these additional chapters as useful tools
for both general and topic specific construction inspection and contract
administration. In this manual, references to RCE (Resident Construction
Engineer) are equivalent to the Project Engineer on an LPA project.
TABLE OF CONTENTS
2.00 PROJECT ORGANIZATION .................................................................................................................. 1
2.01 AUTHORITY OF ENGINEER ............................................................................................................. 1
2.02 RESPONSIBILITY OF PROJECT ENGINEER ....................................................................................... 1
2.03 DELEGATION OF RESPONSIBILITY .................................................................................................. 2
2.10 PRECONSTRUCTION ....................................................................................................................... 2
2.11 PRECONSTRUCTION MEETING ...................................................................................................... 2
Discussion Items ....................................................................................................................... 2
Scheduling the Meeting ........................................................................................................... 3
List of Discussion Topics ........................................................................................................... 3
Utilities and Law Enforcement Attendance ............................................................................. 9
2.12 HAUL ROADS ................................................................................................................................ 10
2.13 STREAM CROSSINGS .................................................................................................................... 10
Permanent Structures - "Iowa Department of Natural Resources Notification of
Completion of Construction" (DNR Form 37) ........................................................... 10
Temporary Stream Crossings ................................................................................................. 10
2.14 WATER REGISTRATION AND PERMIT .......................................................................................... 10
2.15 WORKING AND SHOP DRAWING SUBMITTAL & REVIEW ......................................................... 11
2.20 CONTRACT ADMINISTRATION ......................................................................................................... 11
2.21 OCCUPATIONAL SAFETY AND HEALTH ........................................................................................ 12
2.22 EQUAL EMPLOYMENT OPPORTUNITY (EEO) ............................................................................... 12
Contractor's Responsibility .................................................................................................... 12
Project Engineer's Responsibility ........................................................................................... 14
2.23 TRAINING PROGRAMS ................................................................................................................. 15
2.24 DAVIS-BACON WAGE REQUIREMENTS ........................................................................................ 16
Certified Transcript of Labor Payroll ...................................................................................... 16
Attachment D to I.M. 6.000
June 12, 2024
Project Engineer's Involvement ............................................................................................. 28
Supplemental Wage Rates ..................................................................................................... 32
2.25 SUBCONTRACTS ........................................................................................................................... 32
Subcontract Requests ............................................................................................................ 32
Contractor’s Requirements .................................................................................................... 32
Project Engineer’s Responsibility ........................................................................................... 33
Leased Employees .................................................................................................................. 37
Subcontractor - Disadvantaged Business Enterprise (DBE) ................................................... 38
Subcontractor - Traffic Control .............................................................................................. 42
Prompt Payment to Subcontractors ...................................................................................... 43
Certification of Subcontractor Payment ................................................................................ 43
2.26 USE OF PROPERTY OUTSIDE OF PROJECT RIGHT-OF-WAY .......................................................... 43
2.27 "CONTRACT QUANTITY AGREEMENT" (FORM 830230) .............................................................. 44
2.28 RETAINED FUNDS ........................................................................................................................ 44
Release of Retained Funds ..................................................................................................... 44
Contractor .............................................................................................................................. 45
Project Engineer ..................................................................................................................... 45
2.29 Intentionally left blank ................................................................................................................ 46
2.30 CONSTRUCTION PERIOD .................................................................................................................. 46
2.31 ADMINISTRATION OF THE CONTRACT PERIOD ........................................................................... 46
Contract Types ....................................................................................................................... 46
Working Day ........................................................................................................................... 48
Calendar Day .......................................................................................................................... 49
Controlling Item of Work ....................................................................................................... 50
Special Considerations ........................................................................................................... 53
2.32 NOTICE TO PROCEED ................................................................................................................... 56
2.33 WEEKLY REPORT OF WORKING DAYS .......................................................................................... 58
Preparation of Form 830238 .................................................................................................. 58
Preparation of Incentive/Disincentive Form .......................................................................... 60
Multiple Sites on a Contract ................................................................................................... 61
2.34 LIQUIDATED DAMAGES AND EXTENSION OF CONTRACT TIME .................................................. 62
2.35 EQUIPMENT RENTAL RATES ........................................................................................................ 63
EquipmentWatch Cost Recovery ........................................................................................... 63
Invoiced Rental Costs ............................................................................................................. 64
Equipment Time Charges ....................................................................................................... 64
Chargeable Project Costs ....................................................................................................... 65
Statement of Force Account Form (Form 181213) ................................................................ 67
2.36 CHANGE ORDERS (FORM 831240 or Appia Change Order)......................................................... 67
Policy for Change Orders........................................................................................................ 67
Preparation of Change Order (Form 831240 or Appia Change Order) .................................. 70
Value Engineering .................................................................................................................. 80
2.37 PRIME CONTRACTOR’S PERFORMANCE BOND .......................................................................... 81
2.38 PROJECT ACCEPTANCE AND AUTHORIZATION FOR FINAL PAYMENT ......................................... 81
2.39 CONTRACTOR EVALUATION REPORT ........................................................................................... 81
2.40 PROJECT REVIEW AND AUDITS .................................................................................................... 82
2.41 RESERVED FOR FUTURE USE ........................................................................................................ 82
2.42 PROJECT ENGINEER'S PRE-AUDIT ................................................................................................ 82
Attachment D to I.M. 6.000
June 12, 2024
2.43 ADMINISTERING BUREAU AUDIT ................................................................................................ 82
2.44 RESERVED FOR FUTURE USE ........................................................................................................ 82
2.45 FORMS FOR FINAL PAYMENT PACKET ......................................................................................... 82
2.50 CONTRACTOR PAYMENTS AND PRICE ADJUSTMENTS .................................................................... 82
2.51 PAYMENT FOR MATERIAL ALLOWANCE (STOCKPILED MATERIALS) ........................................... 82
Pre-conditions for Material Allowances................................................................................. 83
Stockpile Documentation Work Sheet ................................................................................... 84
Voucher Entries ...................................................................................................................... 84
Miscellaneous ........................................................................................................................ 84
2.52 PAYMENT FOR UNEXPECTED CLASS 12 ROCK EXCAVATION ....................................................... 85
2.53 PRICE ADJUSTMENT GUIDE FOR REASONABLY CLOSE CONFORMING, REASONABLY
ACCEPTABLE, AND DEFICIENT WORK ......................................................................................... 85
Guide Schedules for Price Adjustments ................................................................................. 85
2.54 PRICE ADJUSTMENT CHANGE ORDERS ........................................................................................ 98
2.55 FINAL PAYMENT TO CONTRACTOR ............................................................................................. 98
Recommended Guidelines ..................................................................................................... 99
Interest Payment Information for County and City Projects ................................................. 99
2.56 FUEL ADJUSTMENT ...................................................................................................................... 99
Fuel Adjustment Calculation ................................................................................................ 100
Instructions for Fuel Adjustment Worksheet....................................................................... 100
2.60 CONSTRUCTION FORMS ................................................................................................................ 101
2.70 Intentionally left blank .................................................................................................................. 102
2.71 BRIDGE INVENTORY REPORT ..................................................................................................... 102
2.72 PREPARATION OF AS-BUILT PLANS ........................................................................................... 103
Types of Work ...................................................................................................................... 103
Wetlands .............................................................................................................................. 105
Right of Way ......................................................................................................................... 105
Land Section Corner Ties ...................................................................................................... 105
Tied Projects ......................................................................................................................... 105
As-Built Plans Checklists ....................................................................................................... 105
2.73 Intentionally left blank .............................................................................................................. 105
2.74 Intentionally left blank .............................................................................................................. 105
Attachment D to I.M. 6.000
June 12, 2024
Page 1 of 105
2.00 PROJECT ORGANIZATION
2.01 AUTHORITY OF ENGINEER
Oversight responsibility for construction contracts on Local Public Agency (LPA) projects
using Federal-aid rests with the Iowa DOT Administering Bureau, which is the Regional
Local Systems Field Engineer or the Systems Planning Bureau. The Iowa DOT
Administering Bureau also has oversight responsibility of LPA projects that utilize
Federal-aid Swap, Farm-to-Market (FM) and State-aid funding, as detailed in various
other Local Systems I.M.s. Responsibility for the actual construction inspection and the
day-to-day contract administration is delegated to the public employee designated as the
Person in responsible charge (PIRC), as defined in I.M. 6.000, of the project on behalf of
the LPA, and ultimately rests with the Project Engineer.
For county or city projects, Project Engineer decisions are subject to review and
concurrence by the appropriate staff person from the Iowa DOT Administering
Bureau. For projects overseen by Local Systems, this person is the Local Systems Field
Engineer. For projects overseen by the Systems Planning Bureau, this person is the
appropriate Grant Programs Team Member.
The Project Engineer has authority to administer construction contracts according to the
contract documents and assign and supervise inspection personnel on construction
projects. Project Engineer decisions pertaining to contract costs, time adjustments, or
contractual agreements are subject to review and perhaps revision by the PIRC.
2.02 RESPONSIBILITY OF PROJECT ENGINEER
The Project Engineer, who is assigned responsibility for supervision of roadway
construction projects, is the key person in the field organization.
In assuming the responsibility for proper fulfillment of assigned construction work, the
Project Engineer is also responsible for:
Maintaining good relations with contractors, affected property owners, and the
general public.
Assigning personnel to inspection and survey operations on the project, along
with providing the supervision and instructions necessary to assure proper
performance of assigned duties.
Keeping the Administering Bureau informed as to construction progress, status,
etc.
Maintaining complete project records and proper documentation.
Assuring proper use of equipment and materials used in the performance of
assigned duties.
Keeping the PIRC informed as to the construction progress, status, and any
issues that may need to be addressed.
While Project Engineers have responsibility for general supervision of the work, their
main concerns are for compliance with specifications and project completion. It is not
their responsibility to direct the everyday activities of the Contractor or their
subcontractors.
Attachment D to I.M. 6.000
June 12, 2024
Page 2 of 105
2.03 DELEGATION OF RESPONSIBILITY
The PIRC cannot and should not expect to retain all the duties and responsibilities. To
have an efficient organization each employee, including the Project Engineer, should be
delegated authority in line with their responsibilities and duties. The PIRC must check to
see that delegated duties are properly performed.
All employees should accept delegated responsibility and make decisions within the
authority delegated to them.
2.10 PRECONSTRUCTION
2.11 PRECONSTRUCTION MEETING
After award of the contract and prior to starting work on the project, the LPA shall
schedule a meeting between the Contractor, Administering Bureau, PIRC, Project
Engineer, and subcontractors. It is important to also invite any other affected or
interested parties including utilities, railroad, emergency response, and businesses that
may be affected by the construction. The meeting is generally conducted to discuss
project requirements and administrative details. The items for discussion at the meeting
and scheduling of the meeting will depend on the type and complexity of the project and
the Contractor and their subcontractors’ familiarity with Iowa DOT's procedures.
Preconstruction meeting invitee requirements vary based upon project funding. See I.M.
1.000, Iowa DOT Oversight of LPA Projects for funding categories and associated
construction administration activities. When Iowa DOT Administering Bureau attendance
is required, the LPA must consult the Administering Bureau in scheduling and provide at
least two weeks notice. Failure to provide proper notice and include Iowa DOT in
scheduling may require the LPA to reschedule the meeting if the Administering Bureau is
unable to attend.
Minutes of the Preconstruction Meeting can be documented on the Preconstruction
Meeting Notes form.
Discussion Items
The Project Engineer must consider the type of work, the experience of the
contractor, and complexity of the project to determine the appropriate items for
discussion.
Many contractors are experienced in working with Iowa DOT specifications and
contract requirements. In these instances, the need for discussing administrative
requirements and procedures in a meeting format may not be necessary and may be
accomplished using a preconstruction questionnaire.
A comprehensive list of topics that may be discussed at preconstruction meetings or
included in a preconstruction questionnaire is included at the end of this
section. The guideline includes topics that may not be necessary or applicable to all
contracts. An optional Pre-Construction Agenda Template can be found here:
https://iowadot.gov/local_systems/documents/Precon-Template.docx
Attachment D to I.M. 6.000
June 12, 2024
Page 3 of 105
Scheduling the Meeting
Preconstruction meetings may be scheduled any time after the award of the contract
and Iowa DOT Contracts and Specifications Bureau concurrence with the
award. Often times, the meetings are scheduled well in advance of the time that the
work will start in order to allow for coordination of utilities, work of other governmental
agencies, or other construction contracts. While these meetings are productive in
discussing the schedule of the project, key project personnel that will be directly
involved with the project may not be available. In this situation the opportunity to
discuss critical quality issues between the project personnel that will have primary
responsibility for the work may not occur.
Preconstruction meetings for projects that do not require detailed coordination efforts
with other entities may be held on the project site just before the work begins. These
meetings shall include the contractor and inspection personnel that will be involved in
the project.
For complex projects that do require advanced coordination of the intended
schedule, an earlier meeting should be held that would involve other appropriate
people. These earlier meetings should focus on the planning efforts needed to
achieve the intended schedule.
Assign the duties of taking minutes for the Preconstruction meeting to someone from
the agency or consultant.
Prepare an attendance list to circulate at the meeting. This list should include
columns for the attendees’ name, organization name, telephone, cell, and email
information. It is also recommended that columns for signatures and job titles be
included.
List of Discussion Topics
A. Administrative Details
1. Change Orders
Before commencing any work not covered by the contract, the Contractor and
the PIRC must agree on the price or prices to be paid for the work. Extra
work performed before this agreement cannot be considered for
payment. The basis of payment for the cost of extra work follows four
general categories:
Contract unit prices
Agreed unit prices
Lump sum
Force account
On force account work, the Contractor is required to record labor, equipment,
and material furnished on a Statement of Force Account form (Form
181213). The form shall be signed by the inspector and Contractor's
representative at the end of each day's work. Both the Contractor and
inspector will retain a copy.
Attachment D to I.M. 6.000
June 12, 2024
Page 4 of 105
Article 1109.10, Disputed Claims for Extra Compensations, of the Standard
Specifications, details requirements for submitting Contractor claims. When
the Contractor deems that extra compensation is due for work or materials
not covered by their contract, they are required to notify the Engineer in
writing before work begins on which the claim is based. The prior notice
allows the Engineer an opportunity to evaluate the issue and, if necessary,
consult with the PIRC, to address possible changes in the design when
appropriate. The Engineer is to respond in writing to the Contractor's claim.
If Doc Express is being utilized for contract administration, the Change
Orders will be made available in Doc Express.
2. Contract Documents
Contractors will see that copies of plans, specifications, and special
provisions are available at all times to their representatives on the project.
Plan revisions will be mailed to the Contractor as soon as they are issued, or
if Doc Express is being utilized for administration of the contract, the plan
revisions will be made available in Doc Express. Contractors will be
responsible for keeping their field representatives informed and supplied with
such revisions. If the Contractor believes such revisions require extra work,
they will immediately advise the Project Engineer.
3. Wage Rates (if applicable)
All wages paid must conform to wage and hour provisions prescribed for the
contract. Crafts must be listed exactly as shown in the wage decision. Crafts
not listed but needed shall be requested by the Contractor through the
Project Engineer. Required payrolls must be submitted weekly and within
seven days after the last day covered by the payroll.
The Contractor shall collect, sign, and submit all payrolls of approved
subcontractors, as a group, to the Project Engineer, or if Doc Express is
being utilized for administration of the contract, the payrolls should be
submitted in Doc Express.
If the Contractor’s payrolls are more than 2 weeks behind schedule, or more
than 3 weeks behind schedule for subcontractors, the Project Engineer
should advise the PIRC withhold progress payments on the items where
payrolls are overdue or require corrective action.
4. Postings
Contractor shall be responsible for erecting and maintaining required postings
as outlined in Sections 2.21 and 2.22 of this Attachment. Discuss methods
and location of postings, especially for projects that are at multiple locations
or are of short duration.
5. Materials
Attachment D to I.M. 6.000
June 12, 2024
Page 5 of 105
If the Contractor or their subcontractors want payment for stockpiled
materials that have been fabricated for the project, they should provide a list
of the types, quantity, and estimated cost of material expected to be
stockpiled. For payment, refer to Section 2.51 of this Attachment.
The Source of Materials List is to be submitted to the Project Engineer, no
later than the Preconstruction Meeting. The Project Engineer is to forward a
copy of the list to the Iowa DOT District Materials Engineer.
It is suggested that the Contractor submits, or uploads to Doc Express, a list
of the certified technicians that will be working on the project. This will allow
the Project Engineer an opportunity to verify that the certifications are current.
6. Subcontracting
On all contracts, the Contractor should have submitted subcontract requests
electronically using the SiteXchange program as described in Section 2.25 of
this Attachment. The Contractor is responsible for EEO and minimum wage
compliance by all subcontractors in addition to fulfilling terms of the contract.
Details of subcontracts that have "Part Items" should be discussed at the
preconstruction meeting. "Part Items" are those items that have a portion of
the plan quantity subcontracted or a part of the work required for a contract
item is subcontracted. It is especially important that "Part Items"
subcontracted to DBE subcontractors be discussed so project personnel are
informed of the work to be performed by DBE subcontractors (i.e.
Commercially Useful Function). The prime contractor should also be
reminded that the FHWA 1273 must be physically attached to each
subcontract on Federal-aid projects.
For subcontract requests and requirements, refer to Section 2.25 of this
Attachment.
7. Project Supervision
The Contractor shall submit in writing, to the Project Engineer, the name of
an authorized representative on the project. Representative will be
empowered to coordinate with all operations of subcontractors and negotiate
with the engineer any questions concerning extra work, including extra work
performed by a subcontractor. If the Contractor wishes, this representative
may be a subcontractor's employee that is present when work on the project
is being performed.
8. Weekly Report of Working Days
During the contract period, the Project Engineer will prepare and furnish the
Contractor with a Weekly Report of Working Days form (Form 830238)
showing working days charged that week or if Doc Express is being utilized
for contract administration, the Weekly Report of Working Days will be made
available in Doc Express. Objections to days charged must be submitted in
writing to the Project Engineer within 10 calendar days after the receipt of the
Attachment D to I.M. 6.000
June 12, 2024
Page 6 of 105
report. Objections based on delays due to unavailability of materials should
be accompanied by copies of orders placed, acceptance of orders, and
promised dates of delivery. Engineer will respond to the objection, indicating
acceptance of the claim or reasons for rejection.
9. Right of Way
All parties are reminded that roadway right-of-way adjoins private
property. Any infringement or trespassing upon such private property could
cause damage that would become a liability to the person or organization
involved. Maintaining good relations with the public is also important.
10. Safety
Contractor must comply with provisions of the Federal and State
Occupational Safety and Health Acts. Contractors are referred to Article
1107.07 of the Standard Specifications regarding safety responsibilities on
construction projects and the Iowa DOT Construction Manual 12.03 regarding
railroad company policies and agreements, if applicable.
11. Water Pollution
The Contractor's Erosion Control Implementation Plan (ECIP) and schedule
for control of water pollution shall be submitted to the Project Engineer, or
uploaded to Doc Express, prior to the preconstruction meeting. Storm water
discharge requirements, if applicable, should be discussed. For projects
regulated by NPDES storm water permit, identify the individual(s) that have
completed the Iowa DOT Erosion & Sediment Control Basics (ESC Basics)
web-based training and will be onsite daily and the Contractor’s Erosion
Control Technician (ECT). Additionally, the prime contractor’s Water
Pollution Control Manager should be identified.
Refer to Section 2602 of the Standard Specifications and Iowa DOT
Construction Manual 10.30.
12. Payment to Contractor
For Secondary projects, the Contractor may request intermediate progress
payments to be made on either a monthly or bi-weekly
interval. Measurement of quantities may be based on contract quantities by a
written Plan Quantity Agreement (Form 830230) (Article 1109.01 of the
Standard Specifications).
13. Contractor’s Use of Social Media
Providing current information to local businesses and residents affected by a
construction project is important. If a contractor intends to use social media
(i.e. Facebook, Twitter, etc.), the project engineer is to notify the PIRC so
they are able to view the information.
14. Contractor Furnished Sites
Attachment D to I.M. 6.000
June 12, 2024
Page 7 of 105
Contractor is responsible for identifying and obtaining all environmental
clearances/permits and land-use permits required by federal, state, and local
regulations for any contractor furnished sites used for obtaining borrow,
depositing waste material, stockpiling or staging, or creating a haul/access
road. These permits or clearances may include, but are not limited to 404
permits, NPDES permits, floodplain permits, and local land use permits.
The contract may contain a requirement for the contractor to submit an
Environmental Review Certification Form (Form 536003) for any contractor
furnished sites/areas. On other projects, submittal of Form 536003 is not
required but encouraged.
Refer to Articles 1106.06 and 1106.07, Construction Manual 6.10 and 6.34,
Environmental Review Certification Form User Guide (Form 536004), and
FAQ’s on “Environmental Considerations, Clearances, and Permits”.
https://iowadot.gov/construction_materials/FAQs/Environmental
15. Electronic Ticketing (E-Ticketing)
Will the Contractor be utilizing electronic tickets for any of the project
materials? If so:
a. What information will be required on the tickets?
b. How will that information be displayed?
c. Who will be responsible for ensuring the information is accurate and
complete at the source?
d. Who will be providing the information on the tickets in the field?
e. Who will need access to the tickets and who will be responsible for
adding those users?
f. If a cellular signal on the project is not available, what provisions will
be made so that the information will be available on the project site?
g. Are any special devices necessary for accessing the E-ticket
information? If so, who will provide them?
B. Project Details
On many projects it may be necessary for the Project Engineer to prepare and
present an enlarged plan or map for showing location, special areas of concern,
right of way restrictions, and staging.
Specific project information to be discussed includes:
Anticipated work starting dates.
Staging schedule (Article 1108.02, J, or Article 1110 of the Standard
Specifications).
Requirement for all employees to be wearing approved high-visibility
apparel as per 23 CFR 655.603 and 6D.03.04 of the MUTCD.
Attachment D to I.M. 6.000
June 12, 2024
Page 8 of 105
Signing and barricade responsibilities
- State/county responsibilities (Article 1107.09A, 1 of the Standard
Specifications).
- Contractor responsibilities (Article 1107.09, A, 2 of the Standard
Specifications).
- Contractor's traffic control contact information, submitted if traffic
to be maintained through construction areas (Article 1107.09, A, 2,
j of the Standard Specifications).
Construction staking requirements.
Discussion of items to be subcontracted and names of
subcontractors. Commercially useful function of DBE subcontractors,
suppliers, and manufacturers should also be discussed. (Section 2.25 of
this Attachment).
Equipment to be used Contractor should identify equipment with greater
than legal axle loads that is to be moved across bridges or pavements
that will remain in place. Equipment with greater than legal axle loads
(Article 2001.01 of the Standard Specifications and Iowa DOT
Construction Manual 3.40) must be either loaded on an appropriate trailer
or specifically exempted. Requests for exemptions will be analyzed on a
case-by-case basis by the Contracting Authority.
Special notes on plans, proposals, and special provisions.
Discuss advanced notification of pedestrian path closures as per Article
2528.01, A, 10, of the Standard Specifications.
Environmentally sensitive areas, including wetlands, mitigation areas,
historical sites; and remind the Contractor that they must obtain
necessary clearances for Contractor Supplied Borrow if they have not
already done so.
Pre-concrete conferences.
Value engineering incentive proposals submitted by the Contractor
(Article 1105.13 of the Standard Specifications and Section 2.36 of this
Attachment).
Railroad agreements and railroad flagging when applicable
C. Documents to be submitted by the Contractor:
Superintendent’s name and contact information
Foreman’s name and contact information
24-hour Contact name and phone number
Plant Inspector’s name and contact information (if applicable)
Traffic Control Technician’s name and contact information (applicable
only if the project includes an item for Traffic Control). Must be an
employee of the Contractor and not the subcontractor.
Attachment D to I.M. 6.000
June 12, 2024
Page 9 of 105
Erosion Control Technician’s name and contact information (applicable
only if the project includes a Storm Water Permit)
Source of Materials List (see Inspection Tools website)
Contractor’s Co-permit for the Storm Water Permit
Storm Water Co-permittee Certification Statement (Form 830215) for
each subcontractors that will be performing work that could result in
erosion or prevent erosion
Borrow documents (applicable only if project includes Contractor
Furnished Borrow)
Example of Contractor’s Daily Traffic Control Diary
Staging schedule
Traffic Control Plan (if applicable)
Value Engineering proposal (if applicable)
Erosion Control Implementation Plan
Utilities and Law Enforcement Attendance
At preconstruction meetings, attendance of utilities and law enforcement personnel could
be highly beneficial to all concerned. The Project Engineer should expend extra effort to
assure attendance and open communication with utilities and appropriate law
enforcement.
Relocation of utilities is of extreme interest to all concerned in the progress of the
project. Meeting with individual utility companies prior to the preconstruction meeting to
discuss their schedule for relocation is recommended. The appropriate time for this
meeting to be most effective will depend on project specific circumstances (i.e. start
date, letting date, extent of relocations required etc.) For safe control of traffic, the ability
to discuss traffic control with all contractors and law enforcement could be highly
beneficial. Local law enforcement officers (Local Police, Sheriff, or Campus Police) and
Highway Patrol should be invited to attend preconstruction meetings when
appropriate. Highway Patrol can be contacted through the Highway Patrol district office
having jurisdiction over the area where the project is located. Communication and
coordination with enforcement personnel regarding work zone staging changes is helpful
in improving project safety.
It is beneficial to discuss utilities relocation, project staging and/or traffic control early in
the meeting before more detailed and time-consuming construction matters are
discussed. Discussion concerning drainage district tile locations and private tile
locations should occur as both tile systems do not get located with the utility one-call
system.
Other Preconstruction Meeting Attendees
For Federal-aid projects, Representatives of the Civil Rights Bureau should be invited to
preconstruction meetings to be available to answer questions about DBEs, AA/EEO, job
postings, and any other questions regarding civil rights issues. Refer to I.M. 1.000, Iowa
DOT Oversight of LPA Projects, for other preconstruction meeting attendance
requirements based upon funding category.
Attachment D to I.M. 6.000
June 12, 2024
Page 10 of 105
2.12 HAUL ROADS
This section is usually not applicable for LPA projects. Negotiate between jurisdictions
as needed.
2.13 STREAM CROSSINGS
Permanent Structures - "Iowa Department of Natural Resources Notification of
Completion of Construction" (DNR Form 542-3017)
When a permanent structure is to be constructed on a stream with a drainage area of
100 square miles in rural areas and over 2 square miles in urban areas, the DNR
requires a permit to build the structure. The requirements are noted in the Iowa
Administrative Code, Environmental Protection [567], Chapter 71, 567-71.1. The permit
is obtained by the Bridges & Structures Bureau and issued to the Iowa Department of
Transportation. The permit will also cover a temporary stream crossing needed during
bridge construction.
When the project is completed, the Project Engineer will complete and finalize the
NPDES permit via their online permitting system. Refer to DNR guidance forms for
further information regarding this process.
Temporary Stream Crossings
Typically, if a temporary stream crossing is not permitted by the project’s Section 404
Permit, the plans will contain a note indicating access is not allowed. However, the
Section 404 permit should be reviewed to verify a temporary stream crossing is
permitted on a project. For more information, refer to the Iowa DOT Construction
Manual 10.40 and Frequently Asked Questions at:
https://iowadot.gov/construction_materials/FAQs/Environmental
The requirements for Temporary Stream Crossings are specified in Section 2547,
Temporary Stream Access, in the Standard Specifications. Temporary stream crossings
and causeways shall be constructed in accordance with Standard Road Plan EW-
401. Note that EW-401 identifies the types of materials that are permitted to be used to
construct temporary stream crossings and causeways and those materials DO NOT
include soils.
2.14 WATER REGISTRATION AND PERMIT
Any use of water which is a minor nonrecurring use, including roadway construction and
maintenance, shall not require a permit. In lieu of a permit, this use may be registered
with the Department of Natural Resources. Registrations usually extend for up to one
year and may be extended by re-registration and re-permitting.
For any construction project requiring water amounting to 25,000 gallons or more per
day, a "Registration of Minor, Nonrecurring Use of Water" (DNR Form 542-3112) must
be completed. An exception is made if the source is a city water supply; the Mississippi,
Missouri, or Big Sioux Rivers; or the Des Moines River bordering Missouri.
Attachment D to I.M. 6.000
June 12, 2024
Page 11 of 105
The Contractor shall complete and submit the "Registration of Minor, Nonrecurring Use
of Water" form (DNR Form 542-3112) and a project location map directly to the Iowa
DNR at the address listed on top of the form. A copy of the form is available at:
https://www.iowadnr.gov/About-DNR/About-DNR/Iowa-DNR-Forms-Permits. The
Contractor shall provide a copy of the completed form to the Project Engineer.
Daily records or documentation of water usage do not need to be kept.
Duplicate copies of "Registration of Minor, Nonrecurring Use of Water" (DNR Form 542-
3112) can be made from blank sample in the Iowa DOT Construction Manual Appendix
2-3.
2.15 WORKING AND SHOP DRAWING SUBMITTAL & REVIEW
Article 1105.03 identifies the contractual requirements for submittal and review of
working and shop drawings including identification of the primary review office. All
submittals of working & shop drawings shall be made to Doc Express, unless noted
otherwise in the contract documents, for review by the Project Engineer.
Working and shop drawing signature requirements are clarified in the following:
1. In the case of the Contractor and their fabricator, working or shop drawing
submittals do not need to be signed by a licensed Engineer if they are prepared
from the information provided in the plans without any changes, and the contract
documents (i.e. plans, specifications, etc.) do not state preparation must be by a
licensed Engineer.
If the working/shop drawing preparer proposes design changes in their submittal,
that would require them to have the submittal prepared and signed by a
Professional Engineer licensed in the State of Iowa.
2. In the case of the reviewer who will approve the working/shop drawings; the
same as above would apply. Also note that the review and approval does not
relieve the submitter/Contractor from responsibility as to the overall correctness
of the submittal as stated in Article 1105.03.
2.20 CONTRACT ADMINISTRATION
This section provides instructions and guidance to the Contractor and Contracting
Authorities for administration of construction contracts. Instructions include information
on required reports or forms, equal employment opportunity, wage reports, training
program, minority recruitment, and subcontracting. Copies of Iowa Department of
Transportation forms referred to in this section are included in the Iowa DOT
Construction Manual Appendix 2 and can be copied as needed. Electronic versions
(Word, Excel or Adobe Reader format) of the forms are also available on the DOT’s
website: https://iowadot.seamlessdocs.com/sc/ or on the Construction and Materials
Bureau website: https://iowadot.gov/construction_materials/Inspection-tool
Forms and Reports - Prepared by the Contractor:
Attachment D to I.M. 6.000
June 12, 2024
Page 12 of 105
Form No.
Title
Reference
Section
102116
Certification of DBE Accomplishment
2.25*
518002
Certification of Subcontractor Payment
2.25*
830176
Certified Transcript of Labor Payroll/Statement of
Compliance
2.24*
830231
Subcontract Request
2.25*
830215
Storm Water Co-Permittee Certification Statement
10.33
831240
Change Order for Local Public Agency Projects
2.36*
Forms & Reports - Initiated by Contractor, Prepared by Project Engineer
830230
Contract Quantity Agreement
2.27*
* Indicates Section in the Attachment
2.21 OCCUPATIONAL SAFETY AND HEALTH
Occupational Safety and Health Act (OSHA) regulations (federal and state) apply to all
construction projects. (Federal OSHA regulations are codified in 29 CFR, Sections 1910
and 1926.) Contractors are responsible for compliance with OSHA regulations and shall
maintain a safe work site. Therefore, the Contractor, the subcontractors, and all of their
employees must be familiar with the health and safety requirements of the act.
Article 1102.19, E, 5 of the Standard Specifications require that a poster entitled Job
Safety and Health Form 70-8025 be displayed in a prominent place at all times.
Iowa Workforce Development
https://workforce.iowa.gov/employers/business-resources/employer-posters
or
Occupational Safety and Health Administration
https://www.osha.gov/publications
23 CFR 634 addresses issues of worker visibility. The purpose of the regulations in this
part is to decrease the likelihood of worker fatalities or injuries caused by motor vehicles
and construction vehicles and equipment while working within the right-of-way on
Federal-aid highways. The rule states that all workers within the right-of-way of a
Federal-aid highway who are exposed either to traffic (vehicles using the highway for
purposes of travel) or to construction equipment within the work area shall wear high-
visibility safety apparel.
2.22 EQUAL EMPLOYMENT OPPORTUNITY (EEO)
Contractor's Responsibility
The Contractor, their subcontractors, and all of their staff who are responsible for the
hiring, supervising, promoting, and discharging of employees shall be knowledgeable
Attachment D to I.M. 6.000
June 12, 2024
Page 13 of 105
of their EEO/AA Policy. Their EEO/AA efforts will be reviewed on a company-wide
basis rather than on project specific efforts.
1. Contractor's EEO Policy
The Contractor and their subcontractors shall have an EEO/AA policy
approved by the Civil Rights Bureau, prior to awarding a contract or
approving subcontracts which are $10,000 or greater. The policy is to be
reviewed and resubmitted each year.
The policy is to include:
General operating statement
Designation of EEO officer
Definition of EEO & AA
Company’s recruitment policy
Certification that the company does not possess segregated facilities
Plan for employee training and promotion If the Contractor or any of
their subcontractors do not have a training program, their EEO/AA
Policy shall state that there is no plan.
The Contractor and their subcontractors shall conduct periodic meetings with
supervisory and personnel staff at least every 6 months to review and discuss
the company’s policy. All new supervisory and personnel staff shall be
instructed of the policy within 30 days of being hired.
2. Postings
All required site postings shall be in a location that is easily accessible to all
employees and applicants. The location should have been identified at the
Preconstruction Meeting (see Section 2.11 of this Attachment). Postings may
be fastened to a bulletin board, tool shed, or job office/trailer and protected
from weather by glass or clear plastic. Postings that become soiled, faded, or
otherwise illegible should be replaced. More than one posting may be
necessary if there are multiple locations where workers report for work. Such
cases typically occur on complex or long projects involving several different
crews and/or subcontractors. The project bulletin board shall be in place
before work starts and remain on the project until the project is completed
and accepted by the Project Engineer (Form 830435 is signed).
The following are required to be posted on the project bulletin board:
Subcontractor Authorization and EEO Poster Notice provided by the Iowa
DOT Contracts and Specifications Bureau that lists the name, address
and phone number of the Contractor's and all subcontractors' EEO/AA
officer. This form is considered the Department’s written authorization of
subcontractors for the contract.
Know Your Rights: Workplace Discrimination is Illegal*
Form FHWA 1022 Notice Concerning False Statements and Records
Form 70-8025 Job Safety and Health
WHD-1420 Your Rights Under the Family Medical Leave Act of 1993
Attachment D to I.M. 6.000
June 12, 2024
Page 14 of 105
WHD-1462 Employee Polygraph Protection Act
Pay Transparency Nondiscrimination Provision
USERRA Poster, “Your Rights Under USERRA”
If predetermined wage requirements apply:
- Current Pre-Determined Wage Rate Decision
- Form WH-1321 Employee Rights Under the Davis-Bacon Act
* The Spanish version of these posters is recommended where Spanish
speaking employees or applicants are likely to occur.
Electronic files of the posters are available for printing by the Contractor on
the Civil Rights website:
https://iowadot.gov/civilrights/documents-forms-and-reports
3. Reports and Records
The Contractor and their subcontractors are required to maintain records to
document compliance with EEO/AA requirements for a period of 3 years
following completion of the contract.
These records include:
Number of minority/non-minority/females employed in each
classification
Progress and efforts made in hiring minorities and females
The Contractor and their subcontractors shall submit the following documents to the Civil
Rights Bureau:
Their company's EEO/AA Policy annually
Annual report each July listing the number of minorities/females/non-
minorities in each classification in July (FHWA-1391)
When requested, documentation of periodic meetings, inspections,
and investigations
The Contractor and their subcontractors who have not complied with the
specification may be required to submit a plan for corrective action to the
Iowa DOT Civil Rights Bureau. Failure to correct the deficiencies may result
in suspension of that contractor’s bidding privileges for a period up to one
year.
Project Engineer's Responsibility
While responsibility for complying with EEO requirements is solely the Contractor
and their subcontractors, the Project Engineers responsibility on contracts include:
1. Subcontract Request
Refer to I.M. 5.030, Attachment B, Iowa DOT Letting Process, for instruction
on how to manage subcontractor requests before the contract is executed.
Attachment D to I.M. 6.000
June 12, 2024
Page 15 of 105
For additional requests or modifications to existing requests, the Contractor
and their subcontractors are to submit the forms to the Project Engineer. The
Project Engineer should confirm that the subcontractor has an approved
EEO/AA policy and that the amount subcontracted does not exceed 70%
prior to approving the subcontract. The Project Engineer forwards the .CON
file (before award) or Form 830231, Subcontract Request, to the Contracts
and Specifications Bureau for processing. A list of contractors with approved
policies is available from the Civil Rights Bureau website.
https://iowadot.gov/civilrights/Documents-forms-and-reports
2. Review of Project Bulletin Boards
Inspection staff is to review the Contractor's bulletin board for required
notices/posters. Progress payments may be suspended if the appropriate
notices/posters are not displayed on the project site. Work may be
suspended for continued non-compliance. At least one inspection shall be
made on contracts of short duration (six months or less). If the contract
exceeds 6 months, at the start of every 6 month period, a site inspection shall
be performed to ensure that the documents are still correct and legible. If the
project's bulletin board is damaged an inspection shall be performed after
repairs have been made to ensure that it meets the requirements. Reviews
shall be documented on Form 650170, Project Engineer’s EEO Project Site
Inspection/Wage Rate Report.
3. "EEO Project Site Inspection/Wage Rate Report" (Form 650170)
After reviewing the project's bulletin board, the inspector's findings should be
documented on the "Project Engineer's EEO Project Site Inspection
Wage/Rate Report." This report includes a checklist of the required postings.
This report also serves to document the wage-rate interviews of the
Contractor and subcontractors’ employees. The completed report is to remain
in the Project Engineer's file and a copy uploaded to Doc Express.
4. In-depth EEO Inspections
On selected contracts, staff from the Iowa DOT, Civil Rights Bureau may
request that a more detailed EEO interview be conducted. The in-depth
interview/report will coincide with EEO reviews of the home office conducted
by staff from the Civil Rights Bureau. The Civil Rights Bureau staff will
provide their request and instructions to the Project Engineer at the time of
the in-depth review.
2.23 TRAINING PROGRAMS
Requirements for training of all contractors' employees are included in the EEO/AA
specification, Article 1102.19. The Contractor and all of their subcontractors are required
to have a written training and promotion plan when their three-year average of all work
contracted (including subcontracted work) with the Department equals or exceeds
$5,000,000. The required minimum number of trainees is dependent on the amount of
work under contract.
Attachment D to I.M. 6.000
June 12, 2024
Page 16 of 105
Responsibility of the Contractor and all of their subcontractors
When required, the written training and promotion program shall include details such
as:
Designated crafts of trainees
Maximum ratio of one trainee to 3 journey-workers (by craft)
Methods for training and number of hours required for training
Payment to trainees
Rate of pay for trainees shall be described as a percentage of journey
worker's rate of pay. Trainees' rate of pay shall be at least the appropriate
rate that is specified in their approved training program. The Project
Engineer should verify with the Civil Rights Bureau that the Contractor and all
of their subcontractors have an approved training program if trainees are
being paid less than full Davis-Bacon wage rates.
Individuals enrolled in a training program shall be paid benefits as outlined in
Section 2.24 of this Attachment.
After a trainee has completed his/her training program, the trainee's base
wage rate shall be increased to the Davis-Bacon's wage determination for
that job classification.
Records
The Contractor and all of their subcontractors shall furnish a copy of the
program to each trainee as well as a certification of satisfactory completion.
All contractors shall submit an annual training report to the Civil Rights
Bureau documenting their training efforts for the year.
2.24 DAVIS-BACON WAGE REQUIREMENTS
Certified Transcript of Labor Payroll
A. Regulations
Regulations covering interstate, primary, secondary, and city projects financed in
whole or in part with federal funds may require submission of a "Certified
Transcript of Labor Payroll" (Form 830176) in accordance with "Required
Contracts Provisions" (Form FHWA-1273). These requirements will be included
on the proposal and shall be carefully studied and observed.
Davis-Bacon regulations apply to laborers and mechanics employed by the
Contractor and subcontractors on, adjacent or virtually adjacent to the "Site of the
Work". "Site of the Work" includes the physical location of the work called for in
the contract documents. Also included are tool yards, batch plants, borrow pits,
etc. provided they are dedicated exclusively to performance of the contract and
"provided they are adjacent or virtually adjacent to the site of the work".
The U.S. Department of Labor has interpreted "adjacent to the Site of Work" to
indicate a common boundary, while "virtually adjacent" indicates a small
separation between the project and temporary plant site.
Attachment D to I.M. 6.000
June 12, 2024
Page 17 of 105
Temporary plants, Contractor Furnish Borrows, or the Contractor's staging yard
established for a project would be considered "Site of Work only when the site is:
adjacent (common boundary between the project and plant site) or
virtually adjacent (for example: plant site is separated from the project site
by a narrow strip of land such as a local road between a project and a
plant site)
Chapter 15 of the Department of Labor Field Operations Handbook describes
Davis-Bacon and the Contract Work Hours and Safety Standard Act
requirements. A link to Chapter 15 of the DOL Handbook is available at
https://www.dol.gov/agencies/whd/field-operations-handbook/Chapter-15.
Project engineers shall refer questions concerning Davis-Bacon coverage to the
Administering Bureau. If necessary, the Administering Bureau will consult with
the Construction and Materials Bureau so uniform interpretations can be
provided.
Occasionally, Project Engineers receive requests from private sources for copies
of certified payroll records. If the project is being administered by a consultant,
the request for release of payroll records should be sent to the PIRC. The PIRC
is the person responsible for all payroll records. Iowa's "Open Records Law"
provides for the release of all information except social security
numbers. Requests for payroll records must be submitted in writing. Copies of
these written requests are to be provided by registered mail to the Contractor that
initially submitted or will submit certified payrolls. If a request for subcontractor
information is received, a copy of the request will also be sent to the
Contractor. Requests are to be acknowledged in writing, confirming that
information is available and indicating that social security numbers will be
withheld. Payroll records must not be released until 14 calendar days after a
copy of the request is received by the Contractor. This allows the Contractor an
opportunity to obtain a court injunction to stop the release if they believed the
information could affect the competitive bidding process. These procedures are
to be followed for requests received from outside sources, such as labor unions.
Adherence to these procedures during investigations by the Department of Labor
or FHWA is not required. Another exception has been made for representatives
of the Iowa Labor Management Work Preservation Fund, who may obtain project
payrolls for a given week without a written request provided it does not cause
undue inconvenience for the Project Engineer's office (Iowa Administrative Code-
761 IAC 4.9(31))
When contract provisions state that a certified transcript of weekly payroll is
required, the Contractor shall submit to the Project Engineer or upload to Doc
Express one copy of Form 830176 or an alternate form which contains the
information as required in FHWA-1273, Section IV 3.
Project engineers must also ensure "Statement of Compliance" information is
furnished with the payrolls and that the Contractor has signed all payrolls
received from subcontractors.
Attachment D to I.M. 6.000
June 12, 2024
Page 18 of 105
If an individual works on more than one project during a period, payroll
information shall include adequate data to verify correct computation and
payment of fringe benefits.
B. Postings
A copy of wage rates must be posted in a location easily accessible and visible to
all employees and applicants. It should be attached or adjacent to the posted
Wage Rate Information Federal-Aid Highway Project form (Form WH-
1321). Supplemental wage rates requested and approved shall also be posted.
C. Davis-Bacon Wage Requirements for Independent Truckers
Federal-aid construction contracts may include Required Contract Provisions
(FHWA-1273) which governs Davis-Bacon wage rates and fringe benefits for the
project. Therefore, all employees of the Contractor or subcontractor hauling on a
Davis-Bacon covered project must be paid in accordance with FHWA-1273
requirements.
When an independent trucking firm is engaged to haul materials to a
Davis-Bacon covered site, Davis-Bacon coverage of drivers depends on the
status of the material supply source. Department of Labor has consistently held
that the following are construction activities covered by Davis-Bacon provisions
[Code of Federal Regulations, 29 CFR, Section 5.2(j)(1) & (2)]:
Employees working in situations where materials are produced from an
operation, plant, or pit that is opened or installed "virtually adjacent" to a
construction site for the exclusive purpose, or nearly so, of fulfilling
contract material requirements, and
Truck drivers who haul and deliver materials from those locations to the
job site. The only exception is for bona fide owner-operators physically
driving their own trucks. This exception does not extend to other drivers
of independent trucks.
Truckers hauling from a commercial source are not covered by Davis-Bacon
requirements except for the time spent on the project. This ruling applies to all
trucking, whether it is by an employee of the Contractor, subcontractor, or an
independent material supplier or transporter. A trucker employed by the
Contractor/subcontractor may be covered when hauling from portable plant to
project and not covered if hauling from commercial quarry to portable plant site.
Commercial sources are not considered part of the "site of work." This includes
permanent plants and quarries that are not established for a specific project.
Portable plant sites set up in a commercial quarry for a specific project are
considered part of the site of work when the quarry is adjacent to or virtually
adjacent to the project site.
For deliveries by a supplier or an independent trucking firm from a certain
material supply facility to be considered outside Davis-Bacon coverage, the
facility must be off the project site and 10% or more of sales must actually be
made from the facility to the general public. (See Section 5.2(1)(3) of
Attachment D to I.M. 6.000
June 12, 2024
Page 19 of 105
Regulations, Part 5.) Sales to the public must be more than token sales.
Additionally, DOL has further defined Material Suppliers as entities that ONLY
deliver materials/supplies and ONLY engage in activities as part of those tasks.
An entity that both supplies materials and also performs contract work is not a
supplier but rather a contractor or subcontractor, and ALL employees are subject
to Davis-Bacon labor standards provided their time on site is not de minimis.
D. Preparation of Certified Transcript of Labor Payroll
Use the Certified Transcript of Labor Payrolls form (Form 830176) when
preparing and submitting payrolls.
1. Heading
The heading of a payroll transcript must include the information as shown
in the Iowa DOT Construction Manual Appendix 2-14.3. Subcontractors
shall include name of the Contractor. Wage decision number must be
listed, so there will be no confusion on minimum wage rates for the
project.
2. Contracts with Multiple Projects
Typically, payroll transcripts are required from the Contractor and each
subcontractor for a project. However, for multi-project contracts, the
Contractor may prepare one "combined" payroll transcript if the projects
have identical wage schedules and are worked more or less as one
project with individuals used interchangeably between projects.
Therefore, the Contractor and subcontractors may combine multiple
projects for payroll transcripts provided:
the Contractor and each subcontractor prepares individual
transcripts, and
all projects included are listed on that "combined" payroll
transcript.
2a. Projects that cover multiple Wage Zones
Contractors are required to pay employees hourly wage rates and fringe
benefits in accordance with the appropriate work classification and Wage
Zone as specified in the Predetermined Wage Rate for the
contract. Wage Zones are defined in the Predetermined Wage Rate by
groupings of counties and cities.
If a project traverses two or more wage zones, the contractor may elect
to pay employees either:
Wage rates/fringe benefits based on the higher Wage Zone, or
Attachment D to I.M. 6.000
June 12, 2024
Page 20 of 105
Wage rates/fringe benefits based on the Wage Zone where the
employee performed work. This requires additional record keeping to
document the time employees worked in different wage zones.
3. Required Contract Provisions
The Required Contract Provisions (Form FHWA-1273) attached to
contract documents show that at least the following items shall be
observed:
a. Payrolls shall only contain employee's full name and an
individually identifying number for each employee (e.g., the last
four digits of the employee's social security number). Contractors
and subcontractors are required to maintain complete social
security numbers and addresses of employees and to provide
such information to government agencies upon request.
b. Employee's craft and classification must be listed exactly as
shown in the wage decision. For example, it is not acceptable to
simply use "Operator-Group 2" without listing the classification.
c. If an employee works in more than one work classification during
the pay period, the employee's hours may be assigned to one
classification, provided the classifications are in the same Group
(i.e. same wage rate and fringe benefit).
d. Deductions must be itemized.
e. No individual shall be employed as laborer or mechanic except on
an hourly-wage basis.
f. All Contractors shall comply with all applicable federal, state, and
local laws governing safety, health, and sanitation.
g. Overtime pay shall be computed on 40 hours/week. This means
an employee must accumulate the initial 40 hours before overtime
becomes reimbursable. This is computed at the base
Davis-Bacon rate with fringe benefits being paid at the straight
time rate.
Employee work hours accumulated on a contract where the
Davis-Bacon Act applies shall be reimbursed at least Davis-Bacon
labor rates. The Contractor and their subcontractors shall
carefully track and document time for employees who charge time
to different contracts in a single pay period, especially if these
different contracts are not all subject to Davis-Bacon labor
rates. For example:
CASE 1:
Attachment D to I.M. 6.000
June 12, 2024
Page 21 of 105
Employee "A" has charged labor time to two projects in week
"X". Project 1 is subject to Davis-Bacon, project 2 is
not. Employee "A's" time sheet shows:
Monday - Thursday, 4 days at 8 hours/day, project 1
Friday, Saturday, 2 days at 8 hours/day, project 2
Employee "A" has accumulated 48 hours (6 days x 8
hours/day) in week "X."
Employee "A" is reimbursed:
4 days x 8 hours/day = 32 hours x project 1's
Davis-Bacon wage rate
1 day x 8 hours/day = 8 hours x project 2's standard
wage rate
1 day x 8 hours/day = 8 hours OT x project 2's
overtime rate
CASE 2:
Employee "B" has charged labor time to the same two projects
noted in Case 1. This employee's time sheet shows:
Monday - Thursday, 4 days at 10 hours/day, project 2
Friday, 1 day at 8 hours/day, project 1
Employee "B" has accumulated 48 hours (4 days x 10
hours/day) plus (1 day x 8 hours).
Employee "B" is reimbursed:
4 days x 10 hours/day = 40 hours x project 2's
standard wage rate
1 day x 8 hours = 8 hours OT x project 1's
Davis-Bacon overtime rate
CASE 3:
An employer may elect to pay weighted overtime for overtime
hours worked. Using the example from Case 2 above,
overtime may be calculated as follows.
Calculate weighted overtime rate:
(40 hours x project 2's standard wage rate) + (8 hours x
project 1’s Davis-Bacon wage rate) = total base pay
Total base pay/48 hours worked = weighted pay rate
Weighted pay rate x 1.5 = weighted overtime rate
NOTE: If the weighted overtime rate does not exceed the
Davis-Bacon rate, the Davis-Bacon rate must be used.
As in Case 2, employee "B" has accumulated 48 hours (4 days
x 10 hours/day) plus (1 day x 8 hours).
Attachment D to I.M. 6.000
June 12, 2024
Page 22 of 105
Employee "B" is reimbursed:
4 days x 10 hours/day = 40 hours x project 2's standard
wage rate
1 day x 8 hours = 8 hours OT x weighted overtime rate
4. Work Assignments
The Contractor and their subcontractors shall acquaint their supervisors
with crafts and minimum wage provisions so employees are assigned
work that conforms to their classification. The correct classification and
rate may be reported to Contractor's home office. Exceptions to the
general rule include:
To establish a uniform procedure among contractors for future wage
determinations, contractor shall show on payroll COMBINATION crafts for
employees performing more than one type of work. However, all work
classifications for that individual shall be listed. For example:
CASE 1:
Lower classification employee doing higher classification work.
Shall segregate hours and pay at higher wage rate if individual
is not being reimbursed the highest rate for class of work
performed.
CASE 2:
Higher classification employee doing lower classification work.
Not necessary to segregate hours performing separate tasks,
provided individual continues to be reimbursed at the highest
rate.
Shall segregate hours and classifications if individual will have
their wage rate reduced when doing lower classification work.
In Iowa, there is not an "Ironworker" classification for all zones. For
these situations, employees erecting structural steel are to be classified
as "Carpenters and Piledrivermen".
5. Working Supervisors
Supervisors who spend more than 20% of their time performing other
"labor type" duties as a regular part of their activities at the job site must
be so designated by having the "other" work classifications listed on the
payroll transcript. For example: A supervisor who also does carpentry
work, or operates a dozer, or drives a truck would have to have these
duties listed on the payroll transcript.
Attachment D to I.M. 6.000
June 12, 2024
Page 23 of 105
This requirement confirms their hourly rate is for the highest work
classification. Any premium pay received for supervision will be over and
above the rate of pay for work performed.
6. Apprentices
Apprentices are permitted to work at less than the predetermined wage rate
when all of the following conditions apply:
They are individually registered in an approved apprenticeship program;
They are paid the percentage of the hourly rate required by the
apprenticeship program;
They are paid the appropriate fringe benefits as discussed in the
paragraph below;
They are employed within the allowable ratio specified in the approved
program for the number of apprentices to journeymen;
Compliance with the apprentice-journeymen ratio is to be applied on the
job site.
Compliance with the apprentice-journeymen ratio is to be determined on
a daily, not weekly, basis.
Apprentices shall be paid fringe benefits in accordance with provisions of
the apprenticeship program. If a particular apprenticeship program does
not specify fringe benefits, apprentices must be paid the full amount of
fringe benefits listed on the wage determination for applicable
classification. If the Wage and Hour Division administrator determines
that a different practice prevails for the applicable apprentice
classification, fringe benefits shall be paid in accordance with that
determination.
Refer to FHWA-1273 IV(4)(a) for more details.
7. Trainees
In general, the same conditions for apprentices above apply for trainees.
Refer to FHWA-1273 IV(4)(b) for more details.
Trainees shall be paid fringe benefits in accordance with provisions of the
trainee program. The Project Engineer should verify with the Civil Rights
Bureau that the contractor has an approved training program if trainees
are being paid less than full Davis-Bacon wage rates. If a particular
trainee program does not mention fringe benefits, trainees shall be paid
the full amount of fringe benefits listed on the wage determination for the
work actually performed. The Wage and Hour Division administrator will
determine if there is an apprenticeship program associated with the
corresponding journeyman wage rate on the wage determination which
provides for less than full fringe benefits for apprentices.
8. Owner-Operators of Hauling Equipment
Attachment D to I.M. 6.000
June 12, 2024
Page 24 of 105
Bona fide owner-operators of trucks and similar construction hauling
equipment, who are independent contractors, are not subject to
enforcement of contract labor standard provisions. Owner-operators of
other non-hauling type equipment are considered as employees, not as
subcontractors.
A ruling by the Department of Labor states in effect that:
Because owner-operators usually work under payment
arrangements based on a unit price [for example, so much per
cubic meter (yard) hauled] rather than on an actual truck or
equipment rental rate plus the driver's (or operator's) rate, and
Because of difficulties that have arisen with respect to securing
adequate data on rental arrangements in order to determine
whether contract minimum rates are being paid, therefore,
As a matter of administrative policy, the provisions of Davis-Bacon
and related acts will not be applied to bona fide owner-operators
of trucks or other similar construction equipment used exclusively
for hauling and who are independent contractors.
This policy, which is not intended to encompass other equipment such as
bulldozers, scrapers, backhoes, cranes, drilling rigs, and welding
machines, will be in effect until such time as it may appear practical to
devise workable and easily enforceable procedures for obtaining
compliance with respect to such owner-operators.
The Certified Transcript of Labor Payrolls form (Form 830176) including
names of such bona fide owner-operators need not show hours worked
nor rates allegedly paid, but only operator's name and the notation
"owner-operator." In this way, such individuals can be recognized as
bona fide independent contractors NOT subject to contract labor standard
provisions and can be distinguished from equipment operators who ARE
subject to such provisions.
A ruling by the Chief Counsel for the Federal Highway Administration
requires that data for each driver employee of truck owner-operators,
regardless of number of trucks owned, must be shown the same as for
any other laborer or mechanic. This means all such employees shall be
listed on the payroll with a complete breakdown of hours worked, hourly
rate paid, and all other required information according to "Required
Contract Provisions" (Form FHWA-1273). In those instances where truck
"owner operators" drive their own truck, payroll notation shall list them as
"owner operator" with no further information relative to hours worked or
wages paid. However, during multi-shift operations when an owner may
hire a driver for a subsequent shift, a complete breakdown of information
relative to daily hours worked, hourly rate paid, etc., must be shown on
the payroll for "employee of owner-operator." This same procedure shall
be followed if owners have several trucks for which they hire drivers. The
only exception to showing a complete breakdown of information is when
"owner operators" physically drive their own trucks.
Attachment D to I.M. 6.000
June 12, 2024
Page 25 of 105
9. Flaggers
The Department of Labor has determined that duties of flaggers are
clearly manual and physical in nature and as such they are laborers or
mechanics within the meaning of the Davis-Bacon Act. Flaggers who
perform a dual function, such as flagger and journeyman, have to be paid
journeyman's rate.
10. Survey Crews
Survey crew members who spend most of their time on a covered project
taking or assisting in taking measurements would likely be deemed
laborers or mechanics and covered by Davis-Bacon labor standards
(provided that they do not meet the tests for exemption as professional,
executive, or administrative employees under 29 CFR part 541).
11. Exempt Classifications
The Department of Labor has determined that classifications whose
duties are generally not manual or physical in nature are not subject to
Davis-Bacon regulations. The following classifications are considered
exempt from Davis-Bacon regulations, provided that the employees are
not engaged in other covered work:
a. Ticket-taker
b. Certified plant inspector, Quality Control technician
c. Survey crew, except for survey crew members who perform
primarily physical and/or manual duties.
12. Corrections
When errors or omissions are discovered, the Contractor or their
subcontractors will be required to make necessary corrections and submit
a supplemental payroll transcript. If a subcontractor has to make
correction, it must be submitted to the Contractor for review before being
submitted to the Contracting Authority. Original transcript will not be
returned. A Supplemental transcript shall be so labeled (e.g. No. 15
Supplemental). Examples of supplemental transcripts are shown in the
Iowa DOT Construction Manual Appendix 2-14.4. Only employees
affected by the errors or omissions are listed on the supplemental.
The Contractor or their subcontractors may be required to submit a
notarized statement from the employee or a copy of both sides of a
canceled check verifying that an adjustment has been made. Sufficient
explanation shall be given to make any adjustment easily understood by
all who may review a supplemental transcript.
13. Starting, Suspending, Completing Payroll Transcripts
Payroll transcripts shall be submitted as soon as the contractor starts any
project activity at the site of work. Transcripts shall be in sequential order
starting with the number "1." When work on a contract is suspended, the
Attachment D to I.M. 6.000
June 12, 2024
Page 26 of 105
last payroll transcript should be labeled "suspend" (e.g. No. 14
Suspend). This procedure shall be followed when work is resumed or
completed (e.g. No. 15 Resume and No. 24 Final). Contractors, if they
choose, may continue payroll transcripts during the suspension period
with a notation on the transcript "No work during this period."
If any of the contractors fail to submit required records or make them
available, the Iowa DOT, FHWA, or DOL may, after written notice to the
Contractor, take such actions as may be necessary to suspend further
payments. Payment should be withheld to the Contractor for those items
that are contracted to the contractor who is in violation. Payment to
subcontractors who submit correct payrolls should not be withheld
because of mistakes of another subcontractor. Failure to submit required
records upon request or make such records available may be grounds for
debarment action.
14. Records
Payrolls and basic records shall be maintained by the Contractor and
each during the course of the work and shall be available for inspection at
any time by authorized representatives of the contracting agency, DOL, or
FHWA.
Regulations and contract provisions require all contractors to preserve
employment records at least 3 years after completion and final settlement
of the contract.
E. Completion of "Statement of Compliance"
A "Statement of Compliance" is printed on the backside of the Certified
Transcript of Labor Payroll form (Form 830176) and relates to wage kickbacks,
payrolls, apprentices, fringe benefits, and falsification penalties. A copy is
provided in the Iowa DOT Construction Manual Appendix 2-14.2. Those
Contractors who have permission to use their own payroll form must attach a
copy of the "Statement of Compliance" to their payroll transcript. The statement
of compliance is certified by the dated signature of the Contractor or an
authorized agent. The Contractor must also sign all Statements of Compliance
submitted by their subcontractors. A scanned copy of the original "Statement of
Compliance" and payroll transcripts may be submitted to the Project Engineer as
email attachments, or by uploading to Doc Express, provided the Contractor
retains the Statement(s) of Compliance with original signature(s) for the required
retention period.
F. Fringe Benefits
Davis-Bacon prevailing wages are made up of two interchangeable components -
basic hourly wages and fringe benefits. Under Davis-Bacon, fringe benefits must
be paid for all hours worked. The fringe benefits may be paid:
In cash
To an approved plan, fund or program
Attachment D to I.M. 6.000
June 12, 2024
Page 27 of 105
Any combination thereof
Example:
The wage decision requires:
Basic hourly rate $10.00
Fringe benefits $ 1.00
Total prevailing rate $11.00
The contractor can comply by paying:
1. $11.00 in cash wages
2. $10.00 plus $1.00 in pension contributions or other "bona fide" fringe
benefits
3. $ 9.00 plus $2.00 in pension contributions or any combination
of "bona fide" fringe benefits. In this example, overtime must be paid
at the basic hourly rate of $10.00.
1. Payment of Fringe Benefits to an Approved Plan
All contractors who pay fringe benefits to approved plans, funds, or
programs in amounts not less than determined in applicable wage
decision shall show on the face of their payroll the basic cash hourly rate
and overtime paid to employees. Such contractors shall check 4(a) to
indicate they are paying to approved plans, funds, or programs not less
than the amount predetermined as fringe benefits for each craft. Any
exception shall be noted in 4(c). Details of the fringe benefit plan, fund, or
program shall be submitted with the first payroll to the Project Engineer.
The submittal shall include description of the benefits, dollar amount
contributed per hour, and if applicable, name of the Trustee or third
person to whom the benefits were paid.
Included as "bona fide" fringe benefits, are benefits such as supplemental
unemployment plan, life insurance, health insurance, pension, vacation,
holidays and sick leave. Credit may be taken as Davis-Bacon fringe
benefits for training, provided the training program is approved by the
U.S. Bureau of Apprenticeship and Training and the amount is
reasonable (i.e. less than $0.50/hr). No credit may be taken for any
benefit required by federal, state or local law (i.e. worker's compensation,
unemployment compensation or social security contributions). Also,
travel expenses, meals, lodging, per diem expenses, uniforms,
administrative expenses, union administrative dues, union working dues
or industry promotional funds (i.e. Heavy Highway Advancement Fund,
Labor-Management Work Preservation Fund) are not considered bona
fide fringe benefits within the meaning of Davis-Bacon regulations.
2. Cash Payment of Fringe Benefits
All contractors who do not pay any fringe benefits to an approved plan,
fund, or program must make cash payment to an employee. Payment
shall not be less than the predetermined fringe benefit amount plus
minimum wage rate. When fringe benefits are paid in cash, the
Attachment D to I.M. 6.000
June 12, 2024
Page 28 of 105
contractor shall check 4(b). Any exceptions shall be noted in 4(c). If part
of the fringe benefits are paid to an approved plan, fund, or program and
part in cash to an employee, then both 4(a) and 4(b) shall be checked.
3. Fringe Benefits and Overtime
Contracts covered by the Davis-Bacon Act are also subject to the
Contract Work Hours and Safety Standards Act (CSHSSA) which
requires overtime on covered projects at 1 ½ the hourly rate for hours
worked in excess of 40 hours per week.
The overtime rate is computed at the sum of 1 ½ times the basic rate plus
the designated hourly rate for fringe benefits. It is not required that the
hourly cash rate for fringe benefits be multiplied by a factor of 1 ½.
For example:
Davis-Bacon rate $10.00
Fringe benefit $ 2.00
The overtime rate of pay may be calculated by 3 methods:
1. $10.00 (base) + $2 (fringe) + ½ $10.00 (D-B rate) = $17.00
2. $12.00 (cash) + ½ $10.00 (D-B rate) = $17.00
3. $ 8.00 (base) + $4 (fringe) + ½ $10.00 (D-B rate) = $17.00
Project Engineer's Involvement
A. Field Procedure
Early and complete labor compliance inspections are essential to the
development of a sound compliance pattern on all contracts. EEO Site
Inspections are required to be performed on the Contractor and each
subcontractor performing more than $10,000 of work (on any contract). Wage
rate interviews are required as part of the Inspection, unless they participate in
the Associated General Contractors of Iowa Prevailing Wage Notification
Program (see below). Results of inspections, wage rate interviews, and/or
confirmation of AGC of Iowa Prevailing Wage Notification Program shall be
documented on the Project Engineer’s EEO Project Site Inspection/Wage Rate
Report form (Form 650170). At least one inspection shall be made on the
following:
Contracts of short duration (six months or less).
If the Contractor or a subcontractor works longer than 6 months on the
project, at the start of every 6 month period, an interview shall be
performed to ensure that the Davis-Bacon requirements are still being
met.
For contracts which extend over a longer period of time (greater than 6 months),
inspections shall be made on approximate six months intervals. The Project
Engineer is responsible to see that required labor compliance inspections are
conducted and recorded. Whoever is assigned the compliance inspection needs
to be thoroughly familiar with the regulations and instructions.
Attachment D to I.M. 6.000
June 12, 2024
Page 29 of 105
The Associated General Contractors of Iowa have implemented a Prevailing
Wage Notification Program. All contractors participating in this voluntary program
have established a proactive method for informing their employees of the Davis-
Bacon wages and benefits to be paid on projects.
It is felt that these proactive measures by the contractor will allow the Project
Engineer to eliminate the routine wage rate interviews and focus on complaints
received from the employees. This procedure will not eliminate the need for
posting the wage rate decision on bulletin boards or submittal of certified
payrolls.
The list of contractors participating in the Prevailing Wage Notification Program is
maintained on the AGCI's website (http://www.agcia.org/pwnp.asp). Any
contractor wishing to participate should contact the AGC of Iowa.
The Project Engineer's office staff review certified payrolls that have been
submitted. In order to ensure that certified payrolls have been received for all
subcontractors whose employees worked during a given week, the office staff
must be advised of the subcontractors that worked. The Project Engineer's office
should develop a process to provide this information between the inspection staff
and office staff.
If payrolls of the Contractor are not received within 2 weeks of the period
covered, the Project Engineer’s staff should advise the Contractor, in writing,
which payrolls have not been submitted and that progress payments for the work
will be withheld. If payrolls of subcontractors are not received within 3 weeks of
the period covered, the Project Engineer should advise the Contractor, in writing,
which payrolls have not been submitted and that progress payments for the
subcontracted items will be withheld. In either case, communication with the
Contractor sooner than these time limits may be appropriate to inquire on the
status of payrolls.
B. Wage-Rate Interview
When conducting a wage-rate interview, the following questions shall serve as a
guide:
1. Is the employee receiving at least the specified wage rate for type and
class of work performed?
2. Is proper allowance being made for fringe benefits and have the plans
been explained to the employees?
3. Is work performed within the proper classification?
4. Are additional classifications necessary?
5. Does the employee have complaints as to hours, wages, and fringe
benefits?
The findings of the wage rate interview are to be documented on the EEO Project
Site Inspection/Wage Rate Interview form (Form 650170). Names of employees
interviewed and date of the certified payroll transcript used are to be recorded on
the interview form. If no discrepancies are identified during the interview, this
Attachment D to I.M. 6.000
June 12, 2024
Page 30 of 105
should be so noted. In some instances, employees may not be knowledgeable of
the pre-determined hourly wage rates and fringe benefits to which they are
entitled. Furthermore, they may not be aware of the hourly wage rates and fringe
benefits they have been paid or what work classification they have been
assigned. In these cases, the interviewer should document on Form 650170 that
the findings of the interview were inconclusive because the employee was unable
to respond to the questions. Interview forms are to be retained in the project files
and uploaded to Doc Express.
C. Violations and Complaints
Any violations discovered, or complaints received, shall be investigated
promptly. The PIRC should be actively involved in the investigation. If the
Contractor is found to be in violation of the contract's labor standard provisions, a
complete report shall be written giving details of violation(s) and results of the
investigation.
The report shall also include an amount of money, if any, found to be due to
employees and the number of employees who shall receive these payments. A
copy of this report shall be sent to the Administering Bureau. The Administering
Bureau will review and forward to the Construction and Materials Bureau.
D. Office Procedure
1. Payroll transcripts shall be checked to verify that:
Information in the heading is correct and complete.
Titles designating crafts correspond correctly with those in wage
schedule for that particular contract. No others may be used
unless a supplemental wage determination has been secured by
the Contractor or subcontractor. If a listed craft is not included in
the wage decision, the Contractor or subcontractor shall be
advised that a supplemental wage rate must be requested.
Rate per hour is not less than that shown for each craft in the
wage schedule for that contract, and overtime rates (if any) are at
least one and one half times the regular base rate, plus any fringe
benefits. Exception: The Contractor and subcontractors have the
option to reduce basic cash wage by the excess payment of fringe
benefits. Fringe benefits may be in cash, by contribution into a
bona fide fringe benefit program, or a combination of both.
Fringe benefits (if any) have been provided and appropriate
paragraph is checked on the Statement of Compliance.
The Statement of Compliance is complete and properly
signed. Multiple-sheet transcripts will be considered certified if the
necessary information and dated signature are shown on the last
sheet of that packet.
Attachment D to I.M. 6.000
June 12, 2024
Page 31 of 105
Signature of the Contractor appears on all payrolls submitted from
subcontractors.
Transcript is submitted within one week after the end of a payroll
period. ESTIMATES SHALL BE WITHHELD until such time as
these requirements are fulfilled.
An occasional spot check to determine accuracy of computations.
Checking payroll transcripts can be time consuming. The primary
objective is to ensure the proper wage rate is being paid. It is
important to review the first 3-4 payrolls received from the
Contractor and subcontractors carefully to be sure information is
complete and accurate. Once it is apparent that wage rates used
are appropriate, it is not necessary to check each line of each
payroll. However, occasional spot checks should continue to be
made, paying particular attention to new crafts listed as the active
work type transitions. If problems are noted, subsequent payrolls
must be checked until problems are resolved. Payrolls submitted
to Doc Express that have been checked shall be indicated by
adding “Checked by xxx” in the comment field in Doc Express.
2. Transition
All payrolls submitted to Doc Express by the Contractor shall be
transitioned to “received” by the Project Engineer. The date of this
transition becomes the “Date Rec’d Project Engineer’s Office” for (Form
830176) This transition shall be completed after the above noted
verification checks, as applicable, and should occur regularly as the
project progresses.
3. Corrections
When errors or omissions are discovered on transcripts, the Contractor
will be advised. Necessary corrections must be made on a supplemental
payroll transcript (See example in the Iowa DOT Construction Manual
Appendix 2-14.5). The original payroll transcript will NOT be returned to
the Contractor or their subcontractors; however, copies indicating
necessary corrections may be supplied. The original payroll and any
previous revisions shall remain in Doc Express as noted in the Doc
Express LPA User’s Guide Appendix.
4. Disposition
Retention of payroll transcripts by the Contracting Authority shall comply
with the requirements in I.M. 6.110, Final Review, Audit, and Close-out
Procedures for Federal-aid, Federal-aid Swap, and Farm-to-Market
Projects.
Attachment D to I.M. 6.000
June 12, 2024
Page 32 of 105
Supplemental Wage Rates
If, after a letting, the Contractor determines that the wage decision for the contract
does not include wage rates for one or more work classifications to be used, the
Contractor must request additional classification(s) and wage rate(s). The
contractor shall initiate the request by completing a “Request for Authorization of
Additional Classification and Rate” form (Form SF-1444)
https://www.gsa.gov/reference/forms/request-for-authorization-of-additional-
classification-and-rate. Contractor completes blocks 1-15. Contractors must request
employees, if present, or their designated representative, to sign block 16 noting the
employee's concurrence or disagreement with the contractor's proposed wage and
benefit rate. The "designated representative" may be a union representative;
however, it cannot be the contractor's representative. The contractor must pay the
proposed wage and benefit rate pending response from DOL.
The request shall be submitted to the Contracts and Specifications Bureau who, after
concurrence, will forward the form to the U.S. Department of Labor for approval.
Approval from the U.S. Department of Labor usually takes at least 30 days, so an
early request by the Contractor is necessary. Final payment to the Contractor shall
not be held up pending a response from the Department of Labor, if the Contractor
has made timely submittals for additional wage classifications and there are no DOL
investigations on file.
2.25 SUBCONTRACTS
Subcontract Requests
Contractor’s Requirements
Instructions for completing Subcontract Requests are available on the Contracts and
Specifications Bureau website:
https://iowadot.gov/contracts/lettings/subcontracting.pdf
Note the additional guidelines on the administration of DBE subcontracts that follow.
Except for trucking by DBE firms, Subcontract Requests (Form 830231) are not
required for trucking of materials. Trucking by DBE firms shall be documented on a
Subcontract Request and Approval form, but the dollar value will not be used to
determine the amount subcontracted. The Contractor or subcontractor shall advise
the Project Engineer in writing, on a daily basis, the names of independent
companies that will be hauling materials on the “site of work”. This will allow the
Project Engineer to monitor trucking companies for compliance with Davis-Bacon
requirements. Similarly subcontract requests also are not required for concrete
pumpers, but employees of concrete pumping companies are subject to Davis-Bacon
wages and Certified Payrolls when employed on the site of work. The contractor (or
Attachment D to I.M. 6.000
June 12, 2024
Page 33 of 105
subcontractor) should also advise the project engineer when concrete pumpers are
on site to ensure compliance with Davis-Bacon requirements.
“Subcontract Requests” are not required for work performed by a “wholly owned”
subsidiary of the Contractor. When the subcontractor is a wholly owned subsidiary of
the prime contractor, the amount subcontracted may be reported as zero. A list of
wholly owned subsidiaries is maintained by the Contracts and Specifications Bureau
and can be obtained from the Administering Bureau. NOTE: the Administering
Bureau can obtain the list at w:\Highway\Contracts\FieldInformation.
The Contracts and Specifications Bureau will upload a Subcontractor Authorization
and EEO Poster Notice to Doc Express for placement on the project’s bulletin board.
This poster is considered the Department’s written authorization of subcontractors for
the contract.
Project Engineer’s Responsibility
For all contracts, the Project Engineer must have the list of subcontractors and their
associated items for proper administration. A .CON file is required to view the
subcontractor list and the SiteXchange software is needed to view the .CON file. A
current pdf of the subcontractor requests and approvals should be in the Contract
Documents drawer in Doc Express.
Initial Subcontract Requests:
For Iowa DOT let projects, the Prime Contractor submits all subcontractors and their
associated bid items to the Contracts and Specifications Bureau either before or at
the time of contract using the electronic .con file produced by the SiteXchange
software. The Contracts and Specifications Bureau will process the initial electronic
subcontractor request(s), create the tax certificates and AA/EEO Poster for all DOT
let, LPA contracts.
Using SiteXchange: To download the SiteXchange software:
o Go to https://iowadot.gov/contracts/general-letting-
information/bidexpress-utility-files and click on “SiteXchange”.
o A box will appear “What do you want to do with SiteXchange.zip”, click
the “Save” button.
NOTE: You only need to do this once to get the software on to your machine!
Save the SubCon.exe file onto your computer.
NOTE: It is VERY IMPORTANT that you keep track of where it is saved,
because when the Contractor sends you a “.con” file, you will need to save it
in this same folder to be able to open it!!! To make this easier, create a
shortcut to the SubCon.exe file on to your desktop so you won’t have to find it
in explorer every time you want to open a “.con” file.
To view the subcontractor list
o Open SiteXchange.
o Click on the File dropdown menu.
o Click on Open…
Attachment D to I.M. 6.000
June 12, 2024
Page 34 of 105
o Or click on the icon that looks like a file folder with an arrow showing that
it is opening.
The Open Contract dialog box will appear.
Click on the contract that you need.
Then click on the Open button.
At this point, click on the printer icon to get the list of Subcontractors.
Attachment D to I.M. 6.000
June 12, 2024
Page 35 of 105
If you want a hard copy for your files and inspectors to have in the field,
select your printer.
You will also need to print an electronic copy print to Adobe pdf.
Printing subcontract requests:
In order to print subcontract requests, you must have a C:\SUBCON folder that
contains 3 files SubCon.exe, vendor.bin, and the appropriate .CON file for the
contract. The vendor.bin file is periodically updated and it is critical to keep the most
current copy of it in the C:\SUBCON folder so the appropriate contractor’s name
prints.
Once you have the 3 files in the C:\SUBCON folder
1. Double click on the SubCon.exe
2. Click on Run
3. Click the Open icon
4. Highlight the appropriate .CON file and then click Open
5. Click the Print icon
All subcontract requests will be printed as well as a summary sheet.
Subcontract requests submitted after time of Contract signature:
If modifications to the subcontractor list are necessary after contract signing, the
Prime Contractor shall submit all requests to the Project Engineer for their review
and approval. The Project Engineer shall:
Verify that the Subcontracting limit of 70% has not been exceeded.
Verify that the subcontractor has a current EEO/AA Policy, they should
appear on the Status listing as found at this website:
https://iowadot.gov/civilrights/documents-forms-and-reports
Approved_EEO_AA_Policy_List.pdf
Send the “.con” file on to the Contracts and Specifications Bureau at
dot.contracts@iowadot.us so they can prepare tax certifications & send a
new EEO poster notice for the Contractor’s bulletin board.
Additional information about required checks and the submittal process to can be
found on the Contracts and Specifications Bureau website, and in Attachment C to
this I.M.
Existing items by subcontractor:
The Project Engineer is to check revised .CON files for accuracy (%
subcontracted, current EEO/AA policy, items assigned to appropriate
subcontractor) and forward the revised .CON file to the Contracts and
Specifications Bureau as an email attachment. The email is sent to
dot.contracts@iowadot.us with a subject line of “Revised Con File”.
New or existing items by a new subcontractor:
If new items are added to a contract and will be completed by a new
subcontractor, the subcontractor request must be submitted to the Project
Engineer using the Subcontract Request form (Form 830231). The SiteXchange
software is not able to generate a Subcontract Request form because the
software does not support new items added by Change Order. A subcontract
Attachment D to I.M. 6.000
June 12, 2024
Page 36 of 105
request is not required for new contract items to be completed by an existing
contractor.
The Project Engineer is to check the Subcontract Request form for accuracy (%
subcontracted and current EEO/AA policy) and forward the form to the Contracts
and Specifications Bureau as an email attachment. The email is sent to
dot.contracts@iowadot.us.
However, if there was originally a .CON file but the revision is due to an item
being added by contract modification or change order, the prime must submit a
paper subcontract request and then you must add the sub’s new item(s) and
notify the Administering Bureau for addition of the subcontractor to Doc Express,
in addition to forwarding it to the Contracts and Specifications Bureau. (The hard
copy of the subcontract request can be scanned and e-mailed.)
If a subcontractor is to be linked to a new item, the Contractor will furnish you
with a paper subcontract request. It is the Project Engineer’s responsibility to
authorize the subcontractor and then forward the request to the Contracts and
Specifications Bureau.
Once the Contractor submits the Subcontract Request to the Project
Engineer as an attachment to an email, the Project Engineer is to review
the Subcontract Request form to ensure that the percent subcontracted
does not exceed the maximum threshold and that the subcontractor has a
current EEO/AA policy. If all information is correct the Subcontract
Request form should be attached to an email to the Contracts and
Specifications Bureau at dot.contrac[email protected]s. The email, with
attachment, should also be forwarded to the project inspector. The
Subcontract Request can then be filed in the project file or uploaded to
Doc Express.
In summary:
All Subcontract Requests must be prepared using the “.CON” file and
submitted electronically, except for new items added to a contract that will be
completed by a subcontractor. In this instance, the SiteXchange does not
support new items added by contract modification or change order. In this
case, the request is submitted on hardcopy form of Subcontract Request
(Form 830231) and submitted to the project engineer as an attachment to an
email. A blank copy of the Subcontract Request (Form 830231) is provided
in the Iowa DOT Construction Manual Appendix 2-16.1 and 2-16.2. The
Contracts and Specifications Bureau will provide a Subcontractor
Authorization and may upload a new EEO Poster Notice to Doc Express for
placement on the project’s poster board. This poster is considered the
Department’s written authorization of subcontractors for the contract. If a
corrected EEO Poster Notice is sent to the Project Engineer, it should replace
the outdated form on the Contractor’s Poster Board. If the Contracts and
Specifications Bureau does not send a corrected EEO Poster Notice, the
Project Engineer should verify with the Contracts and Specifications Bureau
that the new Subcontract Requests were received and the new
subcontractors may be added to the document on the poster board by hand.
Attachment D to I.M. 6.000
June 12, 2024
Page 37 of 105
The additional/modified requests are submitted to the Project Engineer to minimize
delays in providing the information to field staff.
The Project Engineer is responsible to make sure a subcontractor does not perform
more work than described on the approved subcontract.
Occasionally, subcontractors may have to rent additional equipment and hire extra
employees to complete their work. However, when the entire crew and equipment of
the Contractor or another subcontractor is used to complete work, the Contractor is
violating the intent of Article 1108.01 of the Standard Specifications and is
considered brokering a project. If the Project Engineer's staff observes work
performed by anyone other than the approved subcontractors, the Administering
Bureau should be notified. Assistance will be provided to investigate the
circumstances.
At the preconstruction meeting, it will be beneficial to discuss methods of keeping
subcontractors informed of the work status. Although the Contractor is responsible
to make progress payments to a subcontractor, numerous incidents in the past have
indicated a lack of timely progress payments from the Contractor to the
subcontractor. Subcontractors may request the Project Engineer to furnish them a
copy of a progress voucher for informational purposes.
Leased Employees
The Contractor and approved subcontractors may utilize "leased" employees as part
of their "own" work crew. In either case, the Contractor shall submit a Subcontract
Request before leased employees can be on the job site. "Leased" employees shall
be obtained from a firm that does not perform highway construction (i.e. a temporary
employment agency).
When "leased" employees are used, they are considered part of the contactors "own
organization" when the following requirements are followed:
The Contractor maintains control over the supervision of the day-to day
activities of the leased employees.
The Contractor remains responsible for the quality of the work of the leased
employees.
The Contractor retains all power to accept or exclude individual employees
from work on the project.
The Contractor remains ultimately responsible for the payment of
predetermined minimum wages and submission of payrolls on contracts that
required predetermined wages.
The employee leasing company will appear on the list of subcontractors and under
the EEO/AA list. The leasing company is responsible for all customary employer
responsibilities including EEO/AA in hiring, training and promotions, and the
submittal of required employee information to the Department, state, and federal
agencies. If prevailing wages are required, the employee leasing company shall
submit certified payrolls. The certified payroll will need to designate the Contractor
that is using the leased employee(s).
Attachment D to I.M. 6.000
June 12, 2024
Page 38 of 105
A leased employee may be utilized by the Contractor or different subcontractors
during a project; however, the individual employee may be used by only the
Contractor or one of the subcontractors at a time.
DBE Contractors and DBE subcontractors may not use leased employees because
Federal DBE regulations prohibit the use of leased employees and will not meet the
commercial useful function towards DBE commitments.
Subcontractor - Disadvantaged Business Enterprise (DBE)
A. Contract Award
On Federal-aid projects with predetermined goals, all bidders will be required to
submit a Statement of DBE Commitment form (Form 102115) with their bid. This
form identifies DBE subcontractors, suppliers, transporters, and/or manufacturers
that will be used to satisfy the DBE goal. Form 102115 shall also include work or
items to be subcontracted, cost of this work, percent applicable to DBE goal, and
dollar amount committed to each DBE.
Upon execution of a contract, the Contractor becomes committed to those DBEs
listed on Form 102115. This commitment is therefore a contractual arrangement
between the State and the Contractor with the same enforcement as any other
provision specified in the contract documents. The Contractor is required to
enter into a contractual arrangement with each DBE listed by formally executing
a written subcontract agreement specifying the work to be performed and
appropriate compensation for that work. This two-tier process, which
contractually obligates the Contractor to both the State and each participating
DBE, formalizes implementation of all DBE contract provisions.
The Contracts and Specifications Bureau will review the low bidder's Statement
of DBE Commitments form (Form 102115) to assure that certified DBEs are
being used. After review, the DBE commitment information will be posted on Bid
Express (https://bidx.com/ia/main) in the letting page for each letting.
B. Subcontract Requests
For added or modified subcontracts, the Project Engineer must compare the
Subcontract Request form (Form 830231) submitted by the Contractor to the
Contactor's DBE Commitment found in Bid Express
(https://bidx.com/ia/main). The Contractor must subcontract the work to the
certified DBE subcontractor. Any request to change certified DBE
subcontractors, or any request to subcontract work for less than the total amount
shown on the "DBE Commitment" document shall not be approved without
written approval from the Civil Rights Bureau.
1. Temporary Employees and Leased Equipment
A DBE may lease equipment consistent with standard industry practice
provided a rental agreement, specifying terms of lease arrangement, is
approved prior to a DBE starting work. If equipment is of a specialized
nature, the lease may include an equipment operator. If this practice is
Attachment D to I.M. 6.000
June 12, 2024
Page 39 of 105
generally acceptable within the industry, then the operator can remain on
lessor's payroll. For equipment that is not specialized, a DBE is expected
to provide the operator and be responsible for all payroll and labor
compliance requirements.
Operation of equipment shall be subject to full control of the DBE. Such
an arrangement shall be short term and involve a specialized piece of
equipment used at the job site.
The Civil Rights Bureau maintains an electronic roster of certified DBE
trucks: https://iowadot.gov/civilrights/Disadvantaged-business-enterprise-
program-DBE/DBE-Program
2. Commercially Useful Function
A commercially useful function exists when:
A DBE is totally responsible for execution of a distinct element of
work by actually performing, managing, and supervising the work
involved in accordance with the contract documents, normal
industry practice, and
that DBE firm receives due compensation as agreed upon for the
work performed.
To meet commercially useful function requirements of the regulations and
contract, the following statements are applicable:
DBE firm must manage the work contracted. Management shall
include scheduling work operations, ordering equipment and
materials (if materials are part of the contract), preparing and
submitting payrolls and all other required reports and forms, as
well as hiring and firing employees, including supervisory
employees.
DBE shall perform work with employees normally employed by
and under the DBE's control. In all instances, the DBE shall be
responsible for payroll and labor compliance requirements
concerning all workers under their control. DBEs may use other
means to perform work on a limited basis when the contract
requires specialized knowledge, skills, or equipment. A DBE may
be allowed to augment their work force with personnel which
normally work for another firm, if requested and approved by the
Civil Rights Bureau prior to commencing work.
DBE must supervise daily operations of their portion of contracted
work. The only two acceptable ways for a DBE to supervise daily
operations are:
1) The DBE owner may act as the superintendent and
directly supervise work, or
Attachment D to I.M. 6.000
June 12, 2024
Page 40 of 105
2) A skilled and knowledgeable superintendent employed and
paid wages by the DBE must directly supervise that work.
If the latter is used, the DBE owner must be actively involved in
making operational and managerial decisions of the
firm. Basically, this means that all administrative functions shall
be performed by personnel responsible to, or employed by, the
DBE at facilities or locations under the DBE's control.
DBEs shall supervise and perform contracted work with workers
on their payroll and under their direct supervision. The DBE and
their superintendent must, on a full-time basis, supervise and
control contracted work. Supervision of contract work by
personnel normally employed by the Contractor or another
subcontractor, or by personnel not under the DBE's control
constitutes failure to perform a commercially useful function.
The DBE Specifications Article 1102.17 includes minimum requirements
for DBE manufacturers, dealers, transportation services, and
subcontractors. DBE subcontractors that indicate work which will be
performed by employees of another firm or with leased equipment should
be questioned.
The Administering Bureau shall be notified in all cases where there is a
question of commercially useful function before that subcontract is
approved.
The Civil Rights Bureau will assist in determining requirements of a
commercially useful function for DBE suppliers and manufacturers.
3. Partial Subcontract of an Item
It is not unusual for DBE subcontractors to be involved in only part of a
contract item. This is to be documented on Form 830231 by clearly
stating in the "Description" column exactly what portion of an item is to be
accomplished by the DBE and the corresponding dollar amount. Details
of subcontracts that have "Part Items" should be discussed at the
preconstruction meeting so project personnel are informed of the work
(i.e. Commercially Useful Function) to be performed by DBE
subcontractors.
For conditions where a subcontract does not exist but a DBE firm is
manufacturing, supplying, or trucking materials to the job site, terms of
the agreements shall be described in Form 830231. This information is
documented on Form 830231 so the Project Engineer can be assured
that the Contractor is meeting commitments previously stated on the
Statement of DBE Commitments form (Form 102115). The work
documented on the form shall be assigned to a contract item. A typical
example may be for trucking only of hot mix asphalt and should be
included as: "HMA Surface-Trucking Only-Lump Sum"; Quantity =1; Unit
Price= $30,000. This dollar value will not be used to determine the
Attachment D to I.M. 6.000
June 12, 2024
Page 41 of 105
percent subcontracted as specified in Article 1108.01 of the Standard
Specifications.
Inspection staff must monitor work performed and periodically inform the
Project Engineer as to which individuals and equipment actually worked,
so payrolls can be spot-checked.
C. Construction Period
The Project Engineer and inspectors must routinely review work subcontracted to
DBE subcontractors to assure work is being performed as intended and that
DBEs are performing a commercially useful function. Where work is performed
by the Contractor or any other subcontractor or with equipment not owned by the
DBE, the inspector shall issue a non-compliance notice citing violation of the
Specification for Disadvantaged Business Enterprises, of Article 1102.17 of the
Standard Specifications. This non-compliance shall be immediately reported to
the Project Engineer, who will in turn notify the Administering Bureau.
The Contractor will be given credit toward the DBE contract goal only when a
DBE performs a commercially useful function. The requirements for a
commercially useful function are outlined in the previous section "Subcontract
Requests."
A DBE may lease equipment consistent with standard industry practice provided
a rental agreement, specifying terms of lease arrangement, is approved prior to a
DBE starting work. If equipment is of a specialized nature, the lease may include
an equipment operator. No credit will be given for the cost of equipment leased
or rented from the Contractor.
DBEs shall negotiate cost, arrange for delivery, and pay for materials and
supplies required for their portion of the contract work. Invoices for materials shall
be invoiced to the DBE firm and not to the Contractor.
No credit shall be allowed toward the DBE goal for cost of materials placed by a
DBE subcontractor when payment is made by deducting this payment from the
Contractor's payment to the DBE.
Project engineers must document performance of the DBEs activity on all
Federal-aid projects as part of the normal project contract compliance
monitoring. On-site project monitoring by field personnel shall include employee
assignments, equipment used, and supervision of the work as indicated on the
subcontract form. The commercially useful functions shall be documented on the
DBE Commercially Useful Function Checklist (Form 517014) once per DBE per
contract. Even though this form is completed only once per DBE per contract, if
any irregularities are observed any time that DBE is working on a project, it
should be noted on Form 517014. All irregularities must be documented on
Form 517014, and immediately reported to the Contractor and the Administering
Bureau.
Attachment D to I.M. 6.000
June 12, 2024
Page 42 of 105
Project engineers shall not allow the Contractor or other subcontractors to
perform work that has been committed to a DBE subcontractor without prior
written approval from the Civil Rights Bureau.
In situations where a DBE subcontractor cannot (or is not) performing, the
Contractor must follow all steps described in the specifications. Upon receipt of a
signed statement from the DBE and documentation where the Contractor will
satisfy the goal with other items or DBEs, the Project Engineer may recommend
to the Civil Rights Bureau that the commitment be waived and the required goal
adjusted. The Civil Rights Bureau must provide written approval of all
substitutions before any changes in subcontracted work are performed.
D. Post Construction
The Contractor shall submit and electronically sign in Doc Express, a completed
Certification of DBE Accomplishment form (Form 102116) according to the Doc
Express
®
naming convention for all Federal-aid contracts and shall list the dollar
amounts paid to all DBE firms on the contract. This form certifies the dollar
amount paid to each DBE. If the contract had a DBE commitment, Project
Engineers must compare the dollar amounts on Form 102116 to dollar amounts
committed to DBE's as shown in the "DBE Commitment" document.
If the contract contained a DBE commitment, the Project Engineer will verify that
the Contractor has attained the DBE commitment specified to each DBE firm
listed on Form 102116. A price adjustment will be assessed for the amount of
commitment not paid to each DBE firm used unless the DBE commitment to that
DBE firm was reduced as allowed by Article 1102.17, G, 3, of the Standard
Specifications. The Project Engineer must include a written explanation
describing situations, background, and findings which resulted in reductions of
adjustments. This explanation shall be attached to Form 102116. The
Administering Bureau shall review these adjustments prior to signing Form
830436, Final Payment; or Form 640003, Certificate of Completion and Final
Acceptance of Agreement Work.
When the Contractor is a certified DBE contractor, Form 102116 is required to be
submitted upon completion of a Federal-aid contract. The DBE contractor shall
include the amount of work completed by their firm and DBE subcontractors. The
Project Engineer will sign the form acknowledging receipt of the form and does
not need to complete the amounts in the lower portion of the form.
Unique problems have been noted with the goals and variables of the DBE
program. Documentation of any activity related to the program is important and
must not be overlooked. Record all telephone or personal contacts noting time,
place, and details.
Subcontractor - Traffic Control
Traffic control items of a contract may require designation of a subcontractor to
perform the work depending on how much of the total item is performed. Some
guidelines are:
Attachment D to I.M. 6.000
June 12, 2024
Page 43 of 105
A. A Subcontract Request (Form 830231) will NOT be required if:
1. Traffic control is a lump sum bid item and the traffic control supplier:
Furnishes the traffic control devices
Delivers materials to the "first use" location
Keeps equipment operational by being on call from the Contractor
or through periodic visits to the site
Picks up devices when a project is completed
2. Traffic control signals are bid as furnish and install and the traffic control
supplier:
Furnishes the traffic control devices
Delivers materials to the "first use" location
Picks up devices when a project is completed
B. A Subcontract Request (Form 830231) shall be required if:
the traffic control supplier performs the entire item of traffic control (lump
sum, furnish and install) and provides regular surveillance, cleaning, routine
maintenance and repair of devices, or changes the system between stages.
The traffic control supplier performs contract work such as setting devices up
at the "first use" location
Traffic control is bid as incidental to other work
Prompt Payment to Subcontractors
Contractors are required to pay subcontractors for satisfactorily completed work
within 7 calendar days after receiving payment (or should have received payment)
from the Contracting Authority.
Certification of Subcontractor Payment
The Contractor shall submit and electronically sign in Doc Express, the Certification
of Subcontractor Payment form (Form 518002) according to the Doc Express
®
naming convention ahead of the signed final voucher. The form shall include the
names of all approved subcontractors. The Contractor shall provide an explanation
for instances that exceed 30 days.
The Certification of Subcontractor Payment form (Form 518002) is not required to be
submitted if there were no subcontractors on the contract.
2.26 USE OF PROPERTY OUTSIDE OF PROJECT RIGHT-OF-WAY
Any proposed use of property outside of the project right-of-way by the Contractor or any
subcontractor shall be submitted to the Project Engineer. Prior to any use of private
property, the Contractor shall provide the Project Engineer a copy of the written
agreement with the property owner that allows them access to the property and releases
the Contracting Authority of all liability.
Attachment D to I.M. 6.000
June 12, 2024
Page 44 of 105
2.27 "CONTRACT QUANTITY AGREEMENT" (FORM 830230)
The Contractor may request final payment for an item based on contract
quantities. When a contract quantity request is received from the Contractor, the Project
Engineer shall verify that items included on the request are not items to be paid as
contract quantity by Article 1109.01 of the Standard Specifications.
If there are contractual conflicts, i.e. the Contractor does not agree with the quantities in
the contract documents, these issues should be discussed at the Preconstruction
Meeting. The method of measurement for those items that may have conflict should be
identified at this time. For example, if the Contractor does not agree with the quantity of
Class 10 excavation on the contract, the Contractor can request the actual
measurements by providing written notice to the Contracting Authority. The preliminary
cross-sections and the balance points shown in the contract documents will be used as
the basis for payment of quantities. For further explanation of this example, see Article
2102.04, A, 1, c, of the Standard Specifications.
If there are no contractual conflicts, the Project Engineer will prepare a Contract Quantity
Agreement form (Form 830230) and upload it to Doc Express for it to the Contractor to
sign. After the Contractor signs the form, the Project Engineer shall sign.
2.28 RETAINED FUNDS
Retained funds held by the Contracting Authority are for the purpose of satisfying 573
Claims. The term, "573 Claim", originates from Chapter 573 of the Code of Iowa that
addresses claims on government contracts. Persons or companies may file a "573
Claim" with the Finance Bureau on Farm-to-Market funded projects, all others submit
with the Contracting Authority, for unpaid labor and/or materials.
Retained funds are not intended to offset credit payments for deficient work, including
price adjustments and liquidated damages.
When payment is needed to be withheld for price adjustments for deficiencies, item
progress should be withheld on the appropriate contract item(s) for the amount to be
withheld. Pay quantities for the Contractor items should be withheld to cover liquidated
damages. These items will be increased to the final quantities after a Change Order for
price adjustments and/or liquidated damages is processed.
Release of Retained Funds
For contracts let after January 1, 2007, Contractors are required to certify that they have
given notice to all subcontractors and suppliers of their intent to request early release of
retained funds. The notice must be provided 10 calendar days before the release of
contractor retainage is requested. Chapter 26 allows the Contractor to request release
of contractor retainage when the contract is substantially complete or after the contract is
certified complete by the Engineer.
The Contractor should initiate any request for release of contractor retainage. The
Project Engineer should not initiate release of contractor retainage.
Attachment D to I.M. 6.000
June 12, 2024
Page 45 of 105
Procedure and assigned responsibilities:
Contractor
Submit a signed Request for Early Release of Retained Funds form (see I.M.
6.000, Attachment G) in the Working Drawer in Doc Express.
The request shall include a sworn statement, signed by the Contractor, that the
notice was given to all subcontractors and material suppliers at least 10
calendar days prior to the date of the request. The "Request for Early Release
of Retained Funds" form shall be used (see I.M. 6.000, Attachment G).
Shall provide a statement to every subcontractor and material supplier that the
Contractor intends to request release of contractor retainage. In accordance
with Iowa Code the notice shall be similar to the following:
You are hereby notified that [name of Contractor] will be requesting an early
release of funds on a public improvement project or a highway, bridge, or
culvert project designated as [name of project] for which you have or may
have provided labor or materials. The request will be made pursuant to Iowa
Code section 26.13. The request may be filed with the [name of
governmental entity or department] after ten calendar days from the date of
this notice. The purpose of the request is to have [name of governmental
entity or department] release and pay funds for all work that has been
performed and charged to [name of governmental entity or department] as of
the date of this notice. This notice is provided in accordance with Iowa Code
section 26.13.
Project Engineer
Acting on the Contractor's request the Project Engineer will:
1. Confirm criteria have been satisfied, including receipt of the signed statement
from the Contractor.
2. Fill out center section of “Request for Early Release of Retained Funds” form
using markup feature in Doc Express. Contact Finance Bureau for Farm-to-
Market funded projects and the Contracting Authority for all other projects and
inquire if any claims are on file. If 573 Claims have been filed, retain twice the
amount of claims. If there are no claims, the entire amount of contractor
retainage is to be released except for $1.00 per project on the contract. This
$1.00 per project is required to be retained due to limitations in the Department’s
accounting system.
3. Sign Early Release of Retained Funds form (see I.M. 6.000, Attachment G) and
upload to the Project Closeout Drawer in Doc Express. The Contracting
Authority will release the appropriate amount of retainage.
4. Provide the Contractor a written explanation, within 30 days of their request, for
denying any amounts requested.
Attachment D to I.M. 6.000
June 12, 2024
Page 46 of 105
2.29 Intentionally left blank
2.30 CONSTRUCTION PERIOD
2.31 ADMINISTRATION OF THE CONTRACT PERIOD
Administration of any contract period and determination of the controlling item of work
requires a fair and equitable assessment of work performed (either working or calendar
days).
Article 1108.02 of the Standard Specifications identifies how a contract period is
identified in the contract documents and provides guidance for contract
administration.
Article 1108.03 of the Standard Specifications supplements by outlining working
days on non-Incentive/Disincentive (I/D) projects during holidays.
Section 1111 of the Standard Specifications provides direction for
Incentive/Disincentive projects.
Iowa DOT Construction Manual Appendix 2-27 shows "Charging of Contract
Time."
Contract Types
Three types of working day contracts are:
Approximate Start Date
Late Start Date
Specified Start Date
In addition, a contract may include an intermediate contract period for completing
certain phases of work. In all cases, the contract documents will identify a maximum
project duration, i.e., working days. Project durations, identifying the time allowed to
complete work, are used to calculate dollar amounts of liquidated damages and
incentive/disincentive assessments.
A. Approximate Start Date
It is expected that the site will be available by the approximate start date. If it
appears a project site may not be available by the expected start date, the
Project Engineer will notify the Contractor of a delay and, if possible, length of the
expected delay. Contractors are expected to remain informed about site
conditions and be prepared to start work with minimal delay when a site becomes
available.
An approximate start date is designated for the purpose of allowing the
Contractor some leeway in planning their work. The Contractor and Project
Engineer should work with the Contracting Authority to develop an agreed
starting date.
A Contractor may request to start work any time after execution of the contract
and before the approximate start date. This request is subject to approval by the
Project Engineer and the Contracting Authority. If approved, working days will be
charged when work is actually started. If approval is given, the Contractor will be
Attachment D to I.M. 6.000
June 12, 2024
Page 47 of 105
required to sign a waiver giving up any right to claim extra compensation for
damages due to delays related to their early commencement. If the Contractor
requests to start early, they shall not interfere with operations of other
Contractors who have first right to the site.
The guidelines for charging working days are explained in Article 1108.02 and
Article 1108.06 of the Standard Specifications and in the following case:
Frequently a paving contract is let following a grading or structure
contract which has not been completed when expected.
The policy on charging of working days in this situation is as follows: Whenever
paving operations are in progress, working days are charged when paving is
identified as the controlling operation, even though there may be a section of the
project that cannot be paved because of some uncompleted work. If paving
operations must be suspended or cannot start because of this uncompleted
work, charging of working days should also be suspended. The Contractor and
Project Engineer shall agree on a date for resuming paving operations.
The site is considered not available if the Contractor's operation would be
restricted or curtailed to the extent that production is reduced because of
insufficient or excluded areas. Examples of contracts often delayed are:
Bridges delayed due to uncompleted berms
Paving work delayed because of grading construction
Working days will be charged whenever the Contractor is working on the
controlling operation, whether before or after the approximate start date. A
"Notice to Proceed" shall be issued if the Project Engineer determines there are
sufficient reasons and available areas to expect the Contractor to be working. In
this case, the Project Engineer will contact the Contracting Authority and notify
the Contractor that the site is available and work should start. If the Contractor
does not start on or before the 15th day following a "Notice to Proceed," charging
of working days will begin on the 15th day.
Factors to be considered are amount of work available to the Contractor, safety,
other contracts, other work, opening the road to traffic, etc.
Examples of this type of contract are fencing or signing. In either case, the
Contractor will only be able to work as areas are completed and become
available. The Contractor may be expected to work in somewhat confined or
limited areas due to other Contractors or subcontractors on the site.
B. Late Start Date
When a contract includes a late start date, the Contractor may start work any
time after execution of the contract if permitted by specifications and weather. If
an early start is allowed, working days will be charged commencing when work is
actually started. Otherwise, working days will be charged starting on the late
start date.
Attachment D to I.M. 6.000
June 12, 2024
Page 48 of 105
Occasionally the Contractor will start a project, complete several items of work,
and then request that working days be suspended. The charging of working
days may be suspended only when the Contractor begins work on the project
before the late start date and with the approval of the Project Engineer. Project
suspensions should normally not be allowed after the late start date, unless the
project has been opened to traffic. See "Project Suspensions" that follows.
Example of an intermediate project suspension:
Usually the road will not be closed and construction work will be accomplished
while maintaining traffic. Before work is suspended, the road must be left in a
condition that is at least as safe as it was before the start of any preliminary
work. (Refer to "Project Suspensions" in the following section.) After suspending
work, a new late start date is calculated using the number of working days
remaining at the time of suspension. A statement indicating work is suspended
and the new late start date should be reported on the appropriate "Weekly Report
of Working Days." The charging of working days would be resumed starting on
the new date or when the Contractor resumes work, if earlier.
C. Specified Start Date
When a contract includes a specified start date, the Contractor can expect the
site to be available by the start date specified. The guidelines for charging
working days are covered in the applicable specifications. Starting work after the
specified start date, except as noted in the specifications, is unacceptable.
Therefore, the Contractor is expected to have a sufficient work force available to
start work not later than the specified date.
Working Day
A working day, as defined in Article 1101.03 of the Standard Specifications, assumes
that conditions are favorable for work to be performed on the controlling item (or
operation). Non-accelerated projects follow Standard Specification Section 1108.02
E, including the option to work on Saturdays with no time charged. Accelerated
projects are generally a mandatory 6-day work week and will include a proposal note
when required. Please refer to the proposal note for accelerated project specifics.
Generally speaking, if weather and specifications allow, a working day is defined as
any calendar day except:
Days with inclement weather, site conditions, or other conditions beyond the
Contractor's control, that prevent prosecution of the controlling item of work at
least 25% of the daily hours routinely worked.
Days where conditions identified in the contract documents require the
Contractor to suspend construction operations.
Non-accelerated Projects:
o Saturdays worked even when inspection is required.
o Saturdays, Sundays and days defined in Article 1108.03 of the
Standard Specifications for state observed holidays not
worked. (Refer to the note following this section.).
Accelerated Projects:
o Sundays and state observed holidays if not worked.
Attachment D to I.M. 6.000
June 12, 2024
Page 49 of 105
o Day preceding or following a state recognized holiday when the
preceding or following day falls on a Sunday (Refer to the note
following this section.)
Article 1108.02 of the Standard Specifications further refines this by charging 1/2 a
working day for construction activities that occur for less than 75%, but more than
50% of the daily hours routinely worked.
NOTE: With the exception of Sundays, it is not intended to automatically restrict
work on roadways where traffic volumes are not a concern. In fact, the Contractor
should be allowed to work on activities that can be accomplished with minimal impact
on traffic. The specification is intended to allow a Project Engineer work with the
Contracting Authority to approve (or deny) the Contractor's request to work on
normally excluded working days. Permission should be evaluated as to how the
proposed work impacts traffic - based on site experience, Contractor's operation, and
project schedule. Any decision to allow work during normally excluded times, shall
be pre-approved by the Contracting Authority on non-primary road projects. For
projects that impact a primary road the Administering Bureau must also pre-approve
the request.
Working days (reference the Iowa DOT Construction Manual Appendix 2-27) will be
charged when work actually begins on the contract, unless:
A. The Contractor does not start work on the Specified Start, or Late Start, date
required by the contract documents. In this case, working days will be charged
commencing with the date specified.
B. For Approximate Start date contracts, the Contractor does not start work on the
date agreed to at the preconstruction meeting. In this case, the Project Engineer
shall issue (or has already issued) a "Notice to Proceed." Working days will start
on the 15th day following a "Notice to Proceed," or when the Contractor starts,
whichever is earlier. (Refer to Article 1108.02 of the Standard Specifications).
C. The Contractor begins to work, or is working, during winter shutdown (November
15 to April 1) and:
working days remain for the contract, or
the contract does not require winter work.
Calendar Day
Calendar days are typically used on Incentive/Disincentive projects. As the name
implies, calendar days are every day shown on the calendar beginning at 12:01 AM
and ending at 12:00 midnight.
There is clarification for charging calendar days noted in Section 1111 of the
Standard Specifications. It states in part: Additional closure days for weather delays
will not be allowed for the first 5 consecutive closure days by adverse weather (i.e.
rain, snow, extreme heat, etc.). The specification identifies non-weather related
extraordinary circumstances which will be considered provided they cause a delay.
NOTE: Additional closure days have to be authorized by writing a "Substantial"
Change Order to the project.
Attachment D to I.M. 6.000
June 12, 2024
Page 50 of 105
Controlling Item of Work
The controlling item (or operation), as defined in Article 1101.03 of the Standard
Specifications, of work is: Work that is (or could be) in progress at any given period
of time, and would have the greatest influence on the duration of the contract.
Stated another way: at a given point in time, any task which has the greatest impact
on completing the project on time will be considered the controlling item of work.
There can be only one controlling item (or operation) of work at any given time. Also,
by definition: A controlling item (or operation) of work should change as the project
progresses from start to finish, and the item (or operation) need not be completed to
change. For example:
Placement of reinforcing steel may be a controlling operation at some point in
time. However, placing all reinforcing steel in a bridge need not be
completed before another operation such as placing structural concrete
would become controlling.
Fabrication and delivery of tower lighting poles may be a controlling item of
work. However, delivery of "all" towers and masts need not occur before
construction of tower bases or erection of some towers would become the
controlling operation.
Placing granular subbase is a task which obviously needs to occur prior to
placing pavement. However, once placing the subbase has advanced far
enough to stay ahead of placing pavement, the paving operation would
become controlling.
For contracts with a Critical Path Method (CPM) schedule, the controlling item (or
operation) is identified by its appearance on the critical path. For contracts without a
CPM, determining the controlling item (or operation) is not as straightforward and is
decided by the Project Engineer. In these cases, the Project Engineer should
include input from the Contractor and then decide:
What task is, or should be, in progress (at that time) to keep the project on
schedule?
What task (at that time) has the greatest influence on completing the project
on time?
Construction operations must be able to occur on the controlling item (or operation)
before a working day will be assessed. A working day will not be charged unless
work can be performed on the controlling item (or operation) of work, even if the
Contractor is working elsewhere on the project. Factors considered outside the
Contractor's control are:
A. Adverse weather which results in site inaccessibility or non-workability of
materials. Further, the Contractor will not be required to perform any task under
unsafe conditions resulting from (or during) adverse weather. Suspension of
working days is allowed only if the Contractor is working, or ready to work, on the
controlling item (or operation). In the event of adverse weather, working days will
not be charged during inclement weather, even if the Contractor has not
mobilized to the project.
Attachment D to I.M. 6.000
June 12, 2024
Page 51 of 105
B. Insufficient survey stakes, late acceptance or testing of materials, or lack of
inspection support could result in suspension of working days PROVIDED the
item in question is a controlling item (or operation) of work AND:
These delays were caused as a result of inaction by the Contracting
Authority. For example: Insufficient survey will not be a reason for
suspending working days, unless the Contracting Authority has not
provided adequate preliminary survey staking or there is a plan error.
The Contractor provided adequate advance notice indicating a specific
need. Timely notice and communication between all project team
members are of the utmost importance.
Note: There has to be a clear impact to completing the project on time before a
suspension, or additional contract days will be considered.
C. Strikes which are not directed against the Contractor. For example: A labor
strike against a material fabricator, after the project has started. Or a trucking
strike which at a minimum affects all transportation in a particular region where
materials or supplies must come from.
D. Legal stoppages are reason to suspend charging of contract time if they are a
result of legal action:
1. against the Contracting Authority, or
2. against the Contractor and are not based on a specification interpretation
or violation of the contract documents.
E. A controlling item (or operation) could be impacted for reasons such as:
Delays resulting from redesign or a plan revision
Redirecting traffic onto a project by State personnel due to some
unforeseen emergency
Awaiting contract pile lengths based on test pile results
Awaiting a preceding Contractor to complete their work
Delays associated with environmental problems
F. Late Delivery of Material. Procurement of material for a project is solely the
Contractor's responsibility. Contract time credits for late delivery will be
considered only when the Contractor documents:
Orders were placed with a reliable supplier, in sufficient time for materials
to be delivered on schedule.
The supplier has made a reasonable attempt to secure equal materials
elsewhere within the industry.
A supplier has the capability and ability to provide materials at the rate
promised.
Attachment D to I.M. 6.000
June 12, 2024
Page 52 of 105
Contract time credits (working or calendar days) may be allowed for the
difference between promised and actual delivery dates. However, the promised
delivery date must have been realistic, acceptable, and fully documented to the
satisfaction of the Project Engineer. Time credits could be allowed for late
delivery if the problem developed after a project was let because of:
An area or nationwide shortage of the material.
A natural disaster.
An industry wide strike.
Transportation strike which delays the delivery of material.
Delays due to a change in material commitments when caused by a
federal emergency or order.
Delays due to specially fabricated material which are damaged during
shipment to the project.
G. Redoing work that had been completed, but was damaged or destroyed for
reasons beyond the Contractor's control. For example: A grading Contractor is
working on a project and rain occurs. The Contractor starts back to work and
has to disk previously placed material to dry it out. Working days should not be
charged until the site is back to "reasonably" the same condition it was prior to
the rain. (Note: Drying borrow material, after a rain, would also be included in
this scenario.)
RATIONALE: If the Contractor is willing to place special "early" effort into a
project, or if the Contractor has to redo work which was damaged, the intent is
not to penalize that effort by charging contract time until the site is back to its
"original" condition.
Obviously, an alternate would be for the Contractor to wait until site conditions
are perfect and then resume work. This is not beneficial to either the Contracting
Authority or the Contractor.
H. Change Orders and plan revisions could affect the controlling operation. Impacts
on time should be considered for extra work and plan revisions and addressed
when the impact is known. A Change Order for additional time may be executed
when the impacts are quantified. For projects with a CPM schedule, simply
providing an updated schedule, without substantiating information detailing
changes, will be inadequate for a comprehensive review.
For large overruns, the magnitude and impact may not be readily known until the
final quantities have been determined. In such situations, relative information
should be included as notes on the Working Day Report.
I. Natural Disasters are typically a result of storms which produce catastrophic
results and supersede "adverse weather" described in "A" above. In Iowa, the
Governor's office issues disaster proclamations.
A suspension order may be issued on any project in a declared disaster
area. After consulting with the PIRC, recommendations for a disaster
suspension will be initiated by the Project Engineer, sent to the Administering
Bureau for final approval. Disaster suspensions will be considered for projects
Attachment D to I.M. 6.000
June 12, 2024
Page 53 of 105
regardless of the Contractor's working status, i.e., actively working or not yet
mobilized to the site. Time credits could also be considered for damages to plant
facilities, equipment, supplies, partially completed work, and completed work
which must be redone.
J. The Weekly Working Day Report form (Form 830238) or, alternatively, the Appia
Time Limits Report, becomes a very important document in providing a historic
record of events. This form should include notes about delays and other
pertinent information that can be used later to assist in resolving disputes that
may arise.
Special Considerations
A. Adjusting Liquidated Damages
Assignment of working days is based on the estimated value of the contract
costs as found in Table for Proposal Guaranty and Liquidated Damages per Day
in the Iowa DOT Letting Guidelines. Any adjustments to Working Days, when
calculating Liquidated Damages, should be based on costs accrued due to
administration costs, user costs from either delays of the project or out of
distance travel to get around the project should also be considered (see Section
10. Liquidated Damages in the Iowa DOT Letting Guidelines.)
Article 1108.09 of the Standard Specifications states in part that the Contracting
Authority may waive additional liquidated damages which accrue after the work is
in a condition for safe and convenient use by all modes of the traveling public,
including but not limited to vehicular, bicycle and pedestrian traffic. This
specification also identifies conditions which must be met before considering any
credit.
Further, the Contractor would be expected to retain or obtain sufficient equipment
and work force necessary to complete the remaining work within a reasonable
time. Normally 30 calendar days would be considered adequate time to allow for
completing minor work under this provision. One method for administering
working days on projects that are substantially completed with only clean-up /
Punch List items remaining to be completed (typically in the following spring) is to
advise the Contractor that charging of working days will resume in 31 days. This
allows the Contractor to complete the project with no working days for clean-up
work if it is completed with the 30-day period.
B. Winter Work
Determination of contract days (working or calendar days) charged during winter
shut down (November 15 through April 1) will be according to Article 1108.02 of
the Standard Specifications and Section 1111 of the Standard Specifications,
and the contract proposal. Unless otherwise noted, contract proposals allow the
Contractor to work between November 15 and April 1 with no time charged.
Regardless of whether working days are charged, Working Day Reports are to
be issued whenever the Contractor is working on the project. The reports provide
documentation of project status and the Contractor’s progress.
Attachment D to I.M. 6.000
June 12, 2024
Page 54 of 105
However, a contract period ends when the Contractor has used all the specified
number of working days. Therefore, if the Contractor has used all allowed
working days and has not completed the project and continues (or is required) to
work after November 15, working days will be charged.
This could also apply on intermediate completion dates. If all specified working
days for an intermediate completion are used, but contract time remains for
completing the project and the Contractor continues (or is required) to work after
November 15, working days would be charged until the intermediate completion
work is completed. But, charging working days would then be suspended until
April 1.
The two situations above assume work can be completed sometime after
November 15. This is not always the case. Anytime working days are charged
during winter free time because of uncompleted work, the Contractor will be
required to work as long as conditions are favorable for work to occur. At the
point where weather and/or site conditions prohibit acceptable constructive work
to continue, a suspension will be issued and work will be commenced at the first
opportunity in the spring.
The Project Engineer may require the Contractor to place temporary materials
prior to a suspension in the following situations:
A project (or a required intermediate portion) is not completed within the
allowed contract time, and
work continues (or is required) after November 15, and
due to weather conditions, work cannot be completed.
Typically, temporary materials will be required for safety or soil erosion
considerations. All temporary materials shall be furnished, placed, and removed
if required prior to start-up at the Contractor's expense.
If the Contractor wishes to start work prior to April 1 and the contract proposal
allows winter free time, the Contractor is required to request authorization to
commence work prior to April 1. If the Project Engineer and the Contracting
Authority approve the request, a condition shall be imposed that the Contractor is
not entitled to compensation for delays when not able to work during the winter
free period. This condition shall also be used when the Contractor submits a
CPM schedule indicating work performed prior to the contract period.
C. Project Suspensions
The Project Engineer and Contracting Authority may approve a suspension when
either of the following two conditions is met:
when the Contractor starts work prior to the late start date
when a project is substantially completed
However, if it is apparent the intended suspension would make it impossible for
the Contractor to complete the project within the intended construction season,
Attachment D to I.M. 6.000
June 12, 2024
Page 55 of 105
the Contractor will be advised that suspension of work will not be approved and
charging of working days will continue.
If it is necessary, or required, that the road be closed to traffic because of the
preliminary work, a suspension will not be allowed and working days will be
charged unless there are extenuating circumstances or situations.
Charging of working days may be suspended on substantially completed
contracts when only clean-up of the project site and/or completion of minor work
remains. The specification that provides for this allowance depends on whether
liquidated damages have accrued at the time of suspension.
For contracts that have not accrued liquidated damages at the time of
suspension, Article 1108.06 of the Standard Specifications, "Temporary
Suspension of Work" is to be followed and working days will not be charged
when the following conditions are met:
Only minor work or clean-up of the project remains to be completed
The Contractor submits to the Project Engineer a written request for
suspension of work and a schedule for satisfactory completion of the
work.
If approved, the Project Engineer will notify the Contractor that working days will
be suspended. This may be accomplished by the Project Engineer noting on the
weekly working day report that charging of working days is suspended. If the
request is not approved, the Project Engineer must advise the Contractor in
writing of the reasons the suspension is denied. The Contractor should be
provided with a response to their request in a timely manner.
It is important to note that this procedure is not intended to allow a suspension for
an indefinite period of time without a planned and approved schedule for
completing the work. The Project Engineer may resume working day charges
when the approved suspension expires if the Contractor fails to complete the
work in accordance with the schedule submitted with the request for suspension.
On contracts that have exceeded the allowable number of working days allowed
and are accruing liquidated damages, Article 1108.09 of the Standard
Specifications, "Failure to Complete Work Within Contract Period" is to be
followed. In this case, working days should not be charged when the following
conditions are met:
Traffic must have complete use of the roadway, shoulder to shoulder, with
no delays or one-way traffic and no obstructions except for signs warning
of construction work ahead.
The remaining work to be completed is confined to the areas outside the
shoulder edge.
Only minor work is left for completion such as clean-up or erosion control
work if it is a small item, not part of an erosion control contract, and the
erosion control work is completed during the first available seeding
period.
Attachment D to I.M. 6.000
June 12, 2024
Page 56 of 105
The remaining work is completed without excessive delay on the part of
the Contractor.
D. Projects Behind Schedule
Typically, bar charts and Critical Path Method (CPM) schedules have been used
as a means of relating construction progress versus time for various types of
construction projects. The Project Engineer will monitor progress by using these
schedules and the "Weekly Report of Working Days."
No mandatory acceleration action is required of the Contractor unless a project is
10%, or more, behind schedule. If the Contractor is more than 10% behind and
an accelerated work schedule is expected, there should be no additional costs
passed on to the Contracting Authority for any costs borne by the Contractor due
to the requirement of the accelerated work schedule.
10% Behind Schedule
When the Contractor is 10% or more behind schedule, the Contracting
Authority may issue a notice as provided in Article 1108.02, I, of the
Standard Specifications. Further action may be taken if it appears that
the rate of progress is such that the contract will not be completed within
the allowed time. Ten percent behind schedule may warrant written or
verbal assurances from the Contractor of what they will do to bring the
project back on schedule.
20% Behind Schedule
When the Contractor is 20% (or more) behind schedule, and it appears
that completing the project on time is in jeopardy, the Contracting
Authority (working with the Administering Bureau) will recommend actions
described in Articles 1102.03, 1103.01, B, and may take further action
described in Article 1108.02, I, of the Standard Specifications.
A letter to the Contractor will be required when a project is more than
20% behind schedule. This letter should reiterate the Contractor's
obligation to expedite the work and remind them of the various provisions
of Article 1103.01, B, and Article 1108.02, I, of the Standard
Specifications. The letter should also request a reply from the Contractor
on steps which will be implemented to improve work progress within the
next two weeks, and to ultimately have the project completed on time.
The Administering Bureau should be notified at the end of 14 additional working
days if:
the Contractor has failed to respond to the letter, and/or
the Contractor has not taken positive, measurable actions to improve
project deficiencies.
2.32 NOTICE TO PROCEED
Historically, the Notice to Proceed form (Form 830237) has not been widely used due in
part to good coordination efforts and communication skills of project team members and
Attachment D to I.M. 6.000
June 12, 2024
Page 57 of 105
use of the executed contract as the notice that the Contractor may begin work. The form
was developed for Approximate Start Date contracts (where there is no specified starting
date on the contract) to formalize Contractor notification relative to a project start
date. However, the form may be used for any special situation needing a formal time
notice not imposed by the contract documents.
Generally, formal notification is not necessary if:
A start date has been agreed to at the preconstruction meeting and the agreed
date is recorded in the minutes. These minutes must then be distributed to all
participants including the Contractor. A week will be allowed for comments and
revisions. After that time, the minutes become documentation of agreements
made during the meeting.
The Contractor has started work prior to the critical time for issuing a Notice to
Proceed.
An early work waiver has been approved.
If the Contractor does not appear to be ready to start on the agreed date, or project
conditions warrant an earlier start date, the Project Engineer may issue a Notice to
Proceed form (Form 830237). Examples of these cases are:
The Contractor agreed at the preconstruction meeting to mobilize and begin work
on the second week in July. It is now the first week in July, the Project Engineer
has been unable to reaffirm the start date or the Project Engineer has reason to
believe the Contractor has no intention of starting as agreed.
Assume: There is a contract for an HMA overlay. This contract includes some
patching with an approximate start date of June 1. At the preconstruction
meeting, the Contractor noted they would mobilize and begin patching work on
July 15. Sometime after the preconstruction meeting, but before the Contractor
starts to work, the Project Engineer or Contracting Authority becomes aware that
the roadway in question is experiencing rapid deterioration and patching must
begin earlier, say mid-June. In this case, the Notice to Proceed form could be
used to require the Contractor to begin work.
NOTE: Cannot "mandate” the Contractor to begin work prior to the approximate
start date. If the Contractor is agreeable and the site is ready, work can begin
before that date but forcing the Contractor to start early could result in the
potential for an acceleration claim.
In either case the Contractor should be contacted to discuss relevant issues and
attempts made to redefine a new start date. However in the absence of an agreement,
or if the Contractor is not amenable to starting work as needed, the Contracting Authority
should issue a Notice to Proceed form (Form 830237).
NOTE:
1. In the absence of an agreement, the Notice to Proceed form must be issued
before working days can be charged.
2. A starting date in the Notice to Proceed must not be less than 15 calendar days
after date of issuance.
Attachment D to I.M. 6.000
June 12, 2024
Page 58 of 105
3. Working days will be charged beginning on the 15th calendar day after the Date
Issued on the Notice to Proceed, or when the Contractor begins work, whichever
comes first.
2.33 WEEKLY REPORT OF WORKING DAYS
The Weekly Report of Working Days (working day report) form (Form 830238) is an
Iowa DOT form used to document time charged versus actual work completed. Two
forms currently used for reporting of time charges are:
The Weekly Report of Working Days form (Form 830238) is the standard form
used for all construction and/or maintenance contracts.
Incentive/Disincentive contracts require charging of calendar days during critical
closure periods and should use the Weekly Report of Working Days for
Incentive/Disincentive Clause form (Form 830241).
Except for tracking Critical Closure Days, the forms look about the same and their
preparation is similar.
If using Appia, the Time Limits Report within the Appia application should be used
instead of the Weekly Report of Working Days (working day report) referenced above.
Form 830241 will still need to be used for critical closure periods within a working day
contract.
Instructions for completing the Appia Time Limits Report can be found in the Appia
“Under Construction Instructions” on the Local Systems website. Use the methodologies
explained below for Form 830238 to determine how and when days should be charged
and the appropriate reporting of multiple site times.
During the contract period, the Project Engineer will prepare and upload into Doc
Express each week a Weekly Report of Working Days form (Form 830238 or Appia
Time Charge) showing working days charged that week.
The Contractor’s objections to days charged must be submitted in writing to the Project
Engineer within 10 calendar days from the date uploaded into Doc Express. Engineer
will upload the objection as a supporting document into Doc Express. Response to the
objection, indicating acceptance of the claim or reasons for rejection, will also be
uploaded into Doc Express. Objection correspondence shall be completed through
email, and the entire email chain showing the resolution shall be uploaded to Doc
Express as a supporting document to the disputed report. If circumstances beyond
control don’t allow for timely resolution of the day charges, objections can be
documented and resolved at a later date.
Preparation of Form 830238
The form is divided into two basic sections, one for reporting working days used and
the other for reporting work progress. Instructions for preparation are as follows:
1. Late/Approx. Starting Date
Attachment D to I.M. 6.000
June 12, 2024
Page 59 of 105
If an approximate start date is designated, enter that date. If a specified start or
late start date is designated, that date is entered and the abbreviation "Approx."
is crossed out.
2. Length of Project
Enter the length of the project in miles, if applicable. Note: Bridge, culvert, and
other site specific projects need not be included in this section.
3. Type of Work
Enter the type of work such as PCC paving, HMA resurfacing, shoulder
stabilization, structures, etc. For structures, (bridge or culverts) enter the
individual design number(s).
4. Days of Week
For reporting contract time, a day starts at 12:01 AM and ends at 12:00 midnight.
5. Controlling Operation
During the contract period, list the controlling item (or operation). If work is not
progressing on the controlling item (or operation), note controlling item in
appropriate column and actual work item in the "Remarks" column.
When work is stopped or suspended and working days are not charged, the
reason for not charging time should be noted under "explanation of delays."
When the Contractor is not working and working days are being charged, give
the reason why there is no work in progress, if known. For example, under
"Explanation of Delays" and/or "Remarks" note something like: Waiting for
subcontractor to mobilize.
6. Working Days Charged
If conditions allow work on the controlling item (or operation) of work, tabulate
time charged for that day. (Refer to the Iowa DOT Construction Manual
Appendix 2-27 for charging of contract time.) Listed values will be either 1/2 or 1
for days where conditions allow work on the controlling item and 0 (zero) if days
are not charged.
Refer to Section 2.34 of this Attachment for adjustment of time charged.
7. Work Progress
Three blanks are provided for major items or phases of construction. Items
entered in this section are intended to provide a "quick reference" of progress for
various major items. Since working day reports are continuous, it is easy to look
back in a file to glean relevant data. Thus, it is preferable to allow a project
inspector the flexibility to include various major phases rather than rigidly
Attachment D to I.M. 6.000
June 12, 2024
Page 60 of 105
adhering to 3 items for an entire project. In so doing, anyone looking
retrospectively can obtain a quick mental reference as to major work in progress
at any given time. For example:
On report #6 an inspector included Pier 2, North Abutment, and South
Slope Protection.
On report #7 the list changed to Piling, Pier 3 Footing, and Reinforcing
Steel.
On report #8 the list reverted back to report #6's items.
Report Number
Type of Work
% Complete
6
Pier 2
40
North Abutment
60
S. Slope Protection
20
7
Piling (Furnish & Drive)
90
Pier 3 Footing
10
Reinforcing Steel
30
8
Pier 2
70
North Abutment
95
S. Slope Protection
100
Such reporting may seem nonsensical; however, individuals using this report
often need "quick" historical data that is unavailable elsewhere.
8. Percent Complete
Blanks are on the form for entering percent of the total contract completed, and
percent of time used. All the percentages need only be approximate
calculations, rounded to the nearest 1%. When the rate of progress on a project
is behind schedule to the extent that there is danger work will not be completed
on time, note such situations on the "Weekly Report of Working Days."
Preparation of Incentive/Disincentive Form
As noted above, the Weekly Report of Working Days for Incentive/Disincentive
Clause form (Form 830241) for projects specifying incentives and/or disincentives
(I/D). This form tracks both working and calendar days on the same form.
Preparation of Form 830241 for incentive/disincentive is generally the same as for
Weekly Report of Working Days form (Form 830238) except:
1. Under "Controlling Operation" there are two columns, one for CPM and the other
for “Actual”. When charging contract time (working or calendar days), complete
the CPM controlling column. An entry in both columns would be appropriate to
document when the Contractor is working, but not working on the CPM
controlling item (or operation) identified by a CPM.
NOTE: CPM schedules show a critical path. Any item (or operation) on this path
is, by definition, a controlling item (or operation).
Attachment D to I.M. 6.000
June 12, 2024
Page 61 of 105
2. Columns headed "Working Days Charged" or "Critical Closure Days Charged"
days are self-explanatory. NOTE: Working days are assessed when site
conditions permit work on the controlling item (or operation) during noncritical
closure time(s), and calendar days are charged every day during critical closure
time(s).
Multiple Sites on a Contract
A contract may consist of multiple "sites" in addition to the overall contract, which is
known as Site 00. Multiple sites are used when smaller specific portions of the
contract are required to be completed in a time frame that is different than the overall
contract. The site numbers, site description, start date, and time allowed are
described in the "Proposal Details."
Multiple site contracts include:
Contracts with intermediate completion periods. Example: a grading contract
with intermediate completion periods for completion of bridge berms.
Multi-project contracts. Example: a contract consisting of more than one
project.
For multiple site contracts, working days for each site, including the overall contract
(Site 00), will be administered independently based on the controlling operation for
the site. A working day will be charged to a site when work is done on the controlling
item of that site.
An example of a proposal that includes multiple sites:
The overall grading contract (Site 00 with 120 working days allowed)
A hot mix asphalt paving project (Site 01 with 90 working days allowed)
An intermediate completion period for constructing a bridge berm (Site 02
with 50 working days allowed)
A RCB culvert project (Site 03 with 30 working days allowed)
A typical scenario may be that, due to wet weather, conditions allow work on
controlling operations of Sites 01 and 03, but not on Site 00 or 02. In this example,
time would be charged to sites 01 and 03, but not to the overall contract (Site 00) or
Site 02.
Occasionally a proposal will include an intermediate construction period, have a
liquidated damage clause, and a statement which paraphrasing states: Liquidated
damages will not be charged for work prior to (XXX date) regardless of working days
used. In this case, the "XXX date" will be the date (typically approximate start date)
for a following contract. Use of this clause is intended to allow the Contractor
flexibility and latitude in their schedule, while fixing a point in time that a future
Contractor can reasonably assume a site will be available. If the first Contractor
does not meet that date, liquidated damages will be assessed because a future
Contractor/contract is impacted.
Attachment D to I.M. 6.000
June 12, 2024
Page 62 of 105
When intermediate construction period requirements have been met, the "Remarks"
section on the Weekly Report of Working Days form (Form 830238) should be noted
with "final" and:
1. Date intermediate work was complete or when contract requirements were met.
2. Total contract time charged to an intermediate construction phase of the work.
3. Total contract time charged in excess of the number of days specified, if an
intermediate construction date is not completed on time.
2.34 LIQUIDATED DAMAGES AND EXTENSION OF CONTRACT TIME
If the number of allowable working days is exceeded and it is later determined that
previously charged days should not have been charged, the length of the contract period
is to be extended. The number of allowable days is increased by processing a time
extension modification to the contract.
Retained funds held by the Contracting Authority are not intended to offset credit
payments for deficient work and/or liquidated damages.
When liquidated damages, as defined in Weekly Report of Working Days form (Form
830238) or Appia Time Limits Report, are anticipated, item progress of the Contractor’s
items shall be withheld to cover liquidated damages. These items will be increased to
the final quantities after a Change Order for liquidated damages is processed.
Working day disputes should be resolved in a timely manner and not deferred to the end
of a project. If initial negotiations between the Contracting Authority and the Contractor
fail to resolve differences, the Project Engineer shall request negotiation assistance from
the Administering Bureau.
Should combined efforts described above fail to resolve dispute(s), the issue will be
considered to have reached an impasse. At this point, a meeting with all affected parties
shall be scheduled by the Administering Bureau.
If liquidated damages remain after considering possible working day credits or time
extensions, a Change Order is to be written. The amount of liquidated damages shall be
written as a non-substantial credit Change Order using the item number 6200-1108010.
The Administering Bureau will not process a Final Voucher until all liquidated damage
claims are settled.
For projects where construction engineering is Federal-aid funded, the Change Order for
Liquidated Damages should be marked under the “Participating” “Federal-aid” column.
For projects that are State funded, the Change Orders for Liquated Damages should be
marked under the “Participating” “State-aid” column. For all other situations, Liquidated
Damages are non-participating so no marks should be made in either column under
“Participating”. However, it is required to note in the Justification for Costs that “the LDs
on this project do not exceed the construction engineering costs.”
Attachment D to I.M. 6.000
June 12, 2024
Page 63 of 105
2.35 EQUIPMENT RENTAL RATES
On construction projects, unanticipated costs for equipment can arise as a result of work
that was unforeseen at the time a contract was awarded. Such unforeseen work is often
necessary in order to complete a project. Data on actual costs for equipment used for
such additional, unanticipated work is usually not available, primarily because it is
difficult to separate equipment costs from items bid in the contract
documents. Preferably the Project Engineer and Contractor successfully negotiate a
price that is agreed to by the Contracting Authority and concurred by the Administering
Bureau for unanticipated work and execute a Change Order to the contract. In
formulating the costs for such Change Orders, Article 1109.03, B, of the Standard
Specifications allows the Contractor to use EquipmentWatch’s Cost Recovery Rates
(formerly Rental Rate Blue Book) rate guides or actual lease invoices to calculate
equipment costs. If using Appia, equipment usage can be tracked and documented in
the Daily Report feature.
EquipmentWatch Cost Recovery
EquipmentWatch Cost Recover is a recognized standard rate guide which can be used
to determine rental, ownership and operating rates to be reimbursed to the contractor in
force account work, and to substantiate equipment costs for agreed price work.
Typically, this method of determining rental costs is used when a contractor owns, or has
a long term lease for any equipment in question, but does not have an established rental
cost per unit of time. EquipmentWatch updates all of these rates annually.
EquipmentWatch Cost Recovery rates are available on the EquipmentWatch website at
https://equipmentwatch.com/.
One of the greatest challenges in determining costs is finding a particular piece of
equipment. It is important that Contractors provide complete, definitive, information
relative to a particular piece of equipment, i.e., manufacturer, model number, type, size,
horsepower, bucket or box capacity, equipment weights, and age. While the
EquipmentWatch Cost Recovery database includes a vast array of heavy equipment
models that are currently in the market, there may be particular models or types of
equipment not included in the guide due to a lack of data. In the event that a piece of
equipment is not found in the Cost Recovery product, contact EquipmentWatch
customer service or your account executive in order to receive custom ownership and
operating rates from the EquipmentWatch analyst team.
In order to determine accurate equipment costs, several adjustment factors must first be
applied. Local Systems provides an annual schedule of basic equipment rates for use by
cities and counties for preparing their budgets, which can be found here:
https://iowadot.gov/local_systems/Equipment-Rates
A. Regional Adjustment Factor
To make a regional adjustment in the Cost Recovery product you can simply choose
‘Iowa’ from the location drop down menu or by selecting ‘Iowa DOT’ from the
organization drop down menu. Selecting either of these options will automatically
apply the correct regional adjustment for the cost recovery rates.
Attachment D to I.M. 6.000
June 12, 2024
Page 64 of 105
B. Model Year Adjustment Factor
Equipment rate listings contain allowances for depreciation and replacement costs.
FHWA has ruled that equipment costs are not eligible for reimbursement unless the
rate has been adjusted to eliminate depreciation and replacement costs. Therefore,
Iowa DOT policy will be to apply a model year adjustment to both federal aid and
non-federal aid projects. To apply the model year adjustment simply select the
correct model year from the drop down menu and the equipment costs will
automatically be adjusted.
C. Rate Element Adjustment (Indirect Cost)
Care needs to be exercised when applying equipment rates to avoid cost duplication.
Specification 1109.03B states: “No profit percentage shall be added to the rental
rate”. This is because equipment rates published in the Cost Recovery product
include indirect costs, i.e. some overhead, insurance, taxes, licenses, office support,
etc. Since specifications do not allow adding profit, the potential for duplication is
eliminated and there is no need to use a factor for removing the indirect costs. This
means pay what the previously noted adjustments amount to in equipment costs, but
no more.
When performing a search for a particular piece of equipment in EquipmentWatch, the
above factors will automatically be applied as one walks through the search process
including selection of a manufacturer, model, model year, configuration, etc. However, it
is important to verify that the adjustments have been made before finalizing an
acceptable cost.
Invoiced Rental Costs
There are times where the Contractor will obtain needed special or extra equipment at a
rental facility. The Contracting Authority reimburses rental costs for providing equipment
and highly specialized attachments, equipment operating costs, and costs for an
operator, and if necessary equipment support crew. Care needs to be exercised in
checking how a rental arrangement is written. Sometimes operators are furnished in a
rental agreement. In that case, the operator and/or support crew have to be removed
from equipment rates and included on the force account form as hourly labor.
Equipment Time Charges
Charging equipment project time will be as follows:
A. Equipment on the Project
This can be equipment on the project that is owned, leased, or rented by the
Contractor. Rental time is charged when the equipment is physically working at
the extra work site. Standby time will not be allowed for rental equipment which
was on the project (prior to extra work) for work required by the
contract. Further, rental time will not be charged when equipment is not working,
no longer needed for the extra work, or not on the extra work site.
Attachment D to I.M. 6.000
June 12, 2024
Page 65 of 105
B. Equipment not on the Project
This can be equipment that is owned, leased, or rented by the Contractor and is
mobilized to the extra work site specifically for extra work. Rental time is charged
when the equipment is working or is on standby available for work. Rental or
standby time will not be charged when the equipment is no longer needed for
extra work or not on the extra work site.
C. Standby Time
Standby time is that time a piece of equipment is at the extra work site, fully
functional, and available for work. The use of a standby rate is appropriate when
equipment has been ordered to be available for force account work but is idle for
reasons which are not the fault of the Contractor.
Standby time will not be charged for:
nonworking hours
nonworking days (calendar or working days)
D. Set-up Time
Often equipment transported to a work site will have to be assembled (set up)
prior to being fully functional and available for work. Set-up time will be charged
(on a working day basis) after off-loading the equipment from a transporting
vehicle and continue until it is assembled and available for work.
Chargeable Project Costs
As previously noted, rental rates apply to equipment rented or leased for specific
extra work items. Equipment often requires highly specialized (not common)
attachments to functionally perform the work needed. Rental rates for these
attachments will be calculated in the same manner as if they were a separate piece
of equipment. Example: A dozer blade would not be considered a specialized
attachment for a dozer. However, a special rock ripper for a dozer or a drill table for
a crane (used to install drilled shafts) would be considered specialized attachments.
A. EquipmentWatch Cost Recovery
The formula to calculate hourly equipment rate is:
EQUATION 1: W = RR x RF x RA + HO
HA
Where:
W = Hourly Equipment Rate (reported as $ per hour)
RR = Equipment Rate (Use listed monthly rates)
RF = Regional Factor (found in the front of each section)
RA = Rate Adjustment Factor (found in the front of each section)
HO = Hourly Operational Cost (as listed for each piece)
HA = Hourly Adjustment (HA = 176, converts monthly to hourly)
Attachment D to I.M. 6.000
June 12, 2024
Page 66 of 105
Project cost is the hourly equipment rental rate (W), calculated above, and
multiplied by the number of hours charged for that piece during the project. This
value is combined with any other extra work equipment costs and entered in the
"Equipment" column on a Statement of Force Account. NOTE: Operator wages
will be included with other "labor" costs on the Force Account sheet.
B. Standby Costs
Standby rates are calculated as 50% of rental rates, excluding operating
costs. Using the EquipmentWatch Cost Recovery, standby rates are calculated
as follows:
EQUATION 2
Y = RR x RF x RA x 0.50
HA
Where:
Y = Hourly Equipment Stand-by Rate (reported as $ per hour)
RR = Rental Rate (Use listed monthly rates)
RF = Regional Factor (found in the front of each section)
RA = Rate Adjustment Factor (found in the front of each section)
HA = Hourly Adjustment (HA = 176, converts monthly to hourly)
C. Set-up Costs
Project set-up costs will be calculated and charged as standby time. (Refer to
"B" above, and section "D" of Equipment Time Charges.)
D. Mobilization Costs
1. Mobilization and demobilization charges will not be allowed for equipment
which was at the project for ongoing operations prior to the extra work.
2. Contractor owned (or long term leased) equipment which is brought to the
extra work site from another project, or the Contractor's yard, will have
mobilization costs reimbursed based on hauling time to the project. Rental
rates as calculated in Equation Number 1, times the hauling time will be
applied for mobilization costs.
NOTE: Only equipment needed for the extra work and not already on the
project will be considered for mobilization reimbursement. Demobilization
time (or costs) will not be included for payment.
3. Equipment leased specifically for extra work and transported by the
Contractor will have mobilization time reimbursed as outlined in D. 2.
above. Demobilization time (or costs) will not be included for payment.
4. Equipment leased specifically for extra work which is transported by the
lessor, or a third party, will be reimbursed on an invoiced basis.
Demobilization costs will be reimbursed if the equipment is returned to a
lessor's yard.
Attachment D to I.M. 6.000
June 12, 2024
Page 67 of 105
Statement of Force Account Form (Form 181213)
The Statement of Force Account form (Form 181213) completed and signed by the
Contractor and project inspector at the end of each day document hours charged to
equipment for that day. After the ordered extra work has been completed, total
hours charged for equipment can be combined and tabulated on a summary force
account sheet.
2.36 CHANGE ORDERS (FORM 831240 or Appia Change Order)
A Change Order is a written order to the Contractor for:
Changing the authorized quantity of a contract item. This includes increases or
decreases to contract quantities.
Adding a new item or material to an existing contract. Often this is a result of
plan revisions or a change in scope from what was originally envisioned at time
of letting.
A source document for the Finance Bureau to enter changes and additions into
the Contractor Pay System or for the Contracting Authority to authorize extra
work or changes in item quantities. Ultimate results of this endeavor are
changes to items, or additional items, appearing on a Progress Voucher or Pay
Estimate.
Officially documenting changes to the contract documents. Change Orders are
written orders to the Contractor (or consultant) which are initiated and prepared
by the Project Engineer. Once signed by all parties, these orders become legally
binding contract documents ordering a specific change to the original contract.
Policy for Change Orders
A. Contractor Markup
Subcontracted Items. Items added to a contract, and performed by a
subcontractor, entitle the Contractor an allowance to cover administration
expenses. An exception would be wholly owned subsidiaries when working as a
subcontractor for their parent company. Prime contractor markup would not be
applicable in that case. This markup is not to apply to incentive payments,
specified items covered by specifications, or items for which predetermined unit
prices have been established. The percentage allowed per Article 1109.03, B, of
the Standard Specifications is to be applied to each individual item of extra work
which is performed by a subcontractor. The amount of mark-up shall be included
in the unit price and not as a separate item such as "Contractor's Mark-up”.
Contract Unit Price. Change Orders covering overrun/underrun of items at
contract unit price are NOT eligible for any additive. This includes work which
was done by a subcontractor. The contract unit price should have already
considered any necessary additives for administrative expenses.
A Contractor may request a price adjustment to recover lost administration
expense for underruns amounting to more than 25% of the bid amount for a
major item of work. A Contractor is allowed to recover that portion of lost
Attachment D to I.M. 6.000
June 12, 2024
Page 68 of 105
administration expense represented by the difference between the actual
quantity and 75% of the original contract quantity.
Price adjustment may be made to reduce the cost of major items of work which
overrun by more than 25%, since the Contractor should have already included
overhead expenses in their bid. Overrun price adjustments apply to only that
portion/quantity which is more than 125%.
Agreed Unit Price. Change Orders, based on an agreed unit price, or lump
sum, shall have overhead considered as a part of the negotiation. The agreed
unit price may include the cost of overhead for handling subcontracted items. It
may be included in lump sum items if justified. However, if negotiations
specifically excluded markup, the item may be shown as a separate entry on a
cost workup sheet.
Force Account. Specified force account percentages for labor, material and
equipment are intended to cover all costs that the Contractor may incur due to
the work, regardless of who does that work (Contractor or subcontractor). Force
account work to a subcontractor will be authorized for additional administration
percentage to the Contractor.
B. Situations that require processing a Change Order:
Any change in the original scope or intent of the project, i.e. changing the
project limits which results in overruns, underruns, or new contract items
amounting to $10,000 or more. (Contact the Administering Bureau before
proceeding ANY TIME this situation arises. Before any changes to
project limits can be made new NEPA clearances must be obtained.).
Any overrun/underrun of items that are defined at to be paid at contract
quantity according to the specifications.
Overrun/underrun amounting to $50,000 or more on any contract
item.
All price adjustments.
Liquidated damages.
Value engineering proposals.
Incentive/Disincentive payments (if incentive/disincentive items are not
included in the contract).
Added items.
Change in specification.
Plan revision.
Extension of contract time.
C. Price adjustments which reduce payment for an item are occasionally charged
because material or quality of work is below minimum specified standard. These
adjustments are applied when the Project Engineer has determined a problem
that lacks a level of severity warranting removal and replacement. However, the
problem does affect life cycle costs or could cause premature maintenance
costs. For example: Rain damage, out of tolerance slump and/or air content,
deficient smoothness, and insufficient pavement thickness.
Attachment D to I.M. 6.000
June 12, 2024
Page 69 of 105
On the other hand, price adjustments could provide an "incentive or reward" for
exceptional work. In these cases, a project value is added due to increased
diligence on the Contractor's part. Examples are exceptional smoothness and
extra pavement thickness.
D. Mutual benefit agreements require a Change Order to document changes.
E. Reducing the final quantity of an item to zero requires a Change Order if the
original contract item value is $50,000 or more.
F. Settlement of liquidated damages (See Section 2.34 of this
Attachment). Contract proposals will list a daily rate (dollar value) for liquidated
damages. Change Orders written for liquidated damage assessments are written
as non-substantial. Refer to Incentive/Disincentive provisions below.
G. Incentive/Disincentive (I/D) provisions are included to provide the Contractor with
an "incentive" to complete a project early or a "disincentive" if the project is
completed late. I/D provisions will list daily rates to be applied to "critical closure"
times. Change Orders written for incentive/disincentive payments for early/late
completion are considered non-substantial.
H. Value Engineering proposals are encouraged for all aspects of contract
work. (Refer to Value Engineering later in this section.) Change Orders for
implementing value engineering proposals are Substantial and shall document
the terms and changes being implemented.
I. Intentionally left blank.
J. Items NOT Requiring a Change Order:
1. Deletion of a measured items with original contract amount less than
$50,000.
2. Overruns and underruns of measured items less than $50,000.
K. Often, plan revisions result in Change Orders having to be negotiated due to new
and/or changes to contract items. Processing Change Orders resulting from plan
revisions is sometimes delayed due to disagreement on prices, lack of success in
obtaining qualified subcontractor(s), or various other reasons.
It is imperative that the PIRC, in collaboration with the Project Engineer, actively
pursue Change Order negotiations to an early conclusion, especially if proposed
work involves public safety (guardrail, safety enhancement, etc.) or work related
to a prolonged detour. Obviously, agreement on unit prices is desirable;
however, there are times that work will have to proceed on a Force Account
basis. In all cases, documented agreements on the Method of Measurement and
Basis of Payment for items must be obtained before the Change Order is
written. NOTE: No work can begin until the Contractor has either agreed to a
Change Order or agreed to a basis of computing force account costs.
Attachment D to I.M. 6.000
June 12, 2024
Page 70 of 105
Preparation of Change Order (Form 831240 or Appia Change Order)
Each contract, on single project contracts, or each project on multi-project contracts
requires preparation of separate Change Orders for changes or additions.
All Change Orders shall be agreed to by the Contractor, and have all necessary
approvals prior to commencing additional work. This does not necessarily mean a
fully executed Change Order document, but rather a written agreement of the work to
be performed, how it is to be paid, and justification of cost. The only exception to this
rule is Force Account Work. If costs for work cannot be agreed upon, the extra work
must be performed on a force account basis. In such case, the Statement of Force
Account (Form 181213) is used. Article 1109.03, B, of the Standard Specifications
provides guidance and responsibilities for preparation of Force Account forms.
Currently, there are two systems for processing Change Orders:
Change Order form (Form 831240) may be used for projects paid locally by
the LPA or projects on the Farm-to-Market system utilizing paper Contract
Construction Progress Voucher (sometimes referred to as 309's) for
processing progress payments through the Contractor Pay System (CPS).
The Appia program initiates Change Orders. Refer to the Appia User Guide
“Under Construction” Instructions located in the Post-Letting Resources
section of the Local Systems website.
The Accounting I.D. Number must be noted after the project number
on the top of Page 1 of the change order. (This is populated
automatically if the project is set up using a Local Systems provided
.json file.)
Custom fields should be added to the Change Order section to mimic
the fields found in Form 831240. See the Appia “Under
Construction” Instructions for directions on how to add these custom
fields. Refer to the following instructions in Sections A-F for Form
831240.
Refer also to the following instructions for determining whether the
change order is Substantial or Non-Substantial.
The procedure for completing Change Order form (Form 831240) in the Contract
Construction Progress Voucher system or locally paid projects follows:
All information must be furnished (i.e. substantial/non-substantial).
It is important that the information is in the standard format because the data
is manually entered into the Contractor Pay System.
If Appia change orders are used, the local agency must take care to ensure all
necessary information is included. Additionally, if the change order is adding new
items to the contract, the user must ensure the correct “8000” numbers are input for
the new items.
If a project is required to utilize Doc Express (let at the Iowa DOT after January 19,
2018 for counties or July 19, 2018 for cities) or utilizes Doc Express, upload the
Attachment D to I.M. 6.000
June 12, 2024
Page 71 of 105
completed Change Order form (Doc Express Form 831240) in the Change Order
Drawer, following the naming convention as outlined in I.M. 6.000 Attachment F for
signature.
If a project is not required to utilize Doc Express (let at the Iowa DOT prior to January
19, 2018 for counties or July 19, 2018 for cities), one copy of the final Change Order
form (Form 831240) should be printed and distributed for signatures.
Before uploading the Change Order to Doc Express, a draft of the Change Order
must be submitted by email to the Regional Field Technician for review. The Field
Technician will review and provide editorial comments. When these comments have
been addressed, a second draft shall be submitted to the Regional Field Technician
for approval. When the Change Order is ready to be published, the Regional Field
Technician will notify the agency that the Change Order is ready to print to pdf and
upload into Doc Express.
Top of form
No.: Enter the Change Orders number. This should be a consecutive
numbering system for each contract, but multiple projects on a contract must
have their own Change Order. Example: a two project contract and changes
need to be made to both projects at the same time. There must be two Change
Orders written. Changes to one of the projects will be made in Change Order 01
and the changes to the second project will be made in Change Order 02.
Non-Substantial and Substantial boxes: Check the box that is appropriate for
this Change Order. The Administering Bureau shall be consulted if there are any
questions concerning the determination. The following guidelines shall be used
for determination;
Non-substantial
a. Price adjustments made to the contract in accordance with prescribed
guidelines in the Iowa DOT Construction Manual and/or contract
documents, such as (not all inclusive):
Changes in piling length
Jetting pile
Heating and protection of concrete
Price adjustments (plus or minus) for smoothness, pavement
thickness, fuel adjustment
Price adjustments for liquidated damages
Price adjustments for rain damaged pavement
b. Lump sum agreements, force account, and agreed price settlements
less than $150,000.
c. Change in contract quantity at contract unit price when variations from
the estimated plan quantities are not due to a plan or design change
and do not equal or exceed $150,000.
d. Total deletion of a measured item that has a bid amount greater than
$50,000.
Attachment D to I.M. 6.000
June 12, 2024
Page 72 of 105
e. Extension of contract time. Refer to CM 2.34.
f. Other items for which the rate of pay is pre-established in the contract
documents such as water for dust control or removal of anchor lugs
Substantial
NOTE: when a Change Order for a Federal-aid or Federal-aid Swap
project is classified as substantial, the Contracting Authority must obtain
written pre-approval from the Administering Bureau.
a. An extra work effort at contract unit prices, agreed unit prices, or force
account methods that equals or exceeds a total cost of $150,000. An
extra work effort may include a single item or multiple items.
b. Change Orders that include an overrun / underrun of an original
contract item or overrun/underrun of group of items that are part of an
extra work effort amounting to $150,000 or more.
c. Changes to the Method of Measurement or Basis of Payment of a
contract item or changes to price adjustment schedules for deficient
work detailed in the Iowa DOT Construction Manual.
d. Re-negotiation of a contract item's unit price.
e. Value Engineering proposals in accordance with Article 1105.13 of the
Standard Specifications.
f. Modifications to the terms of a contract, such as changes in contract
periods (includes completion date changes).
g. Adjustment in time of critical closure periods.
h. Changes in limits of contract or scope of work.
i. Prior to the work in the extended area, for federal-aid projects, the
following items must be accomplished, regardless of the funding
source for the extra work:
NEPA Location and Environment staff have reviewed
environmental documents and documented the extended area is
clear.
Document the work to be performed is either cost effective or in
response to an emergency.
FMIS Request Administering Bureau to request a change in
scope of work and project limits in FMIS (Fiscal Management
Information System). Also, included are the dates for "revised
NEPA clearance" and "cost effectiveness determination".
Administering Bureau Concurrence Date: This is the date that the
Administering Bureau concurs with the Change Order so work may commence.
This concurrence can be through verbal communication or email, and entered by
the Engineer. This allows work to be performed without waiting until the
Administering Bureau receives the form for their official signature at the end of
the form. The Administrating Bureau Concurrence Date must be noted for
substantial change orders.
Attachment D to I.M. 6.000
June 12, 2024
Page 73 of 105
Accounting ID No. (5-digit number): This is the 5-digit accounting number for
this project. This number is obtained from the Contract Project(s) section of the
contract, typically found on the second page of the contract.
Kind of Work: This is the Project Work Type that is obtained from the Contract
Project(s) section of the contract, typically found on the second page of the
contract.
Contractor: Name of the Contractor’s company on this contract.
Project Number: The project number in this contract that will be affected by this
Change Order.
Local Public Agency: The Local Public Agency that is the Contracting Authority
for this contract.
Date Prepared: The date this Change Order was prepared.
Section A - Description of modification to be made
Section A is used to provide a description of the work to be completed or the
modifications to be made. All descriptions should be brief and to the point; and
each should be proceeded by the Line Number (xxxx) in Section F and/or the
Change Number (8xxx) in Section G. For example:
xxxx Change Increase item for "Class 10 Excavation, Roadway &
Borrow".
8xxx Change Add an item for "Silt Basins". Work shall be in accordance
with the Pollution Prevention Plan provided for in the
contract documents.
8xxx Change Add an item for "Sealing Wells". Work shall be in
accordance with Section 2538, of the Standard
Specifications.
8xxx Change Add a new item for “Lime Green Boulders”. This is not a
current item; therefore, specifications for this work do not
exist. The 5 parts of the specifications must be entered in
this Section:
1. Description
2. Materials
3. Construction
4. Method of Measurement
5. Basis of Payment
When new items are added to the contract by Change Order, an item code and
item description will be added in Section G of the Change Order form. The item
code and item description are found in the Index to English Bid Items. Existing
Standard Specifications may or may not be able to be used for item codes
starting with, but not limited to, 2590, 2595, 2599, 6100, and 6200. If an existing
Specification can be used, identify the section of the Standard Specifications, or
the number of the Supplemental Specification, Developmental Specification, or
Special Provision, in this Section A (see example above). If there is not an
Attachment D to I.M. 6.000
June 12, 2024
Page 74 of 105
existing Standard Specification, the Description, Materials, Construction, Method
of Measurement, and Basis of Payment for that item must be included in this
Section A.
Section B - Reason for modification
Section B provides space for a brief narrative of reasons (or background) for
ordering the modifications outlined in Section A.
The explanation should be in sufficient detail and clarity to provide reasons why
the modification is necessary; and each should be identified by the Line Number
in Section F and/or the Change Number in Section G. A statement such as
"Extra Work ordered by the Engineer" or "As per plan revision" is not a sufficient
explanation.
Section C - Settlement for cost(s) of modification as follows with items
addressed in Sections F and G
Section C provides space for an explanation of the basis for the cost(s) of the
modification; and each should be preceded by the Line Number in Section F
and/or the Change Number in Section G. The basis should be noted as one of
the following: contract unit price, agreed unit price, agreed lump sum, force
account, no-cost change, or mutual benefit.
Section D - Justification for cost(s)
Section D provides space for the justification for the cost(s). The Project
Engineer shall conduct an independent cost analysis for items added or changed
by the change order prior to agreeing to those costs. An extension of contract
unit price(s) and price(s) established in the contract documents do not need
further justification. However, agreed unit price(s), lump sum, and force account
basis do require justification; and each should be preceded by the Line Number
in Section F and/or the Change Number in Section G.
Examples of justification could be:
Original copies of material quotes.
Comparable to item xxxx (a similar item) in the contract or a previous
Change Order.
Independent cost check of area suppliers.
Rental Rate Blue Book values and attached to the Change Order.
Invoiced price(s) and estimated labor cost (Davis-Bacon wage
determinations) is comparable to item xxxx (a similar item).
Certified payroll expenses, invoiced rental rate charges, and actual
material invoiced.
Davis-Bacon wage determinations.
Summary of cost(s) and attached to the Change Order.
Similar contracted items on previous project.
Comparing the unit price to past bid prices published in the Iowa DOT
Summary of Awarded Contract Unit Prices.
Attachment D to I.M. 6.000
June 12, 2024
Page 75 of 105
If all or part of the cost is based on an actual invoice from the contractor, attach a
copy of the invoice to the Change Order.
If the Statement of Force Account (Form 181213) is used, attach copies of each
days form as justification for this Change Order.
Section E - Contract time adjustment
Section E is to address any modifications that may need to be made to the
Contract Period. Every Change Order must address working days whether or
not an adjustment needs to be made to the Contract Period. Make sure to
address working days by checking the appropriate box; “No Working Days
added” if the change will have no impact to the time required to complete the
controlling item of work, “Working Days added” and how many if the change will
require additional days to complete the controlling item of work, or “Unknown at
this time” if the impact to the progress of the controlling item is unknown at the
time the Change Order is written. If the impact is unknown, it must be
addressed in a future Change Order. Add an explanation to justify the Contract
Time Adjustment that was selected.
Impacts on time should be considered when the Change Order for extra work is
written. If the impacts can be quantified, the number of days may be addressed
in the Change Order. But, in many situations, the impact on contract time may
not be known until the work is performed. In those cases, when impact on
contract time has been determined and the Change Order has not been fully
executed, the time may be addressed on the Change Order. If the Change
Order has been fully executed, another Change Order must be written to address
the time.
Make sure to address working days by checking the appropriate box:
1) “No Working Days added” if the change will have no impact to the time
required to complete the controlling item of work,
2) “Working Days added” and how many if the change will require additional
days to complete the controlling item of work, or
3) “Unknown at this time” if the impact to the progress of the controlling item
is unknown at the time the Change Order is written. If the impact is
unknown, it must be addressed in a future Change Order.
Note: This option should only be used in cases where impacts to time are
unknown until after the work is completed.
Section F - Items included in contract
Section F provides lines for entering modifications to existing contract
items. Change Orders written as "Mutual Benefit" or “No-cost Change” do not
have entries in this section.
Section F is completed as follows:
The first two columns indicate the “Participating” funding sources, if there
is Federal-aid and/or State-aid. Communication with the Administering
Attachment D to I.M. 6.000
June 12, 2024
Page 76 of 105
Bureau for their initial approval on Federal-aid and/or State-aid
participation before entering an “x” in the column(s) that will indicate how
the modification could potentially be funded. The Administering Bureau
will review the Federal and State potential participation determination and
make changes if necessary. If an “x” is not entered in either of the first
two columns, the change will be locally or Farm-to-Market funded.
Remember to always ask for and obtain initial approval from the
Administering Bureau before proceeding.
Most changes to items on Federal-aid projects are eligible for Federal-aid
participation. Examples of items which may not be participating are:
1. Costs relating to field mistakes. These could be errors by the
Contractor or inspection forces.
2. Unincorporated material
3. Added work that is considered “maintenance” in nature
4. Hauling of salvaged materials
The third column, Line Number, lists each modification to a contract
item. The "Line Number" identifies the specific contract item affected by a
particular change. The line number is the four-digit number identifying the
specific contract item and can be found in the contract under “Line No”. If
making a change that has been added by a previous Change Order, use
the 8xxx “Change Number” found on the Change Order in which it was
added.
In the fourth column, Item Description, enter the name of the item being
modified. This can be found either on the contract under “Item
Description”; or for items that were added by previous Change Orders, it
can be found on that Change Order.
In the fifth column, Unit Price, enter the contract unit price of the affected
item. Unit Prices are entered to 2 decimals.
NOTE: Lump Sum items can be entered with a unit price of 1.00.
In the sixth column, Quantity, enter the adjustment's quantity. (How much
quantity is being changed?) All quantities should be entered to 3 decimal
places. For example: Structural Concrete is being increased 53 CY. The
"Quantity" would be entered as 53.000. If the change to the item will
result in a decrease to the quantity, add a negative sign before the
quantity to indicate this decrease (-x.xxx).
NOTE: Lump Sum items have the agreed cost (in dollars) entered in the
quantity column. For example: Assume some item of work will be
deleted. That item was bid as lump sum with a unit price of $500. Then
500.000 would be entered for the "Quantity."
The seventh column, Amount, is typically a calculated amount (total
dollars) represented by a single entry. The Amount is automatically
Attachment D to I.M. 6.000
June 12, 2024
Page 77 of 105
calculated when using the electronic version of the Change Order form.
For example: Structural Concrete is being increased by 53 CY at a unit
price of $250 per CY. The dollar amount of this change would be 53 x
250 = $13,250.00. "Amounts" are entered to 2 decimal places. If the
change to the item is for a negative price adjustment or other decrease in
contract costs, add a negative sign before the number in this column also
to indicate a decrease in cost, unless using the electronic form in which a
negative sign will automatically be entered with the calculated amount.
NOTE: Care must be exercised to identify decreased and deleted
contract items, and disincentives. Obviously, the amount is negative for
these types of adjustments. To indicate "negative" values, a negative
sign (-) must be entered before the numbers in either the “Unit Price” or
"Quantity" column. Failure to correctly enter negative values could result
in increased payments to the Contractor, when in reality reduced
payments were required.
Section G - Items not included in contract
Section G, provides lines for adding new items NOT originally included in the
contract. The Iowa DOT policy requires additional, or new, items to be
sequentially numbered starting with 8001 for each project if the contract includes
multiple projects. Items added by 8xxx will appear on the progress voucher or
can be entered on the pay estimate as an 8xxx item after the Change Order has
been processed. Once an 8xxx item has been added, changes to that item shall
be considered as existing contract items. Future changes to these items shall be
processed as changes to items included in the contract under Section F and will
continue to carry the 8xxx line number.
NOTE: Change Orders written as "Mutual Benefit" or “No-cost Change” do not
have entries in this section.
Section G is completed as follows:
The first two columns indicate the “Participating” funding sources,
Federal-aid and/or State-aid. Enter an “x” in the column(s) that will
indicate how the modification could potentially be funded. See Section F
above.
The third column, Change Number, lists each new item being added to
the contract. Change numbers begin with 8001 and continue sequentially
for each project, even on multiple project contracts. Currently there are
two 8xxx items which have special significance. 8998 is used solely for
indicating liquidated damages and 8999 is used for stockpile of materials.
The fourth column, Item Number, can be obtained from the Index to
English Bid Items. Item numbers reference the appropriate section of the
Specification Book, Supplemental Specifications, Developmental
Specifications, or Special Provisions; and it is mandatory to check to see
if an item number exists in the Index of English Forms for the work being
added. If an item number specific to the work can be identified, use that
Attachment D to I.M. 6.000
June 12, 2024
Page 78 of 105
item number. If a specification does not exist for the work being added,
use the generic 2599 items and include the specification requirements in
Section A.
The fifth column, Item Description, identifies an addition by properly
describing the item according to Index of English Forms. If it cannot be
identified in the Index of English Forms, provide a brief description of the
work being added. The item description should relate to the specification
referenced in Section A.
The last 3 columns (Unit Price, Quantity, and Amount) are used in the
same manner as explained in Section F above. For price or quantity
deductions enter the number as a negative (-x.xx or -x.xxx). An example
of a deduction would be when reducing payment amount on the contract
include a negative sign before the amount entered in the “Quantity”
column. For a disincentive item, enter -1.000 in the “Quantity” column.
The form will automatically calculate a negative dollar amount in the
“Amount” column.
NOTE 1: The list in the "Summary of Awarded Contract Prices" book
may also be used to identify item numbers and descriptions. This book is
available at https://www.bidx.com/ia/lettings. On the “Lettings” tab, select
the most recent letting and click on “Awarded Contract Unit Prices -
ENGLISH” under “Downloads” on the right side of the screen. This
shows the award summary for a one year period ending with the letting
selected.
NOTE 2: To indicate "negative" values, (i.e., price adjustments) a
negative sign (-) must be entered before the numbers in either the “Unit
Price” or "Quantity" column. Failure to correctly enter negative values
could result in increased payments to the Contractor, when in reality
reduced payments were required.
Section H - Signatures
Agreed: This is for the Contractor’s signature that they agree with the Change
Orders as written. The Contractor should be the first to sign the Change Order.
Recommended: This is for the Project Engineer’s signature and should be the
second to sign the Change Order. For publicly owned projects, the Engineer is a
Professional Engineer licensed in the State of Iowa and authorized
representative of the Contracting Authority, and may or may not be an employee
of the Contracting Authority. For privately contracted projects, with improvements
that will become publicly owned, the Engineer is the authorized representative of
the public entity ultimately accepting ownership of the improvements. For all
other projects, the Engineer is the owner’s authorized representative.
Approved:
Attachment D to I.M. 6.000
June 12, 2024
Page 79 of 105
Person in Responsible Charge (PIRC): This may or may not be the
same person as the Project Engineer. If it is the same person, they may
sign on the “Project Engineer” signature line and this line, but their
signature on the Project Engineer line is the only one required. If the LPA
uses a consultant to perform construction inspection services, 23 CFR
635.105 requires the LPA to have a full time employee who is in
responsible charge of the project. For counties and larger cities, this
person is typically the county or city engineer; however, they need not be
a licensed engineer or architect to be the Person in Responsible Charge.
For smaller cities that do not have full time employees, the mayor or city
clerk may perform this function, with assistance from the Iowa DOT
Administering Bureau. A consultant may not serve as the Person in
Responsible Charge for a Federal-aid project. For future explanation of
duties and functions of the PIRC, see I.M. 6.000.
Contracting Authority and Other lines: These lines are all optional. If
the Contracting Authority and the PIRC is the same person, they only
need to sign the PIRC line above. The Contracting Authority is the
governmental body, board, commission, or officer having authority to
award a contract. Some City Boards and County Commissions like to
have their Chairs or Treasurers also sign financial documents. This gives
them a place for other signatures as they desire or require themselves.
Iowa DOT Administering Bureau: The Iowa DOT’s representative who
is responsible for oversight of the project. The representative may be a
Local Systems Field Engineer, Local Systems Field Technician, or the
Director from the Systems Planning Bureau.
NOTE: Change Orders for Farm-to-Market projects do not need to be
reviewed and signed by the Administering Bureau.
FHWA Concurrence: This is only required for Substantial Change
Orders which FHWA has oversight and that determination is the
responsibility of the Administering Bureau.
NOTE: For projects utilizing Doc Express, all signatures are to be
obtained electronically through Doc Express after the document has been
uploaded.
Distribution
When all required signatures are obtained, the Iowa DOT Administering
Bureau will distribute the form as listed in the “DISTRIBUTION” list. If FHWA
concurrence is required, FHWA will return the document to the Iowa DOT
Administering Bureau after it has been signed. The person who distributes
the executed Change Order will date and initial the document that is retained
in their Office.
Multiple Pages of the Form
Attachment D to I.M. 6.000
June 12, 2024
Page 80 of 105
The Accounting I.D. No. and Change Order No. must be included in the upper right
hand corner of each subsequent page.
Value Engineering
In accordance with Article 1105.13 of the Standard Specifications the Contractor may
submit a value engineering proposal to the Project Engineer with copies to the
Administering Bureau. The purpose of value engineering is to encourage alternative,
cost effective measures which produce equal or better quality end products.
Value Engineering proposals will not be accepted for:
Changes in basic design of a bridge or pavement type. For example: Value
engineering a project from PCC to HMA will not be acceptable. Changing a
designed bridge to a box culvert is not acceptable.
Changes which the Contracting Authority may already be considering.
Basing a value engineering proposal on, or similar to, existing standard
specifications, special provisions, or design plans and standards adopted by
the Contracting Authority. For example: A plan was let using 15 feet PCC
joint spacing. A value engineering proposal would not be accepted changing
this to 20 feet because "RH" standards have included this spacing as an
acceptable standard.
The written proposal shall have sufficient detail to be evaluated for compliance with
the requirements and limitations of Article 1105.13 of the Standard
Specifications. The detail provided must also allow for reviewing how a proposal
impacts the entire project. It shall include:
A description of existing requirements and proposed changes.
All affected contract items, including new Change Order items and supporting
justification for that extra work.
Unit prices requested for the work.
Effects on crew, equipment, and production needs for the project.
Impact on the construction period.
Schedule for obtaining all required materials.
It is very important to pursue these requests quickly to maximize potential
savings. Once a proposal is received, the Project Engineer should discuss merits of
VE proposal with the Administering Bureau. If appropriate, the Administering Bureau
will coordinate the review with other offices, including selected section leaders
(Design and/or Bridges & Structures) and FHWA if appropriate. Following this
review the Administering Bureau will notify the Project Engineer of approval or
disapproval, and any special considerations or requirements.
The Project Engineer will notify the PIRC to prepare and send a written notification to
the Contractor outlining the review and conclusions of that review.
If a proposal is acceptable, this notification will form the basis for issuing a Change
Order to implement conditions of the value engineering proposal. Therefore, a
notification should include:
Attachment D to I.M. 6.000
June 12, 2024
Page 81 of 105
A restatement of any changes.
All costs involved, and how costs will be addressed.
Any specification requirements as a result of changes or modifications to the
existing contract.
Details pertaining to special requirements for materials inspection and testing,
if applicable.
Any other special considerations or conditions.
If a proposal is not approved, the notification needs to include reasons for rejection.
The Iowa DOT has established a goal of 10 days to complete the entire review and
notification process.
2.37 PRIME CONTRACTOR’S PERFORMANCE BOND
One condition of awarding a contract to a prime contractor is that they provide a
performance bond that guarantees that the work of the contract will be completed.
Performance bonds are typically issued by sureties to cover 100% of the contract
amount (excluding predetermined incentives and bonuses). The implication of
Paragraph 3 of our standard bond form is that in cases where overruns or extra work will
increase the total contract dollars beyond 120% of the original contract amount, the
prime contractor must contact the surety and request that the surety expressly
acknowledge and agree that its bond applies and extends to the contract as modified or
amended. When this occurs, the surety will issue a Consent of Surety to the prime
contractor. This document should be submitted to the Contract Documents drawer in
Doc Express.
2.38 PROJECT ACCEPTANCE AND AUTHORIZATION FOR FINAL PAYMENT
See I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal-aid, Federal-
aid Swap, and Farm-to-Market Projects.
2.39 CONTRACTOR EVALUATION REPORT
Use the instructions on the Evaluation Report Instructions web page.
The intent of an evaluation is to report strength and/or weakness of the Contractor
Contractor's project related activities including paperwork, material documentation,
attitude, and cooperation. Special attention should be given to the Contractor rating
below 50 points. Remarks are required for any individual item(s) that is rated less than
50%. Remarks are also required when the Contractor is given a 100% rating.
The Contracts and Specifications Bureau maintains a database of Contractor evaluation
ratings, reacts to low evaluations, and seeks to improve Contractor project
administration. Evaluations are also used as a factor to establish bidder
qualifications. Therefore, it is very important that Contractors are evaluated realistically,
factually, and without bias.
Attachment D to I.M. 6.000
June 12, 2024
Page 82 of 105
It is anticipated that lower than average ratings would have been discussed at a meeting
between the Project Engineer and Contractor representatives prior to form submittal. A
Contractor should have an opportunity to discuss and understand why a low rating was
given. Further, the Contractor should be given (if requested) a critique of corrective
actions which would prevent reoccurrence of low rating(s).
See I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal-aid, Federal-
aid Swap, and Farm-to-Market Projects for additional instructions.
2.40 PROJECT REVIEW AND AUDITS
2.41 RESERVED FOR FUTURE USE
2.42 PROJECT ENGINEER'S PRE-AUDIT
See I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal-aid, Federal-
aid Swap, and Farm-to-Market Projects.
2.43 ADMINISTERING BUREAU AUDIT
See I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal-aid, Federal-
aid Swap, and Farm-to-Market Projects.
2.44 RESERVED FOR FUTURE USE
2.45 FORMS FOR FINAL PAYMENT PACKET
See I.M. 6.110, Attachment F, Final Form Packet Checklist (Word)
2.50 CONTRACTOR PAYMENTS AND PRICE ADJUSTMENTS
2.51 PAYMENT FOR MATERIAL ALLOWANCE (STOCKPILED MATERIALS)
Article 1109.05 of the Standard Specifications allows for payment of material stored at
the project site or, under certain conditions, at other locations. NOTE: The phrase
"material allowance" is also referred to as "stockpiled material."
Payment for stockpiled material may be allowed for materials that will be incorporated in
the project. Payment will not be considered for contracts with an award amount less
than $10,000. When reimbursement is allowed, payment will be based on:
100% of invoice cost for material properly documented and properly stored at the
project; or,
90% of invoice cost for material properly documented and stored
elsewhere. Storage locations must facilitate routine inspection by Project Engineer.
Payment of materials allowance will not exceed 80% of the authorized amount of the
associated bid item.
Attachment D to I.M. 6.000
June 12, 2024
Page 83 of 105
When material is stockpiled off-site and inspection of the material is not possible by the
Project Engineer or Iowa DOT Materials personnel, if Iowa DOT Materials inspection has
been requested and approved, the material may be paid for at 90% provided the
following information has been submitted by the Contractor:
Invoice cost of the material,
Description and quantity of the material,
Inspection reports, test reports, mill certifications, and approved shop drawings,
Location of the material, and
Material clearly marked for the County, Project Number, and Contractor as
reserved for that project, including photo(s) of stockpiled materials and photo(s)
of product identification tags.
Material allowances could be extended to "raw" structural steel provided:
"Raw" as used in this context means steel products that have been processed by
a steel mill into plates, sheets, or shapes of standard mill dimensions.
"Fabrication" is then taking these mill run products, and fabricating them into
usable structural shapes as specified in the contract documents.
Mill Certifications and Heat Numbers have been submitted and approved by the
Construction and Materials Bureau.
All shop drawings have been submitted and approved, including development of
a fabrication shop cutting diagram.
Iowa DOT shop fabrication inspector has verified and inspected all "raw" steel as
being delivered, properly marked for the project, and properly stored at the
fabrication shop.
Pre-conditions for Material Allowances
Payment for material allowances is based on actual invoiced cost. This means
the Contractor has ownership and/or control of any stockpiled material.
Checking or verification of payment by the Contractor may be required in
instances where a Project Engineer deems it necessary. In lieu of checking,
certification that the Contractor owns or controls the material may suffice.
Off-site material should be secured and clearly identifiable to the project.
Material considered for material allowances shall be specifically fabricated or
processed for that project. By definition, fabricated items will require shop
drawings or shall be fabricated from standard Iowa DOT detail sheets.
NOTE: Aggregate is obviously not "fabricated," but is "processed" and can be
considered unique as long as the material meets other applicable requirements
of this pre-condition section and has been certified by the producer.
The Project Engineer shall confirm the following items before payment is made:
1. Inspection or certification reports, test reports, and invoices are included
in the project file or in the Construction and Materials Bureau.
Attachment D to I.M. 6.000
June 12, 2024
Page 84 of 105
2. Processed or fabricated material is satisfactorily stored, correctly
identified, reserved for the project, and available for inspection to verify
existence and quantity.
3. Provisions should be made for inspection to verify that quality has not
deteriorated and that material has not been utilized for other
projects. This inspection can be arranged through the Project Engineer.
The preconstruction meeting is a good place to identify items for, or begin the
discussion of, potential stockpiled material. Potential items can be identified, but no
action needs to be taken until the material is available at the project or at other
agreed locations.
Stockpile Documentation Work Sheet
Payment for material allowances must be documented and monitored. It will be
necessary to maintain a project level work sheet covering:
value and quantity of material being stockpiled
location of stockpile (not on the project)
dates of the Project Engineer’s inspections
basis for material approval
The work sheet must show a running total for materials delivered and those used in
construction of the project, including the total quantity and value of the remaining
stockpiled materials. As materials are placed into "the stockpile," payment may be
made by properly including the new amount to Item 8999 on the progress voucher or
pay estimate.
If using Appia, use the Stockpiles module to track stockpile advances and
recoveries. See the Appia “Under Construction” Instructions for direction on how to
use the Stockpiles module. Appia will automatically deduct the appropriate quantity
from the stockpile when that item is recorded in an “Item Posting” (when the item is
placed in the field).
Voucher Entries
For Contract Construction Progress Vouchers (“309” Vouchers), an 8999 item
number will be preprinted on the voucher for Stockpiled Material. (If an 8999 item
number is not provided, one can be added by writing a Change Order to the contract
for Stockpiled Material.) For locally paid projects, a Change Order may be
processed for payment of stock pile materials, but it is not required. Appia attributes
stockpiles to the existing bid item rather than to a stockpile-specific line item, so the
8999 number is not used in that system.
Miscellaneous
The term "material allowance" is used to designate material which will later be
incorporated in the project and ultimately paid at contract unit prices. The term
"unincorporated material" is used for material ordered for use on the project, but not
used. Payment for material ordered, but not used and taken over by the Contracting
Attachment D to I.M. 6.000
June 12, 2024
Page 85 of 105
Authority must be paid by Change Order. (Refer to Section 2.36 of this Attachment
for procedure used to process a Change Order.)
2.52 PAYMENT FOR UNEXPECTED CLASS 12 ROCK EXCAVATION
When Class 12 excavation is unexpectedly encountered and there is no contract item for
Class 12, the quantity of Class 12 will be paid for as extra work through a Change
Order. (Refer to Section 2.36 of this Attachment for procedure used to process a
Change Order.)
Approval for Work:
CASE I (Contract has an item for Class 10.)
Specification 2102.05, A, 1 establishes a price of ten times the Class 10 contract unit
price for unexpected Class 12 excavation.
CASE II (Contract does not have an item for Class 10.)
In this case a new price will have to be negotiated.
NOTE: When the contract contains items for special categories of Class 12, such as
Class 12 (channel) or Class 12 (boulders), these items are not considered as
representing normal Class 12 roadway and borrow excavation work.
2.53 PRICE ADJUSTMENT GUIDE FOR REASONABLY CLOSE CONFORMING,
REASONABLY ACCEPTABLE, AND DEFICIENT WORK
Every effort should be made to prevent substandard work and/or non-complying material
from being incorporated into the project. However, when work and/or materials are
deemed to be non-complying, Sections 1101 and 1105 of the Standard Specifications
give authority to the Project Engineer for determining if construction work or materials
are acceptable and/or within reasonably close conformity to the plans and
specifications. Therefore, the Project Engineer must decide whether deficient work is to
be removed and replaced or left in place with a price adjustment. Unusual situations or
circumstances may warrant consultation with the Administering Bureau.
NOTE: A price adjustment is no substitute for specification compliance and
"unacceptable work" shall always be removed and replaced with acceptable
work. Further, Contractors need to be given an option of removing deficient work and
replacing with acceptable work in lieu of a price adjustment.
Guide Schedules for Price Adjustments
A. Gradation
Unless otherwise specified, variations in the gradation of aggregates shall be
price adjusted as prescribed by Price Adjustment for Aggregate Gradation Test
Deviation (see Iowa DOT Construction Manual Appendix 2-34(A)). These
adjustments apply to variations in gradations for:
Portland Cement Concrete
B. PCC Slump, Air Content, Rain Damage, and Edge Damage
Attachment D to I.M. 6.000
June 12, 2024
Page 86 of 105
1. Concrete Slump Price Adjustments are prescribed in the Iowa DOT
Construction Manual Appendix 2-34(B). Concrete Air Content, Water
Cement Ratio, Vibrator Frequency, Certified Plant Inspection, and Late
Curing Application Price Adjustments are prescribed in the Iowa DOT
Construction Manual Appendix 2-34(C).
2. Rain Damaged Portland Cement Concrete
When rain damage occurs, removal and replacement may be required by the
Project Engineer in accordance with Article 2301.03, K, 4, of the Standard
Specifications. However, damage must be determined to be severe enough
to warrant such action. Contact the Administering Bureau for assistance, if
needed.
If work is allowed to remain, Article 1109.03, C, of the Standard
Specifications requires the Project Engineer to determine "... a modification of
the contract unit price." The following CASES shall be used for determining
rain damage price adjustments.
NOTE: Price adjustments are applied to an entire area encompassing the
damage. (This means full width placed when damage occurred, beginning at
the first transverse joint before any damage and ending at the first transverse
joint after damage.)
ADJUSTMENT SCHEDULE
CASE I - (Payment is 95% of contract unit price.)
Texture is absent from practically all of surface area. Surface
appearance may have a "sandy" appearance or may be "pock" marked
from the rain droplets. An occasional edge repair may be required due to
excess edge slump or from edge rounding. Small areas along edge may
have coarser particles of fine aggregate exposed. Surfaces finished in
the rain or after a rain are also included in Case I. This includes any
manipulation of the pavement surface including mopping of the surface to
attempt to remove rainwater or retexturing while rainwater is present.
CASE II - (Payment is 90% of contract unit price.)
Texture is totally absent from the surface and cement mortar has been
eroded to an extent that coarser particles of the fine aggregate fraction
are generally exposed. Some slight troughs or depressions are apparent;
exposing coarse aggregate particles, but this damage is confined to a
limited area or randomly spread intermittently throughout damaged
area. Some edge repairs may be required to restore eroded
edges. Surface mortar that was removed by rain water, but later replaced
or supplemented with plastic concrete is included in Case II since a cold
joint or sand lens with minimal Portland cement paste contact may have
been inadvertently incorporated into the slab.
CASE III - (Payment is 85% of contract unit price.)
Surface mortar has been practically all removed to an extent that coarse
particles of the coarse aggregate fraction are visible. Considerable
erosion of edges has occurred, but not to an extent that pavement width
Attachment D to I.M. 6.000
June 12, 2024
Page 87 of 105
is affected. Intermittent edge repair may be required as well as some
surface patching of slight troughs or depressions that may have formed in
pavement surface due to flowing water.
Severe rain damage may require "localized area" repair by bridge deck
overlay procedures. Full depth removal and replacement may be
required if edge damage is severe. Severe cases of rain damage should
be referred to the Administering Bureau for review prior to determination
of repair or replacement.
In addition to above described price adjustments and repairs, slab
surfaces with missing, omitted, or damaged texturing shall have
macrotexture re-established by grooving prior to acceptance by Project
Engineer. As an alternative to price adjustment and grooving, for CASE I
and CASE II corrections, the Contractor may elect to diamond grind the
entire affected area to remove questionable surface mortar and re-
establish texture. When this option is chosen, payment for CASE I rain
damage will be 100% of the contract unit price, and the payment for
CASE II rain damage will be 95% of the contract unit price.
3. PCC Pavement Edge Damage
Price adjustments and recommended repairs for PCC pavement edge
damage are included in the Iowa DOT Construction Manual Appendix 2-
34(N). Typically, PCC pavement edge damage does not affect the structure
of the pavement, but it is unsightly and a result of substandard
workmanship. Therefore, in moderate cases, a price adjustment is warranted
over repair. In severe cases, price adjustment and repair may be
appropriate.
C. Steel Products
Certificates for steel products should be reviewed for compliance with the federal
Buy America requirements before it is incorporated in the project or paid as
stockpiled material. The intent of the Federal requirements is not to utilize
foreign steel in a Federal-aid project. If the Contracting Authority permits the
minimum usage as allowed by the Standard Specifications, the Contracting
Authority must track and report the usage of foreign steel to ensure the minimum
usage is not exceeded.
If it is discovered after-the-fact that foreign steel has been incorporated into to the
project exceeded the minimum usage, the Contracting Authority must contact the
Administering Bureau for guidance. All after-the-fact discovers of foreign steel
must be reported to FHWA who will determine the resolution on a case-by-case
basis, and will vary depending on the circumstances. If the Contracting Authority
has chosen to allow the minimum usage, and exceeds the minimum usage, their
risk of losing federal reimbursement is increased.
D. "L" Joint Tie Steel Deficiencies
Tolerance problems with "L" joint tie steel shall be corrected according to
procedures established in the Iowa DOT Construction Manual 9.26. (Note: ""BT"
and "KT" deficiencies usually require field correction.)
Attachment D to I.M. 6.000
June 12, 2024
Page 88 of 105
An adjustment in the contract unit price shall be made for out of tolerance "L"
joint tie steel areas. This price adjustment should be a reduction of 5% to the
contract unit price per square yard for affected areas on full depth pavements.
On PCC overlay projects, a 5% price adjustment should be applied to the PCC
furnish item in cubic yards and a 5% price adjustment should also be applied to
the PCC place item in square yards. It should be calculated based upon the
length of the area with deficient tie steel multiplied by the width of the placement.
The price adjustment is not intended to apply to individual out of tolerance tie
steel.
E. Bridge Floor Overlay price adjustments are prescribed in the Iowa DOT
Construction Manual Appendix 2-34(D).
F. Macro texture adjustments will be determined by the Project Engineer on a
case-by-case basis depending on severity and amount of surface area involved.
For texture depth measurement criteria, refer to the Iowa DOT Construction
Manual 9.43. Texture depths less than 1.5 mm 1/16 inch) shall be corrected by
sawing in grooving or diamond grinding. Texture depth exceeding 4.5 mm (3/16
inch) may require price adjustment as directed by the Project Engineer. Price
adjustments for over depth grooving are found in the Iowa DOT Construction
Manual Appendix 2-34(E).
G. Traffic Control
1. Price adjustments may be applied for failure to comply with traffic control
requirements in the contract documents. Contract price adjustments will be
determined by the Project Engineer, based on magnitude and frequency of
violations. A suggested sliding scale is $500 for the first violation, $1,000 for the
second violation, $2000 for the third and subsequent violations. See flowchart in
the Iowa DOT Construction Manual Appendix 2-15 for further guidance. After the
third violation has occurred, work may be suspended. If the traffic control
violation is serious, a higher price adjustment may be used based on the
Contracting Authority’s discretion as recommended by the Project Engineer
and/or Administering Bureau.
If the traffic control noncompliance requires the Local Agency to provide other
resources, the costs for these other resources can be added to the price
adjustment.
Price adjustment violations will be counted from first violation through last
violation for an entire contract. It is the Contractor's responsibility to ensure a
safe work zone for all construction activities regardless of work in progress or
who is doing that work. Therefore, violations will accumulate against the
"contract" and not be separated or individualized by subcontractor.
Examples of situations where a price adjustment would be appropriate include:
Attachment D to I.M. 6.000
June 12, 2024
Page 89 of 105
Failure to maintain traffic control devices (costs incurred by the
Contracting Authority may be recovered against this item).
Working without proper traffic control setup.
Unauthorized crossing of multilane divided roadway median.
Use of unauthorized, substandard, or non-standard traffic control
items such as incorrect sign sheeting or unapproved floodlights.
Violations of, or failure to comply with, traffic control requirements in
the contract documents.
Failure to maintain and keep functional any PDMS unit.
It is not intended that minor deficiencies be price adjusted if corrected in a
timely manner.
In addition to price adjustments, Project Engineers may suspend work for
irresponsible and/or repeated failure to conduct construction activities using
proper traffic control procedures.
It is acceptable for Contractors to work beyond the specified work hours when
all of the following conditions are met:
Contractor is working behind temporary barrier rail.
Inspection is not required.
No vehicles are entering the work area.
Traffic control is in accordance with the Night Work Lighting
requirements (Section 2550 of the Standard Specifications).
The work continues only for a short time frame to complete a specific
work task.
Copies of traffic control non-compliance notices should be provided to both
the Contractor and Subcontractor if the Subcontractor was issued the non-
compliance notice.
2. Failure to maintain traffic control devices and signs on a daily basis continues
to be a concern of the Project Engineer and/or Contracting Authority. Price
adjustments are appropriate for failure to adequately maintain these devices
and signs. To determine an appropriate daily price adjustment for lack of
maintenance, the total bid price for the traffic control item should be divided
by the number of working days allowed on the contract. This calculated
amount should then be divided in two to determine an appropriate daily
maintenance value. This daily maintenance value would be the appropriate
price adjustment for failure to maintain traffic control devices and signs.
The daily maintenance price adjustment calculated below is in addition to
other traffic control price adjustments.
An example calculation to determine this daily maintenance value follows:
Traffic control bid item amount (TC) = $25,000
Number of contract working days (WD) = 100
Attachment D to I.M. 6.000
June 12, 2024
Page 90 of 105
Daily maintenance price adjustment (PA)
PA = (TC/WD)/2
PA = ($25,000/100)/2 = (250)/2 = $125
PA = $125
3. Occasionally Contractors fail to provide the required traffic control technician
or have the daily traffic control diary completed during the construction of the
project.
An appropriate price adjustment for failure to provide a traffic control
technician is 20% of the traffic control bid item price or $500,
whichever is greater.
An appropriate price adjustment for failure to provide a traffic control
diary that is supervised by a trained Traffic Control Technician for
review during construction activities is an additional 10% of the traffic
control bid item or $500, whichever is greater. This price adjustment
can be issued multiple times throughout the duration of the project
and may even be issued on a daily basis for gross failure to have an
up-to-date completed Traffic Control Diary each day.
An appropriate price adjustment for failure to submit to the Project
Engineer upon project completion a traffic control diary that is
supervised by a trained Traffic Control Technician is an additional
20% of the traffic control bid item price or $500, whichever is greater.
These price adjustments are independent of each other and are also
in addition to other traffic control price adjustments.
4. When a flagger is incorrectly flagging according to the Flagger's Handbook,
as referenced in Article 2528.03, K, of the Standard Specifications, the
project should have the Flagger bid item price adjusted. This price
adjustment should be one half of the daily unit bid price for the Flagger item.
Examples of situations where a flagger price adjustment would be
appropriate include:
Incorrect flagging procedures
Nighttime flagging without a correctly lighted flagger station or without
appropriate nighttime flagging equipment or apparel
Incorrect, inappropriate, or incomplete flagger attire
Use of incorrect STOP/SLOW paddle
Failure to carry their flagger training card
When an untrained flagger is used in violation of the specifications, the
flagger shall not be measured and paid. The flagger shall continue to flag for
the remainder of the day and a trained flagger shall be substituted the next
day. Unattended flagger stations are not allowed by specifications. Any
unattended flagger station is considered a severe violation of the
specifications and should be price adjusted per Item 1 price adjustments.
When an untrained flagger is used in violation of the specifications, the
flagger shall not be measured and paid. The flagger shall continue to flag for
the remainder of the day and a trained flagger shall be substituted the next
Attachment D to I.M. 6.000
June 12, 2024
Page 91 of 105
day. Unattended flagger stations are a severe violation of the specifications
and should be price adjusted per Item 1 price adjustments.
These price adjustments are also in addition to other traffic control price
adjustments.
G. Asphalt
1. Liquid Asphalt
a. Viscosity or Penetration
When non-complying tests occur, determine the quantity
affected. Average all non-complying quality control tests and use that
average in conjunction with the Iowa DOT Construction Manual Appendix
2-34(F) to determine if, or how much, price adjustment is warranted.
b. Residue
The determination of compliance for emulsions used as tack coats shall
be based on residue percentage. Undiluted emulsion contains a
minimum of 57% asphalt residue. Emulsion diluted with one part
emulsion to one part water shall contain a minimum of 28.5% residue.
When non-complying tests occur, determine the quantity
affected. Average all non-complying quality control tests and use that
average in conjunction with the Iowa DOT Construction Manual Appendix
2-34(G) to determine if, or how much, price adjustment is warranted.
2. Asphalt Binder - Viscosity
When a non-complying viscosity test occurs, establish the quantity of material
affected. This quantity may be the total asphalt binder used that day, unless
intermediate quality measurements have been made during the day. The
quantity affected shall be in relation to the proportion of non-complying
samples to the total number of asphalt binder samples obtained that day.
Example:
Total samples taken during the day = 5
Number of failing samples for the day = 2
Total asphalt binder used that day = 200 tons
Quantity affected = (2 ÷ 5) x 200 = 80 tons
Non-complying test results for the day shall be averaged to determine the
amount of deviation from specification requirements. This average will be
used to apply the appropriate percent of payment for the quantity
affected. Use the Price Adjustment schedule in the Iowa DOT Construction
Manual Appendix 2-34(H) and Appendix 2-34(I) to obtain the applicable
payment adjustment.
The materials, both liquid asphalt and asphalt binder, are used on the basis
of certification. The follow-up acceptance testing is performed to verify the
Attachment D to I.M. 6.000
June 12, 2024
Page 92 of 105
compliance so work will not be delayed pending the test results. However, if
the material has not been incorporated and acceptance tests indicate non-
compliance, the material will be rejected.
Unless indicated otherwise in the contract documents, the Contractor must
use performance graded (PG) asphalt binders. If a PG asphalt binder is used
but the properties do not comply with specifications, consult with the
Administering Bureau and the District Materials Engineer for appropriate
resolution. A price adjustment may or may not be appropriate depending
upon the circumstances involved in each situation.
3. Asphalt Binder Content
The determination for compliance with the specifications of the asphalt binder
content control shall be made for periods not exceeding one day in
length. Determinations shall be made for shorter time intervals when non-
compliance for the shorter intervals has occurred.
The specifications for asphalt construction require the Contractor to maintain
the asphalt binder content within plus or minus 0.3 percentage points of the
percent intended. The percent intended is given on the job-mix formula
sheet. No payment will be made for asphalt binder used in a mixture in
excess of tolerance specified. Please note that the Price Adjustment for
Deviation in Asphalt Binder Content (see Iowa DOT Construction Manual
Appendix 2-34(J)), is only for use in situations when no hot box samples are
taken for a given day of asphalt paving.
Excessive asphalt binder content can result in low lab voids which can, in
turn, result in a high potential for pavement failure due to flushing and
rutting. When the deviation from intended asphalt binder content is greater
than 0.3% and the lab voids for the lot are extremely low, the District
Materials Engineer should be consulted regarding the rutting potential of the
pavement. In cases where severe rutting or flushing develops or is likely to
develop, removal and replacement of the non-complying asphalt pavement
should be considered. See Materials I.M. 511 Appendix D for troubleshooting
asphalt binder content issues.
When the asphalt mixture quantity involved is 200 tons or less, tank-stick
measurements lack precision and cannot be used as a basis for determining
asphalt binder content. In this case, the average of tank-stick measurement
results from the day before and the day after may be used to provide further
verification.
Measurement of asphalt binder content is made using calibrated in-line flow
meter readings, per Materials I.M. 509. Yield checks are made either by using
a calibrated tank-stick or by comparing the quantity of material delivered with
the quantity used. Perform yield checks a minimum of once per week or as
otherwise required by the Engineer. The procedures listed in the Iowa DOT
Materials I.M. 508 and I.M. 509 and I.M. 509 Appendix A should be followed
closely in making tank-stick measurement calculations.
Attachment D to I.M. 6.000
June 12, 2024
Page 93 of 105
The Contractors are cautioned to observe the following procedures in order to
help insure accuracy of the determinations:
a. Keep the storage tank level and in good condition
b. Make sure that the asphalt binder in the surge tank is exactly the
same level each time that measurements are made
c. Try not to drain the asphalt binder level in the tanks into the heater
coil area when measurements are made
d. See that rail cars and transport trucks are completely unloaded or any
unused asphalt binder returned is weighed or measured
To eliminate misunderstandings and uncertainties, it is strongly urged that an
authorized representative of the Contractor observe all asphalt binder
sampling and quantity measurements and check all calculations. A
Contractor's representative should also be requested to initial or sign the field
book or record sheet containing the measurements and results as they are
made.
4. Segregation in Asphalt Pavement
When mixture segregation occurs in the pavement such that the composition
and quality of the mixture required by specification are not uniformly attained,
the sections judged deficient may be required to be removed and replaced as
defective work. An adjustment in contract price may be made for deficient
work for the cases described in the following schedule.
a. Pavement Surface
The adjustments in contract price are to be applied to the entire paver
lane width and lift thickness between extreme areas of
segregation. Price adjustment shall apply only to the payment for the
asphalt mixture. Price adjustments are defined in the Iowa DOT
Construction Manual Appendix 2-34(K).
ADJUSTMENT SCHEDULE
Case I (Payment is 80% of contract unit price.)
When uniform surface texture and mixture composition is evident
(by visual observation) except for occasional and random areas of
segregation, the mix shall be subject to price adjustment if the
area determined segregated equals or exceeds 1 square yard per
station per paver width (length determined by longitudinal distance
both directions from segregated area).
Case II (Payment is 50% of contract unit price.)
When a non-uniform surface texture and mixture composition is
evident (by visual observation) and there is a regular interval of
numerous areas of segregation connected or nearly connected
with longitudinal traces of segregation, the mix shall be subject to
price adjustment if the total area segregated equals or exceeds 3
square yards per station per paver lane width (length determined
Attachment D to I.M. 6.000
June 12, 2024
Page 94 of 105
by longitudinal distance both directions from the extreme ends of
areas of segregation).
Case III Longitudinal Streaks (Payment is 80% of contract unit
price.)
When a non-uniform surface texture and mixture composition is
evident (by visual observation) and in the form of longitudinal
streaks of 3 inches or more in width, the mix shall be subject to
price adjustment if the segregation occurs at a rate that exceeds 1
square yard per station. The rate is determined by multiplying
approximate width by length of the streaks to determine area and
dividing by the length of the streaks (in stations). Longitudinal
streaks most commonly occur with the windrow-pickup process,
particularly when resurfacing superelevated curves. Streaks are
typically seen in the wheel path areas and occasionally in the
center of the lane. Streak widths typically vary from 3 to 12 inches
and may be continuous or intermittent. This type of segregation
results in longitudinal cracking.
More severe surface and mixture segregation may require
corrective procedures as:
full width thin layer 1 inch thick resurfacing or
removal of asphalt mixture course with no extra payment
and replacement with construction that fully complies
Note: Determination of segregation in asphalt pavement is by
visual examination in accordance with current specifications. The
engineer may consider further verification through coring and
extraction tests. Segregation case examples, with corresponding
price adjustment calculations, are illustrated in the Iowa DOT
Construction Manual Appendix 2-34(K).
b. Fillets & Runouts
This price adjustment procedure does not apply to fillets, bridge
runouts, or other hand-worked areas outside of the normal paver lane
width.
c. Base & Intermediate Courses
The price adjustment percentages shall be reduced as indicated in the
Iowa DOT Construction Manual Appendix 2-34(K) for all base or
intermediate courses, except when such mixture is specified and used
as the surface course.
d. Procedure for Determination of Price Adjusted Quantities
The segregation case examples shown in the Iowa DOT Construction
Manual Appendix 2-34(K) illustrate a concept that may be used to
define the severity of segregation and appropriate price adjustment
Attachment D to I.M. 6.000
June 12, 2024
Page 95 of 105
factor. It is not required, however, to physically measure each area of
segregation to determine a quantity of HMA mixture that is subject to
price adjustment. The intent is to define the quantity subject to price
adjustment by identifying the number of truckloads in which
segregated areas are evident. This obviously takes some judgment to
decide how large or severe an area must be before it is price
adjusted. The 1 square yard area shown in examples is a
"rule-of-thumb." Most importantly, segregated areas that exhibit an
obvious concentration of coarse aggregate resulting in a non-uniform
open texture should be price adjusted.
Whenever segregation is observed, the Contractor shall be advised
immediately and the inspector must document the deficiency with a
Non-compliance Notice. The notice should reference the applicable
specification and indicate the Project Engineer will review the work to
determine the acceptability of the work. It is recommended that a
Non-compliance Notice be issued when segregation is initially
observed with final evaluation and price adjustment determined later
but prior to project acceptance.
Timeliness is important for two reasons. First, the Contractor must take
corrective action immediately. Failure to do so should result in suspension of
work. Secondly, early identification of unacceptable work allows for
resolution of any disputes before there is an "implied" acceptance. The Iowa
DOT Construction Manual 1.12 discusses the enhancement of working
relationships by timely notification of unacceptable work.
For streak type segregation, it will be necessary to identify and tabulate the
location and length of the segregated streak areas subject to price
adjustment and base the price adjustment on the mix quantity within the
beginning and ending station limits of the streaks.
Normally this procedure should be repeated for each day from header to
header on the day following placement. Each day's run can be tabulated
showing a summary of affected tons of HMA mixture subject to price
adjustment.
5. Asphalt Binder Film Thickness
Film thickness, as calculated in the Iowa DOT Materials I.M. 501, provides a
general indication of an asphalt pavement’s potential long-term
durability. When asphalt binder content changes are considered to adjust air
voids, caution must be used to assure that adequate film thickness required
in the Iowa DOT Materials I.M. 510 Appendix A, Table 1 is maintained. When
the resulting film thickness is outside the specified range, procedures given in
the Specification 2303.05, A, 3, c. should be used to determine the
appropriate price adjustment or alternate course of action.
6. Laboratory Voids and Field Voids
Attachment D to I.M. 6.000
June 12, 2024
Page 96 of 105
Production control and compaction requirements are covered in the current
specifications for Asphalt Mixtures. Price adjustment is made through use of
Pay Factors for laboratory voids and field voids determined for the lot. The
Pay Factors are applied to the unit price for asphalt mixture only.
7. Defective Field Voids in Asphalt Pavement
When Percent-Within-Limits (PWL) falls below 50 for field voids, the lot may
be declared defective. Use the following guidelines to determine if the
material shall remain in place or be removed. These guidelines are to be
used with engineering judgment. The resulting pay factor at the completion of
review should be between 0 and 0.75.
First, determine if there is a testing issue by reviewing Gmm for consistency
and correlation. If it is determined the Gmm is not reliable due to testing
concerns, re-calculate the field voids using the Engineer’s test results and
compare. It may be necessary to proceed through the guidelines below with
both initial results, and re-calculated results. If Gmm is valid, use the following
guidelines:
a. Randomly core the defective area. The cores shall be for information
only and not be included in the acceptance decision.
b. Re-calculate the voids for each core using the nearest Gmm value
instead of the average Gmm value.
c. Evaluate the initial set of cores as well as the additional cores as
follows:
If Field Voids are High (risk of long-term durability and strength
issues)
If all of the following are true or for a non-surface lift, consider
leaving in place with a price adjustment:
o No core exceeds 10% voids
o Film thickness >= 10
o Average field voids < 9%
If all of the above are not true, consider removal.
If Field Voids are Low (risk of rutting)
o If low traffic and high speed, then consider leaving in
place.
o If high traffic, consider removal.
If the average thickness is less than the intended, consider
removal.
H. Adjustments for All Contract Administration Issues
Price adjustments for non-complying work are occasionally appropriate when the
issue relates to other incidental items in the contract documents. Price
adjustments shall not be considered unless there is willful or repeated
reoccurrences indicating lack of due consideration on the Contractor's part. In
such cases, the following will apply:
Attachment D to I.M. 6.000
June 12, 2024
Page 97 of 105
Provide a clear and concise notification to all parties involved with the
incident. (This could be a verbal notification or a written non-compliance
without price adjustment.)
Subsequent violations would result in additional non-compliances and
could be reason for price adjustments starting at $100, then $250, $500
etc. (progressively doubling the amount of each following violation).
NOTE: It is NOT intended that minor deficiencies be price adjusted if corrected
in a timely manner. Situations and circumstances will dictate how this portion
should be applied.
I. Steel H-Pile Weight Deficiency
The Iowa DOT Materials I.M. 467 specifies a mass tolerance of 2.5% on steel H-
pile weight deficiency. Steel H-piles that are deficient by more than 2.5% of
theoretical weight should not be accepted for incorporation into the work except
when:
The need for the steel H-pile is immediate and considered critical by the
Project Engineer.
Replacement of steel H-pile is not reasonably possible due to short
supply and availability.
In the above cases, the Project Engineer may decide to approve the use of
deficient steel H-pile and apply a price adjustment in contract unit price for the
material as prescribed by Steel H-Pile Weight Deficiency Price Adjustment" in the
Iowa DOT Construction Manual Appendix 2-34(L).
J. Erosion Control or Other Environmental Issues
1. Occasionally Contractors fail to provide the required erosion control
technician (ECT) or an Erosion & Sediment Control (ESC) Basics trained
individual during the construction of the project.
An appropriate price adjustment for failure to provide an ECT or ESC
Basics trained individual during construction activities anytime during a
month is $250. This adjustment would be issued on a monthly basis.
Price adjustments will not exceed $1,000 per year.
These price adjustments are in addition to other erosion control price
adjustments.
2. Price adjustments may be applied for failure to comply with erosion and
sediment control requirements in the contract documents. Contract price
adjustments will be determined by the project engineer, based on
magnitude/severity and frequency of violations. A suggested sliding scale
is $500 for the first violation, $1,000 for the second violation, $2000 for
the third and continuing to double for each subsequent violation. See
flowchart in Appendix 2-34(O) for further guidance. If the erosion control
Attachment D to I.M. 6.000
June 12, 2024
Page 98 of 105
violation is serious, a higher price adjustment may be used based on the
Engineer’s discretion.
The same sliding scale is suggested for other environmental issues.
It is not intended that minor, non-recurring deficiencies be price adjusted
if corrected in a timely manner.
K. Railroad Safety Violations
Projects that affect railroads will include Contractor safety and flagging
requirements. The provisions may specify amounts for price adjustments for
safety violations. If the provisions do not include amounts for price adjustments,
the Project Engineer and/or Contracting Authority should consult with the Local
Systems Bureau to determine the appropriate amount.
Copies of non-compliance notices for railroad safety violations should be
forwarded to the Administering Bureau.
L. Use of Non-Domestic Steel Products
Certificates for steel products are to be reviewed for compliance with the contract
documents before the material is incorporated in the project or paid as stockpiled
material. The intent of Specification 1107.06, B and I.M. 107 is not to utilize
foreign steel. If the Engineer permits the minimum usage as allowed by the
Standard Specifications, the Engineer must track and report the usage of foreign
steel to ensure the minimum usage is not exceeded.
If it is discovered “after-the-fact” that foreign steel has been incorporated into the
project exceeding the minimum usage, the Engineer must contact the
Administering Bureau. All after-the-fact discoveries of foreign steel incorporated
into a federal-aid contract must be reported to FHWA who will determine the
resolution on a case-by-case basis.
2.54 PRICE ADJUSTMENT CHANGE ORDERS
Price adjustment deductions are processed by Change Orders using an 8xxx Change
Number. (Refer to Section 2.36 of this Attachment for information about processing
Change Orders.)
If using Appia, do not use the “Adjustments” feature to assess payment adjustments.
Instead, use Change Orders as described above.
2.55 FINAL PAYMENT TO CONTRACTOR
Iowa Code allows a maximum of 5% to be retained until a contract is completed. Iowa
DOT specifications require that 3% will be retained on the first $1,000,000 paid on a
contract.
This retainage is specifically withheld to cover:
Attachment D to I.M. 6.000
June 12, 2024
Page 99 of 105
Unpaid creditors who file claims against a contract. The Contracting Authority is
obligated by Iowa Code Section 573, to withhold at least double the amount of
any claims on file from the retained funds. The amount of retained funds is the
maximum amount available for 573 claims.
Iowa Code also requires payment of interest on retained contract funds.
Refer to I.M. 6.130, Interest Payment Procedures, for the applicable interest
payment requirements.
573 Claim
A "573 Claim" is a term used to signify an Iowa Code Section 573 that
establishes procedures by which unpaid subcontractors, material suppliers, etc.
may file a claim for payment against the contract. These claims are formally filed
with the Finance Bureau for contracts paid through the Contractor Pay System
(located on Farm-to-Market routes), or with the Contracting Authority for
contracts paid using local funds.
If a claim is filed, Iowa Code mandates that the Contracting Authority shall
withhold, from the retained funds, an amount of 2 times any claim. The amount of
retained funds is the maximum amount available for 573 claims. Following
resolution of a "573 claim" or 60 days after the final (if no lawsuit has been filed),
the Contracting Authority issues payments as required.
Recommended Guidelines
At the preconstruction meeting, Contractors should be advised that all required
forms, documents, and certifications must be properly prepared and forwarded to the
Project Engineer before a final progress voucher can be processed. Forms required
for Contractor submittal are explained in Section 2.20 of this Attachment and the
Contractor is expected to read and be knowledgeable of these requirements.
It is important that required forms, documents, and certifications are dated when
received from the Contractor. Every effort should be made to have all
documentation and Change Order issues resolved on, or soon after, accepting the
project.
For more information, see I.M. 6.110, Final Review, Audit, and Close-out Procedures
for Federal-aid, Federal-aid Swap, and Farm-to-Market Projects.
Interest Payment Information for County and City Projects
See I.M. 6.130, Interest Payment Procedures. (Form 830236)
2.56 FUEL ADJUSTMENT
The specification for Fuel Adjustment, Section 2120 of the Standard Specifications,
applies only when the contract quantity of that eligible item is 50,000 cubic yards or more
as noted in the Specifications.
Attachment D to I.M. 6.000
June 12, 2024
Page 100 of 105
The Current Price Index (CPI) is available at the Contracts and Specifications Bureau
website: https://www.iowadot.gov/contracts/lettings/FuelAdjustment.pdf. The Base Price
Index (BPI) for fuel adjustment calculations will be the CPI listed for the month prior to
the letting date of the contract.
Fuel Adjustment Calculation
Standardized Fuel Adjustment work sheet (Form 105) is available in electronic format
under the "Inspection Tools" tab on the Construction and Materials Bureau "Contract
Administration" webpage:
https://iowadot.gov/construction_materials/Contract-administration/fuel_adj
Payment for fuel adjustments is to be calculated at the end of each month for all
qualifying work accomplished that month.
The Contractor shall provide to the Project Engineer, on a monthly basis, a spreadsheet
with quantities and the calculated amount of fuel adjustment.
Instructions for Fuel Adjustment Worksheet
Following instructions also available at:
https://iowadot.gov/construction_materials/contract-administration/fuel-adj
1. Download the Fuel Adjustment Worksheet and save file to user's computer.
2. Complete contract information in header of spreadsheet.
3. Obtain Base Price Index (BPI), from the Contracts and Specifications Bureau
by selecting Price Index for month previous to month of the letting. (For
example: Letting Date is October 18, select CPI for September).
4. Enter the BPI in the designated space.
5. Enter the contract quantity of the items in the designated rows in the
"Estimated Project Quantities". Other items included in the contract, but not
listed, shall be added.
6. Obtain the Current Price Index (CPI) for a month from the Contracts and
Specifications Bureau.
7. Enter the CPI in the column "CPI" for the designated month.
8. Enter the quantities that have been hauled in the appropriate item columns
and month row. For example, Selected Backfill and Class 10 Excavation
were hauled in June. In the June row, the Selected Backfill quantity is entered
in Cell E35 and Class 10 Excavation quantity in Cell F35. The total quantity
for the month will be automatically computed and shown in the column
labeled "Total CY".
9. When adding an item not already shown in the spreadsheet, use one of the
columns designated for the applicable Fuel Usage Factor (FUF). The
Attachment D to I.M. 6.000
June 12, 2024
Page 101 of 105
spreadsheet uses yellow shading for items which use a FUF of 0.20 and
green shading for Embankment-in-Place items which use a FUF of 0.27.
10. The fuel adjustment amount for the month will be automatically computed and
shown in the column "FA" (Fuel Adjustment).
11. Submit a copy of the completed form to the Project Engineer. Payment or
credit will be made by processing a Change Order. The form shall be
completed and submitted on a monthly basis. The monthly quantities shall be
added to the previous month's spreadsheet.
12. The Contractor and Contracting Authority shall agree upon the frequency of
payment or credit.
Fuel Adjustment Payment
Payment shall be by a Change Order form (Form 831240) using the item number
6200-5000171. With the Contractor's approval, one Change Order may be executed
at the end of the project or at intervals agreeable to both the Project Engineer and
the Contractor. Regardless of payment intervals, calculations on Form 105 shall be
made at the end of each month with a copy forwarded to the Project Engineer for
their files.
2.60 CONSTRUCTION FORMS
Most forms can be found on the Iowa DOT’s Forms webpage, but if difficulty is
encountered in locating forms, contact the Administering Bureau.
FORM
NUMBER
TITLE
MANUAL
LOCATION
General Construction
830301
Audit of Final Pay Estimate
2.43*
640003
Certificate of Completion and Final Acceptance for Agreement
Work
12.04
518002
Certification of Subcontractor Payments
2.25*
830176
Certified Transcript of Labor Payroll/Statement of Compliance
(WH-348)
2.24*
831240
Change Order
2.36*
830230
Contract Quantity Agreement
2.27*
102008
Contractor Concept for Value Engineering Incentive Proposal
2.36*
830215
Co-Permittee Certification Statement
10.33
830436
Final Payment
2.37*
820193
Identification of Sample for Test
3.21
830236
Interest Payment Information for County and City Projects
2.55*
830245
Noncompliance Notice
3.21
Attachment D to I.M. 6.000
June 12, 2024
Page 102 of 105
830216
Notice of Discontinuation of a Stormwater Discharge
10.31
810036
Notice of Suspension or Resumption of Work
3.06
830237
Notice to Proceed
2.32*
830435
Statement of Completion and Final Acceptance of Work
2.37*
181213
Statement of Force Account
2.35*
830214
Storm Water Site Inspection
10.33
830231
Subcontract Request
2.25*
830238
Weekly Report of Working Days
2.33*
830241
Weekly Report of Working Days (I/D)
2.33*
EEO and Employee Training
102116
Certification of DBE Accomplishment
2.25*
650170
Project Engineer’s EEO Project Site Inspection / Wage Rate
Report
2.22*
102115
Statement of DBE Commitments
2.25*
Grading
650014
Preliminary Estimate for Clearing Right-of-Way
6.11
830214
Storm Water Site Inspection
10.33
830215
Co-Permittee Certification Statement
10.33
830216
Notice of Discontinuation of a Storm Water Discharge
10.31
Structures
830209
Log of Piling Driven with Wave Equation
11.25
830210
Log of Piling Driven by Formula
Appendix
11.22
800240E
PCC Plant Page (English)
11.51
Hot Mix Asphalt and Flexible Bases and Subbases
800241
Daily HMA Plant Report (English/Metric)
8.02
Portland Cement Concrete Paving
830212
Ready Mix Concrete Ticket
9.03
830213
Project Information/Paver Inspection
9.69
800240E
PCC Plant Page (English)
9.02
* Indicates Section in the Attachment
2.70 Intentionally left blank
2.71 BRIDGE INVENTORY REPORT
See I.M. 7.020, Bridge Inspections.
Attachment D to I.M. 6.000
June 12, 2024
Page 103 of 105
2.72 PREPARATION OF AS-BUILT PLANS
It is recommended practice to generate as-built plans on all projects for historical records
but it is not required; however, for projects that go over, under, or intersect with an
Interstate or Primary highway, as-built plans must be submitted to the Administering
Bureau.
When revising information on the plan with As-built information, the voided information
should be lined out.
The As-built plan shall include the actual quantities included in the project, as well as
items added to the project by Change Order that change physical features of the project.
It is not necessary to change wording in the As-built plan from future tense to past tense.
The title page of all as-built plans should include the certification block (Form 520003)
with the name of the Contractor, year of project completion, Project Engineer's signature
and certification.
Samples are included in the Iowa DOT Construction Manual Appendix 2-37.
Types of Work
The following work types will not require preparation of as-built plans unless safety items
such as guardrail or barrier rail are included in the project:
Landscaping/Wildflower planting
Erosion Control/Seeding/Slide Repair
Signing/Statewide Signing/Delineator & Milepost Projects
Spot Overlays
Patching
Joint and Crack Sealing
Slurry Seal
Bridge Painting
Bridge Deck Repairs/Bridge Deck Overlays
Bridge Beam Repairs
Paved Shoulders
HMA Resurfacing
Bridge Washing
Changes in the following types of work may include the listed items in the As-built
plan:
A. Grading, Paving, Subdrains, Fencing, and Erosion Control
The As-built plan may include the following:
1. Control points - marked and referenced.
2. Land section corners - marked and referenced.
3. Vertical and horizontal alignment.
Attachment D to I.M. 6.000
June 12, 2024
Page 104 of 105
4. Corrections and adjustments in stationing.
5. Elevation of final bench marks and deletion of abandoned bench
marks.
6. Planned drainage including pipe location, sizes, and flowlines;
subdrains; backslope and letdown drains; etc.
7. Field Tile Crossings including size and location.
8. Subgrade treatment areas.
9. Locations, type, and width of accesses, driveways, and street
connections.
10. Include location of overhead and underground utilities, if known.
11. Utility permit number and filing location.
12. Planned location, sizes, and flow lines of storm and sanitary sewers
and intakes.
13. Location and type of fence.
14. Erosion control ditch treatment and let-down treatment.
15. Guardrail and other safety appurtenances.
B. HMA Resurfacing
Wedge and strengthening courses and other items such as guardrail, culvert
extensions, etc.
C. Structures
Items to include for structures and bridges converted to culverts:
1. Flow line and footing elevation
2. Elevation of bench mark
3. Log of piling
4. Excavation limits (Class 21, 22,23, and 24)
5. Weep hole locations
D. Lighting, Signing, and Traffic Signals
Lighting, Signing, and Traffic Signal projects may include:
1. Location of underground conduit
2. Location of pole and handhole
3. Mounting heights and lengths of mast arms
4. Log of piling for tower lighting projects
5. Location of sign footing, post size and length
6. Vertical clearance of sign truss
7. Detector Loop type, size, and location
E. Bridge Deck Repairs and Pavement Patching
As-built plans are not required for bridge deck repair and pavement patching
projects, unless safety items such as; guardrail or barrier rail have been
changed. The repair projects for replacing bridge beams do not require an
As-built plan.
Attachment D to I.M. 6.000
June 12, 2024
Page 105 of 105
Wetlands
Corps of Engineers' Section 404 Permits require that "Wetland Mitigation As-
Constructed Drawings" be submitted to the Corps within 30 days of the completion of
the mitigation sites. These drawings are separate from the usual Contracting
Authority As-built plans. "Wetland Mitigation As-Constructed Drawings" are more
detailed site maps that are used to confirm compliance with mitigation agreements
and to monitor future performance of the wetland. The information varies with the
permit, but typically includes before/after cross-sections, location and elevation of
water control structures, monitoring sites, final boundary of constructed wetlands, list
of plant species, photos, depth of transplanted topsoil, geometry and treatment of
buffer areas, ditch plugs, drain tiles, and boundary markers.
Right of Way
All right-of-way lines may be darkened and the station and offset included for all
right-of-way breakpoints. Location of right-of-way corners may be identified. If the
plan and profile sheets become too crowded when the right-of-way information is
included, this information may be included on a separate plan sheet.
Information regarding access may be included on the As-built plan, including the
limits of access rights purchased and location of constructed and deleted entrances.
The parcel information may include the owner's name and parcel
number. Temporary easements do not need to be shown on the As-built plan.
Land Section Corner Ties
During As-built plan preparation, the final land section corner ties information shall be
reviewed with the District Land Surveyor. A plan sheet of the corrected land section
corner ties shall be included in the As-built plan.
Tied Projects
Tied projects may include references on the As-built plan title sheet that list other
projects included in the contract. Project quantity item numbers should correspond
to the item numbers shown in the contract, by plan. As-built plans for each project
should be completed separately.
As-Built Plans Checklists
See the Iowa DOT Construction Manual Appendix 2-37.5 for checklists to use in
developing As-built plans.
2.73 Intentionally left blank
2.74 Intentionally left blank