| NODIS Library | Program Formulation(7000s) | Search |
NASA
Procedural
Requirements
NPR 7120.5F
Effective Date: August 03, 2021
Expiration Date: August 03,
2026
COMPLIANCE IS MANDATORY FOR NASA EMPLOYEES
NASA Space Flight Program and Project Management
Requirements w/Change 3
Responsible Office: Associate Administrator
NASA Space Flight Program and Project Management Handbook
Table of Contents
Change History
Preface
P.1 Purpose
P.2 Applicability
P.3 Authority
P.4 Applicablcable Documents and Forms
P.5 Measurement/Verification
P.6 Cancellation
Chapter 1. Introduction
1.1 Key Policy Changes to NPR 7120.5 Revision F Since Revision E
1.2 Background
1.3 Overview of Management Process
1.4 Acquisition
1.5 Document Structure
Chapter 2. NASA Life Cycles for Space Flight Programs and
Projects
2.1 Programs and Projects
NPR 7120.5F -- TOC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 1 of 147
NPR 7120.5F -- TOC Page 1 of 147
2.2 Program and Project Life Cycles
2.3 Program and Project Oversight and Approval
2.4 Approving and Maintaining Program and Project Plans, Baselines, and Commitments
Chapter 3. Program and Project Management Roles and
Responsibilities
3.1 Governance
3.2 Roles and Responsibilities
3.3 Technical Authority
3.4 Process for Handling Formal Dissent
3.5 Principles Related to Tailoring Requirements
3.6 Reimbursable Space Flight Work
3.7 Use of the Metric System
Appendix A. Definitions
Appendix B. Acronyms
Appendix C. Compliance Matrix and Tailoring Guidance and
Resources
Appendix D. Program Commitment Agreement Template
D.1 PCA Title Page
D.2 PCA Template
Appendix E. Formulation Authorization Document Template
E.1 Program FAD Title Page
E.2 Project FAD Title Page
E.3 Program/Project FAD Template
Appendix F. Project Formulation Agreement Template
F.1 Formulation Agreement Template Instructions
F.2 Formulation Agreement Title Page
Appendix G. Program Plan Template
G.1 Template Instructions
G.2 Program Plan Title Page
G.3 Program Plan Template
Appendix H. Project Plan Template
NPR 7120.5F -- TOC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 2 of 147
NPR 7120.5F -- TOC Page 2 of 147
H.1 Template Instructions
H.2 Project Plan Title Page
H.3 Project Plan Template
Appendix I. Program and Project Products by Phase
Appendix J. References
LIST OF TABLES
Table 1-1 Programmatic Requirements Hierarchy
Table 2-1 Project Categorization Guidelines
Table 2-2 Convening Authorities for Standing Review Board
Table 2-3 Expected Maturity State Through the Life Cycle of Uncoupled and Loosely Coupled
Programs
Table 2-4 Expected Maturity State Through the Life Cycle of Tightly Coupled Programs
Table 2-5 Expected Maturity State Through the Life Cycle of Projects and Single-Project Programs
Table 2-6 Objectives for Other Reviews
Table C-1 Compliance Matrix
Table D-1 Sample Program Commitment Agreement Activities Log
Table I-1 Uncoupled and Loosely Coupled Program Milestone Products and Control Plans Maturity
Matrix
Table I-2 Tightly Coupled Program Milestone Products Maturity Matrix
Table I-3 Tightly Coupled Program Plan Control Plans Maturity Matrix
Table I-4 Project Milestone Products Maturity Matrix
Table I-5 Project Plan Control Plans Maturity Matrix
Table I-6 Single-Project Program Milestone Products Maturity Matrix
Table I-7 Single-Project Program Plan Control Plans Maturity Matrix
LIST OF FIGURES
Figure 1-1 Institutional Requirements Flow Down
Figure 2-1 Programmatic Authority Organizational Hierarchy
Figure 2-2 NASA Uncoupled and Loosely Coupled Program Life Cycle
Figure 2-3 NASA Tightly Coupled Program Life Cycle
Figure 2-4 NASA Single-Project Program Life Cycle
Figure 2-5 NASA Project Life Cycle
Figure 2 6 Example of Agreements and Commitments in Terms of Cost for Projects
Figure D-1 Program Commitment Agreement Title Page
Figure E-1 Program Formulation Authorization Document Title Page
Figure E-2 Project Formulation Authorization Document Title Page
Figure F-1 Formulation Agreement Title Page
Figure G-1 Program Plan Title Page
Figure H-1 Project Plan Title Page
Figure H-2 Standard Level 2 WBS Elements for Space Flight Projects
NPR 7120.5F -- TOC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 3 of 147
NPR 7120.5F -- TOC Page 3 of 147
Change History
Chg# Approver
Date
Approved
Description/Comments
1 OTPS 03/03/2023 Administrative changes made as follows:
Change Responsible Office
Additions to Appendix A. Definitions
Updates to reflect changes to other NPR and
Handbook numbers, titles, and links
Additional references
Minor editorial and reference corrections.
2 OTPS 07/09/2023 Administrative changes to change responsible
functions from the Office of the Chief Engineer to
the NASA AA as implemented by the Office of the
Chief Program Management Officer (CPMO) in
chapters 2 and 3 and appendices B, C, G, I and J.
Added the role of the CPMO to Section 3.2.
Reinstated missing text in 3.3.2. Added paragraph
3.5.1.a to Tailoring. Updated references to Human
Systems Integration Plan to Human Systems
Integration Approach in chapter 1 and appendices
C, G, H, and I. Updated references to NASA
Standing Review Board Handbook. Appendix E
added Analysis of Alternatives (per GAO-20-68).
Updated Reference Appendix.
3 OTPS 10/27/2023 Updates to reflect changes to timing of ASM
consistent with NPD 1000.5 in chapter 1; Figures
2-2, 2-3, 2-4, and 2-5; and Appendices A, C, E,
and I. Delete references to "Guidance and
Expectations for Small Category 3, Risk
Classification D (Cat3/Class D) Space Flight
Projects with Life-Cycle Cost Under $150
Million" document in chapter 2 and Appendix C.
Updates to clarify "innovative acquisitions".
Updates to reflect changes to other NPR numbers
and titles.
NPR 7120.5F --
ChangeHistory
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 4 of 147
NPR 7120.5F -- ChangeHistory Page 4 of 147
Preface
P.1 Purpose
This document establishes the requirements by which NASA formulates and implements space
flight programs and projects, consistent with the governance model contained in NASA Policy
Directive (NPD) 1000.0, NASA Governance and Strategic Management Handbook.
P.2 Applicability
a. This NASA Procedural Requirements (NPR) is applicable to NASA Headquarters (HQ) and
NASA Centers, including Component Facilities and Technical and Service Support Centers. This
language applies to the Jet Propulsion Laboratory (a Federally Funded Research and Development
Center), other contractors and recipients of grants, cooperative agreements, or other agreements,
only to the extent specified or referenced in the applicable contracts, grants, or agreements.
b. This NPR applies to all NASA space flight programs and projects including spacecraft, launch
vehicles, instruments developed for space flight programs and projects, some research and
technology (R&T) programs and projects
1
, technical facilities specifically developed or
significantly modified for space flight systems, Information Technology (IT) acquired as a part of
space flight programs and projects, and ground systems that are in direct support of space flight
operations. This NPR also applies to reimbursable space flight programs and projects performed for
non-NASA sponsors and to NASA contributions to space flight programs and projects performed
with international and interagency partners.
c. For existing programs and projects, the Revision F changes to the requirements of this NPR apply
to their current and future phases as determined by the responsible Mission Directorate and
concurred with by the NASA Chief Program Management Officer (CPMO) (or as delegated) and the
Decision Authority.
d. This NPR can be applied to other NASA investments at the discretion of the responsible manager
or the NASA Associate Administrator.
e. In this directive, all mandatory actions (i.e., requirements) are denoted by statements containing
the term "shall." The terms "may" or "can" denote discretionary privilege or permission, "should"
denotes a good practice and is recommended but not required, "will" denotes expected outcome, and
"are/is" denotes descriptive material.
1
R&T programs and projects will be managed using NPR 7120.5 in lieu of NPR 7120.8 when: 1) the R&T program or project is
directly funded by a human or robotic space flight program or project; 2) a space flight program or project is directly dependent on
the R&T program or project; 3) the R&T program or project has an LCC greater than $365M and is intended to be flown in space;
4) the R&T program or project includes significant radioactive material (see Section 2.1.3.1), whether or not the system being
developed is for ground or space flight; or 5) as determined by the NASA AA. If clarification or guidance is needed, R&T
programs and projects should consult with the CPMO.
f. In this directive, all document citations are assumed to be the latest version unless otherwise
noted. Documents cited as authority, applicable, or reference documents may be cited as a different
NPR 7120.5F -- Preface
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 5 of 147
NPR 7120.5F -- Preface Page 5 of 147
categorization, which characterizes its function in relation to the specific context.
P.3 Authority
a. The National Aeronautics and Space Act, as amended, 51 U.S.C. § 20113(a).
b. NPD 1000.0, NASA Governance and Strategic Management Handbook.
c. NPD 1000.3, The NASA Organization.
d. NPD 1000.5, Policy for NASA Acquisition.
e. NPD 1001.0, NASA Strategic Plan.
f. NPD 7120.4, NASA Engineering and Program/Project Management Policy.
P.4 Applicable Documents and Forms
a. NASA Federal Acquisition Regulation (FAR) Supplement (NFS), 48 Code of Federal Regulation
(CFR), Chapter 18.
b. NPD 7500.1, Program and Project Life-Cycle Logistics Support Policy.
c. NPD 8020.7, Biological Contamination Control for Outbound and Inbound Planetary Spacecraft.
d. NPR 1040.1, NASA Continuity of Operations (COOP) Planning Procedural Requirements.
e. NPR 1058.1, NASA Enterprise Protection Program.
f. NPR 1600.1, NASA Security Program Procedural Requirements.
g. NPR 2190.1, NASA Export Control Program.
h. NPR 2810.1, Security of Information and Information Systems.
i. NPR 7120.10, Technical Standards for NASA Programs and Projects.
j. NPR 7123.1, NASA Systems Engineering Processes and Requirements.
k. NPR 7150.2, NASA Software Engineering Requirements.
l. NPR 8000.4, Agency Risk Management Procedural Requirements.
m. NPR 8079.1, NASA Spacecraft Conjunction Analysis and Collision Avoidance for Space
Environment Protection.
n. NPR 8580.1, Implementing the National Environmental Policy Act and Executive Order 12114.
o. NPR 8600.1, NASA Capability Portfolio Management Requirements.
p. NPR 8705.2, Human-Rating Requirements for Space Systems.
q. NPR 8705.4, Risk Classification for NASA Payloads.
r. NPR 8715.24, Planetary Protection Provisions for Robotic Extraterrestrial Missions.
NPR 7120.5F -- Preface
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 6 of 147
NPR 7120.5F -- Preface Page 6 of 147
s. NASA/SP-20230001306, NASA Standing Review Board Handbook.
https://ntrs.nasa.gov/citations/20230001306
t. EIA-748, Earned Value Management Systems.
P.5 Measurement/Verification
a. Compliance with this document is verified by submitting the gate products identified in this
document at Key Decision Points (KDPs) to responsible NASA officials and milestone products and
control plans due at life-cycle reviews (LCRs) and by internal and external controls. Internal
controls are consistent with processes per NPD 1200.1, NASA Internal Control. Internal controls
include surveys, audits, and reviews conducted in accordance with NPD 1210.2, NASA Surveys,
Audits, and Reviews Policy. External controls may include external surveys, audits, and reporting
requirements.
b. Compliance is also documented by appending a completed Compliance Matrix for this NPR (see
Appendix C) to the Formulation Agreement for projects in Formulation and/or the Program Plan or
Project Plan (see appendices G or H) for programs or projects entering or in Implementation. A copy
of the Compliance Matrix is forwarded to the CPMO and the Office of the Chief Engineer (OCE) for
programs and Category 1 projects and to the OCE for Category 2 and 3 projects for review.
Organizations with authority to approve waivers or deviations to specific requirements are specified
in Appendix C, Table C-1, Compliance Matrix.
P.6 Cancellation
a. NPR 7120.5E, NASA Space Flight Program and Project Management Requirements, dated
August 14, 2012.
b. NID 7120.130, NASA Space Flight Program and Project Management Requirements - Space
Systems Protection Standard Update.
c. NID 7120.122, Joint Cost and Schedule Confidence Level (JCL) Requirements Updates.
NPR 7120.5F -- Preface
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 7 of 147
NPR 7120.5F -- Preface Page 7 of 147
Chapter 1. Introduction
1.1 Key Policy Changes to NPR 7120.5 Revision F Since Revision
E
1.1.1 Key policy changes in NPR 7120.5F, NASA Space Flight Program and Project Management
Requirements, include updating the requirements for establishing Agency Baseline Commitments
(ABC) and for performing Joint Cost and Schedule Confidence Level (JCL) analyses for tightly
coupled programs, adding additional requirements for doing a JCL analysis for single-project
programs and projects over $1B life-cycle cost (LCC), and using initial capability cost estimates
instead of LCC estimates in specific, identified instances for single-project programs and projects
that plan continuing operations and production, including integration of capability upgrades, with an
unspecified Phase E end point.
1.1.2 Per NPD 1000.0, NASA Governance and Strategic Management Handbook, tailoring is both
accepted and expected. Tailoring guidance has been added to Appendix C along with a reference to
a tailoring Web site that includes resources to facilitate tailoring the requirements in this NPR.
Changes to tailoring guidance include clarifying the process for assigning "non-applicable" to
requirements and modifying stand-alone requirements for program and project control plans;
examples of tailoring approaches used by programs to accommodate their acquisition strategies;
clarification of delegation of tailoring authority; and pre-customization of the NPR 7120.5
Compliance Matrix. Requirements for tailoring are in Section 3.5.
1.1.3 With the release of the NASA-STD-1006, Space System Protection Standard and NPR 1058.1,
NASA Enterprise Protection Program, Space Asset Protection is now the Mission Resiliency and
Protection Program. Programs are no longer required to do a Threat Summary, and Project
Protection Plans need to address the new standard and NPR.
1.1.4 Changes related to governance include updates to program and project acquisition strategy and
planning aligned with NPD 1000.5, Policy for NASA Acquisition; shifted responsibility for
management of independent reviews from the Independent Program Assessment Office to Mission
Directorates; and added program and project consideration for management and utilization of
Agency-level capability components through capability portfolios per NPR 8600.1, NASA
Capability Portfolio Management Requirements. The Dissenting Opinion process is now the Formal
Dissent process, which retains the current process augmented with an expedited escalation path.
1.1.5 Changes to the life cycle include clarification of the criteria triggering a Program
Implementation Review (PIR), adding emphasis to the use of Leading Indicators in life-cycle
reviews (LCRs) and Key Decision Points (KDPs), and providing additional guidance in the NASA
Common Leading Indicators Detailed Reference Guide at
https://nodis3.gsfc.nasa.gov/OCE_rep/OCE_list.cfm.
1.1.6 Updates to program and project documentation and guidance include changes to the Appendix
I table documentation and products developed during the life cycle. This includes the addition of the
Human Systems Integration approach, System Security Plan, Quality Assurance Surveillance Plan,
Orbital Collision Avoidance Plan, and Performance Measurement Baseline and the deletion of the
Education Plan, Information Technology Plan, and Product Data and Life Cycle Management Plan.
In addition, this NPR adds reference to NASA/SP-2016-3424, NASA Project Planning and Control
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 8 of 147
NPR 7120.5F -- Chapter1 Page 8 of 147
In addition, this NPR adds reference to NASA/SP-2016-3424, NASA Project Planning and Control
Handbook.
1.2 Background
1.2.1 NASA space flight programs and projects develop and operate a wide variety of spacecraft,
launch vehicles, in-space facilities, communications networks, instruments, and supporting ground
systems.
2
This document establishes a standard of uniformity for the process by which NASA
formulates and implements space flight programs and projects.
1.2.2 NASA approaches the formulation and implementation of programs and projects through a
governance model that balances different perspectives from different elements of the organization.
The cornerstone of program and project governance is the organizational separation of the
Programmatic Authorities from the Institutional Authorities. The Programmatic Authorities include
the Mission Directorates and their respective programs and projects. The Institutional Authorities
include the Mission Support Directorate and other mission support offices (e.g., engineering, safety
and mission assurance, information technology, procurement, and health and medical) and Center
Directors and Center organizations that align with these mission support offices. (See NPD 1000.0,
NASA Governance and Strategic Management Handbook and NASA/SP-20220009501, NASA
Space Flight Program and Project Management Handbook.)
1.2.3 This NPR distinguishes between "programmatic requirements" and "institutional
requirements." Both categories of requirements ultimately need to be satisfied in program and
project Formulation and Implementation.
1.2.3.1 Programmatic requirements are the responsibility of the Programmatic Authorities.
Programmatic requirements focus on the products to be developed and delivered and specifically
relate to the goals and objectives of a particular NASA program or project. These programmatic
requirements flow down from the Agency's strategic planning process. Table 1-1 shows this flow
down from Agency strategic planning through Agency, directorate, program, and project
requirement levels to the systems that will be implemented to achieve the Agency goals.
2
NASA space flight programs and projects often need to mature technologies to meet mission goals. These enabling and/or
enhancing technologies are also covered by this NPR, insofar as developments of those technologies apply per Section P.2(b)
above.
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 9 of 147
NPR 7120.5F -- Chapter1 Page 9 of 147
Table 1-1 Programmatic Requirements Hierarchy
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 10 of 147
NPR 7120.5F -- Chapter1 Page 10 of 147
Requirements
Level
Content
Governing
Document
Approver Originator
NASA
Strategic Goals
Agency goals,
objectives, and
strategic direction
NPD 1001.0,
NASA Strategic
Plan; and
Strategic Planning
Guidance
NASA
Admin-istrator
OCFO
Mission
Directorate
Requirements
High-level
requirements levied on
a program to carry out
strategic and
architectural direction,
including
programmatic
direction for initiating
specific projects
Program
Commitment
Agreement (PCA)
NASA AA MDAA
Program
Requirements
Detailed requirements
levied on a program to
implement the PCA
and high-level
programmatic
requirements allocated
from the program to its
projects
Program Plan MDAA Program
Manager
Project
Requirements
Detailed requirements
levied on a project to
implement the
Program Plan and flow
down programmatic
requirements allocated
from the program to
the project
Project Plan Program
Manager
Project
Manager
System
Requirements
Detailed requirements
allocated from the
project to the next
lower level of the
project
System
Requirements
Documentation
Project
Manager
Responsible
System Lead
MDAA = Mission Directorate Associate Administrator; NASA AA = NASA Associate
Administrator
1.2.3.2 Institutional requirements are the responsibility of the Institutional Authorities. (See Section
3.3 for details on Technical Authority.) Institutional requirements focus on how NASA does
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 11 of 147
NPR 7120.5F -- Chapter1 Page 11 of 147
business and are independent of any particular program or project. These requirements are issued by
NASA HQ (including the Office of the Administrator, Mission Support Directorate, and other
mission support offices) and by Center organizations. Institutional requirements may respond to
Federal and State statute, regulation, treaty, or Executive Order. They are normally documented in
NPDs, NPRs, NASA Standards, Center Policy Directives, Center Procedural Requirements, and
Mission Directorate requirements.
1.2.4 This NPR is focused on improving program and project performance against internal and
external commitments. Figure 1-1 shows the flow down from NPD 1000.0, NASA Governance and
Strategic Management Handbook through Program and Project Plans. The figure identifies the five
types of institutional requirements that flow down to these plans: engineering, program/project
management, safety and mission assurance, health and medical, and mission support requirements.
These terms are defined in Appendix A.
Figure 1-1 Institutional Requirements Flow Down
1.3 Overview of Management Process
1.3.1 Although this document emphasizes program and project management based on life cycles,
Key Decision Points (KDPs), and evolving programmatic products during each life-cycle phase,
these elements are embedded in NASA's four-part process for managing programs and projects,
which consists of:
a. Formulation—identifying how the program or project supports the Agency's strategic goals;
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 12 of 147
NPR 7120.5F -- Chapter1 Page 12 of 147
assessing feasibility, technology, and concepts; performing trade studies; assessing and possibly
mitigating risks based on risk-informed decision making (RIDM) and continuous risk management
(CRM) processes; maturing technologies; building teams; developing system-level preliminary
designs; developing operations concepts and acquisition strategies; establishing high-level
requirements, requirements flow down, and success criteria; assessing the relevant industrial
base/supply chain to ensure program or project success; preparing plans, cost estimates, budget
submissions, and schedules essential to the success of a program or project; and establishing control
systems to ensure performance of those plans and alignment with current Agency strategies.
b. Approval (for Implementation)—acknowledgment by the Decision Authority (see Appendix A for
definition of "Decision Authority") that the program/project has met Formulation requirements and
is ready to proceed to Implementation. By approving a program/project, the Decision Authority
commits to the time-phased cost plan based on technical scope and schedule necessary to continue
into Implementation.
c. Implementation—execution of approved plans for the development and operation of the
program/project and use of control systems to ensure performance to approved plans and
requirements and continued alignment with the Agency's strategic goals.
d. Evaluation—continual self and independent assessment of the performance of a program or
project and incorporation of the assessment findings to ensure adequacy of planning and execution
according to approved plans and requirements.
1.4 Acquisition
1.4.1 NASA's program and project support of its overall mission is long term in nature, but the
environment in which these programs and projects are conducted is dynamic. In recognition of this,
NPD 1000.0, NASA Governance and Strategic Management Handbook and NPD 1000.5, Policy for
NASA Acquisition have put in place a framework for ensuring that NASA's strategic vision,
programs and projects, and resources remain properly aligned. The acquisition process and annual
strategic resource planning form a continuous process to oversee this alignment. In addition, the
Agency's senior Acquisition Strategy Council (ASC) makes decisions regarding strategic resource
planning, specific acquisition strategy approval, and acquisition policy integration and performance.
1.4.2 All programs and projects implement acquisitions consistent with NPD 1000.5, Policy for
NASA Acquisition. At the program and project level, the Decision Framing Meeting or the
Pre-Acquisition Strategy Meeting (Pre-ASM), the Acquisition Strategy Meeting (ASM), and the
Procurement Strategy Meeting (PSM) support the Agency's acquisition process, which includes
strategic planning as well as procurement. Information on Decision Framing Meetings or Pre-ASMs,
and on ASMs, the associated convening authorities, and criteria for determining the convening
authority is provided in NPD 1000.5, Policy for NASA Acquisition, NASA Advisory
Implementing Instruction (NAII) 1000.1 Decision Framing Meeting (DFM) and Pre-Acquisition
Strategy Meeting (Pre-ASM) Guide, and NAII 1000.2 Acquisition Strategy Meeting (ASM) Guide.
The PSM is described in NASA FAR Supplement (NFS) 1807.170-71. The PSM guide may be
accessed at Office of Procurement - NASA PSM Guide.pdf - Agency-Wide Procurement Templates
(sharepoint.com) or by contacting the Office of Procurement.
1.5 Document Structure
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 13 of 147
NPR 7120.5F -- Chapter1 Page 13 of 147
1.5.1 Chapter 2 defines the different types of programs and projects, their documents, and how they
mature through their different life cycles. It also describes how to establish baselines and approval
processes. Chapter 3 describes roles and responsibilities relevant to program and project managers,
the governance structure, Technical Authority (TA), the dissent process, and how to tailor
requirements. Appendix C contains the Compliance Matrix and tailoring guidance and resources.
Templates for required program and project documents are contained in appendices D through H.
Appendix I encompasses the tables of program and project products by phase. Appendix J provides
a list of references.
1.5.2 The companion handbook to this NPR, NASA/SP-20220009501, NASA Space Flight Program
and Project Management Handbook, describes how programs and projects are managed in NASA
and contains explanatory material and context to help understand the requirements of this NPR and
how to implement them. In addition, NASA/SP-20230001306, NASA Standing Review Board
Handbook is closely aligned to this NPR and provides guidance for the planning, preparation,
review, reporting, and closeout of Standing Review Board (SRB) activities. These Handbooks can be
found on the "Other NASA-Level Documents" menu in the NASA Online Directives Information
System (NODIS) under the tab for the Office of the Chief Engineer (OCE).
NPR 7120.5F -- Chapter1
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 14 of 147
NPR 7120.5F -- Chapter1 Page 14 of 147
Chapter 2. NASA Life Cycles for Space Flight
Programs and Projects
2.1 Programs and Projects
2.1.1 Space flight programs and projects flow from the implementation of national priorities, defined
in the Agency’s Strategic Plan, through the Agency’s Mission Directorates, as part of the Agency’s
general work breakdown hierarchy shown in Figure 2-1.
Figure 2-1 Programmatic Authority Organizational Hierarchy
2.1.1.1 This hierarchical relationship of programs to projects shows that programs and projects are
different, and their management involves different activities and focus. Programs and projects are
distinguished by the following characteristics.
a. Program—Programs are a strategic investment by Mission Directorates or mission support offices
with a defined architecture and/or technical approach, requirements, funding level, and a
management structure that initiates and directs one or more projects. A program implements a
strategic direction that the Agency has identified as needed to accomplish Agency goals and
objectives.
b. Project—Space flight projects are a specific investment identified in a Program Plan having
defined requirements, a life-cycle cost, a beginning, and an end. A project also has a management
structure and may have interfaces to other projects, agencies, and international partners. A project
yields new or revised products that directly address NASA’s strategic goals.
2.1.1.2 Regardless of the structure of a program or project meeting the criteria of Section P.2, this
NPR shall apply to the full scope of the program or project and all the activities under it. Specific
NPR 7120.5 requirements are flowed down to these activities to the extent necessary for the program
or project to ensure compliance and mission success. See Section 3.5.5.1 for the process of obtaining
any required deviations or waivers.
2.1.2 NASA Programs
2.1.2.1 NASA space flight programs are initiated and implemented to accomplish scientific or
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 15 of 147
NPR 7120.5F -- Chapter2 Page 15 of 147
exploration goals that generally require a collection of mutually supporting projects. Programs
integrate and manage these projects over time and provide on-going enabling systems, activities,
methods, technology developments, and feedback to projects and stakeholders. Programs are
generally created by a Mission Directorate with a long-term horizon in mind, though as the
Agency’s strategic direction or circumstances change, a Mission Directorate occasionally needs to
replan its programs or combine related programs to increase effectiveness. Programs are generally
executed at NASA Centers under the direction of the Mission Directorate and are assigned to
Centers based on decisions made by Agency senior management consistent with the results of the
Agency’s strategic acquisition planning process. Because the scientific and exploration goals of
programs vary significantly, different program implementation strategies are required, ranging from
simple to complex. To accommodate these differences, NASA identifies four basic types of
programs (described below and defined in Appendix A) that may be employed: single-project
programs, uncoupled programs, loosely coupled programs, and tightly coupled programs.
Characteristics of the program types are:
a. Single-Project: These programs (e.g., James Webb Space Telescope) tend to have long
development and operational lifetimes and represent a large investment of Agency resources.
Multiple organizations or agencies contribute to them. Single-project programs have one project and
implement their program objectives and requirements through one of two management approaches:
(1) separate program and project structures or (2) a combined structure. The requirements for both
programs and projects apply to single-project programs as described in this NPR.
b. Uncoupled: These programs (e.g., Discovery Program) are implemented under a broad theme
(like planetary science) and/or a common program implementation mechanism, such as providing
flight opportunities for formally competed cost-capped projects or Principal Investigator (PI)-led
missions and investigations. Each project in an uncoupled program is independent of the other
projects within the program.
c. Loosely Coupled: These programs (e.g., Mars Exploration Program) address specific objectives
through multiple space flight projects of varied scope. While each project has an independent set of
mission objectives, the projects as a whole have architectural and technological synergies and
strategies that benefit the program. For example, Mars orbiters designed for more than one Mars
year in orbit are required to carry a communication system to support present and future landers.
d. Tightly Coupled: These programs have multiple projects that execute portions of a mission or
missions. No single project is capable of implementing a complete mission. Typically, multiple
NASA Centers contribute to the program. Individual projects may be managed at different Centers.
The program may also include other agency or international partner contributions.
2.1.3 NASA Projects
2.1.3.1 As with programs, projects vary in scope and complexity and thus require varying levels of
management requirements and Agency attention and oversight. Consequently, project categorization
defines Agency expectations of project managers by determining both the oversight council and the
specific approval requirements. Projects are Category 1, 2, or 3 and shall be assigned to a category
based initially on: (1) the project life-cycle cost (LCC) estimate, the inclusion of significant
radioactive material
3
, and whether or not the system being developed is for human space flight; and
(2) the priority level, which is related to the importance of the activity to NASA, the extent of
international participation (or joint effort with other government agencies), the degree of uncertainty
surrounding the application of new or untested technologies, and spacecraft/payload development
risk classification. (See NPR 8705.4, Risk Classification for NASA Payloads.) Guidelines for
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 16 of 147
NPR 7120.5F -- Chapter2 Page 16 of 147
determining project categorization are shown in Table 2-1, but categorization may be changed based
on recommendations by the Mission Directorate Associate Administrator (MDAA), who considers
additional risk factors facing the project. Projects that plan continuing operations and production,
including integration of capability upgrades, with an unspecified Phase E end point are assigned to
Category 1 unless otherwise agreed to by the Decision Authority. (See Section 2.4.1.3.b and Section
2.4.1.6.) The NASA Associate Administrator (AA) approves the final project categorization. The
project category is identified in the Formulation Authorization Document (FAD) and Project Plan
and documented in the KDP B Decision Memorandum. The Office of the Chief Financial Officer
(OCFO) is responsible for the official listing of NASA programs and projects.
4
For purposes of
project categorization, the project LCC estimate includes phases A through F and all Work
Breakdown Structure (WBS) Level 2 elements and is measured in real-year (nominal) dollars.
3
Significant radioactive material is defined as levels of radioactive material onboard the spacecraft and/or launch vehicle that
require nuclear launch authorization by the NASA Administrator or Executive Office of the President as described in NPR
8715.26, Nuclear Flight Safety.
4
This data is maintained by OCFO in a database called the Meta-Data Manager (MdM). This database is the basis for the
Agency's work breakdown and forms the structure for program and project status reporting across all Mission Directorates and
mission support offices.
Table 2-1 Project Categorization Guidelines
Priority Level LCC < $365M $365M ≤ LCC ≤ $2B
LCC > $2B,
significant
radioactive material,
or human space
flight
High Category 2 Category 2 Category 1
Medium Category 3 Category 2 Category 1
Low Category 3 Category 2 Category 1
2.1.3.2 When projects are initiated, they are assigned to a NASA Center or implementing
organization by the MDAA consistent with direction and guidance from the strategic planning
process. They are either assigned directly to a Center by the Mission Directorate or are selected
through a competitive process such as an Announcement of Opportunity (AO).
5
For Category 1
projects, the assignment of a project to a Center or implementing organization shall be with the
concurrence of the NASA AA.
5
As part of the process of assigning projects to NASA Centers, the affected program manager may recommend project
assignments to the MDAA.
2.1.4 Program and Project Manager Certification
2.1.4.1 Programs and projects with a LCC or initial capability cost (see Section 2.4.1.3.b) greater
than $250M shall be managed by program and project managers who have been certified in
compliance with Office of Management and Budget (OMB)’s promulgated Federal acquisition
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 17 of 147
NPR 7120.5F -- Chapter2 Page 17 of 147
program/project management certification requirements. This certification is required within one
year of appointment. Further information on how NASA is implementing program and project
manager certification can be found in the NASA Space Flight Program and Project Management
Handbook.
2.2 Program and Project Life Cycles
2.2.1 Program and project managers shall follow their appropriate life cycle as identified in each
program and project respective life-cycle figure. Life cycles include life-cycle phases, gates, and
major events; performing KDPs and major life-cycle reviews (LCRs); developing principal
documents that govern the conduct of each phase; and re-entering the life cycle when program or
project changes warrant such action.
2.2.2 Each program and project performs the work required for each phase, which is described in the
NASA Space Flight Program and Project Management Handbook; NASA/SP-2016-3424, NASA
Project Planning and Control Handbook, which covers the functions and activities of the planning
and control community; NPR 7123.1, NASA Systems Engineering Processes and Requirements;
and NPR 7150.2, NASA Software Engineering Requirements. Program and project managers shall
organize the work required for each phase using a product-based WBS developed in accordance with
the Program and Project Plan templates (appendices G and H). Additional information on the NASA
WBS structure is provided in the NASA Work Breakdown Structure (WBS) Handbook,
NASA/SP-2010-3404, which can be found in NODIS on the OCE tab under the “Other
NASA-Level Documents” menu. When an alternate approach provides for better program/project
implementation, the program/project manager should tailor the requirement as noted in the
Compliance Matrix. (See Appendix C.)
2.2.3 The documents shown on the life-cycle figures and described below shall be prepared in
accordance with the templates in appendices D, E, F, G, and H.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 18 of 147
NPR 7120.5F -- Chapter2 Page 18 of 147
Figure 2-2 NASA Uncoupled and Loosely Coupled Program Life Cycle
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 19 of 147
NPR 7120.5F -- Chapter2 Page 19 of 147
Figure 2-3 NASA Tightly Coupled Program Life Cycle
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 20 of 147
NPR 7120.5F -- Chapter2 Page 20 of 147
Figure 2-4 NASA Single-Project Program Life Cycle
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 21 of 147
NPR 7120.5F -- Chapter2 Page 21 of 147
Figure 2-5 NASA Project Life Cycle
2.2.3.1 The program FAD (see Appendix E) is prepared by the Mission Directorate and authorizes a
program manager to initiate the planning of a new program and to perform the analysis of
alternatives required to formulate a sound Program Plan that contains project elements,
requirements, schedules, and time-phased cost plans.
2.2.3.2 The Program Commitment Agreement (PCA) (see Appendix D) is an agreement between the
MDAA and the NASA AA (the Decision Authority) that authorizes program transition from
Formulation to Implementation. The PCA is prepared by the Mission Directorate and documents
Agency requirements that flow down to the program, Mission Directorate requirements, program
objectives, management and technical approach and associated architecture, technical performance,
schedule, time-phased cost plans, safety and risk factors, internal and external agreements, LCRs,
and all attendant top-level program requirements.
2.2.3.3 The Program Plan (see Appendix G) is an agreement between the MDAA (who has final
approval authority for the plan), the participating Center Director(s), and the program manager. It
documents at a high level the program’s objectives and requirements, scope, implementation
approach, interfaces with other programs, environment within which the program operates, funding
by time-phased cost plans consistent with the approved PCA, and commitments of the program. The
Program Plan is prepared by the program.
2.2.3.4 The project FAD (see Appendix E) is prepared by the Mission Directorate. It authorizes a
project manager to initiate the planning of a new project and to perform the analysis of alternatives
required to formulate a sound Formulation Agreement and subsequent Project Plan. The FAD
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 22 of 147
NPR 7120.5F -- Chapter2 Page 22 of 147
contains requirements, schedules, and project funding requirements.
2.2.3.5 The Formulation Agreement (see Appendix F) is prepared by the project in response to the
FAD to establish the technical and acquisition work that needs to be conducted during Formulation
and defines the schedule and funding requirements during Phase A and Phase B for that work.
2.2.3.6 The Project Plan (see Appendix H) is an agreement among the MDAA; the program
manager; participating Center Director(s); the project manager; and for AO-selected missions, the
principal investigator.
6
The Project Plan is prepared by the project manager with the support of the
project team and defines at a high level the project’s objectives, technical and management
approach, environment within which the project operates, and commitments of the project to the
program.
6
A principal investigator is a person who conceives an investigation and is responsible for carrying it out and reporting its results.
In some cases, principal investigators from industry and academia act as project managers for smaller development efforts with
NASA personnel providing oversight.
2.2.4 Each program and project shall perform the LCRs in accordance with NPR 7123.1, applicable
Center practices, and the requirements of this document. These reviews provide a periodic
assessment of the program’s or project’s technical and programmatic status and health at key points
in the life cycle using six criteria: alignment with and contribution to Agency strategic goals,
adequacy of management approach, adequacy of technical approach, adequacy of the integrated cost
and schedule estimates and funding strategy, adequacy and availability of resources other than
budget, and adequacy of the risk management approach. (For further guidance on addressing the six
criteria, see NASA/SP-20230001306, NASA Standing Review Board Handbook.) LCRs that occur
at the end of each life-cycle phase are complete when the governing Program Management Council
(PMC) and Decision Authority complete their assessment at the KDP and sign the Decision
Memorandum. (See Section 2.4.1.)
2.2.4.1 NASA programs and projects that leverage commercial partnerships or other practices (e.g.,
Commercial Crew Program) may employ tailoring approaches to accommodate their acquisition
strategies. Examples of tailoring approaches used by these programs are provided on the Agency
Tailoring Web site at https://appel.nasa.gov/npr-7120-5-tailoring-resources.
2.2.4.2 The need for a PIR LCR is determined in one of two ways:
a. The NASA AA determines the need for a PIR based on the occurrence of a trigger and discussion
with the Convening Authorities. The MDAA or an independent team member (Technical
Authorities (TAs), OCFO) report to the NASA AA that a trigger for discussing the need for a PIR
has occurred. This is reported at the Agency Program Management Council (APMC) during the
annual review of Mission Directorate Independent Assessment Manifests. (For considerations that
trigger a discussion on the need for a PIR see the NASA Space Flight Program and Project
Management Handbook, Section 5.11.3.)
b. The NASA AA or MDAA, per their discretion, determine that a PIR is needed.
2.2.4.3 Programs or projects that implement major upgrades as referenced in Section 2.4.1.6 will
enter the life cycle at the appropriate LCR within the Formulation Phase. If other upgrades to a
program or project are needed between flights, the program or project will re-enter the life cycle and
perform the LCRs as necessary to demonstrate technical, cost, and schedule maturity for those
upgrades through the applicable Formulation and/or Implementation phases.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 23 of 147
NPR 7120.5F -- Chapter2 Page 23 of 147
2.2.5 Program or project managers and an independent Standing Review Board (SRB) shall conduct
the System Requirements Review (SRR), System Definition Review (SDR)/ Mission Definition
Review (MDR), Preliminary Design Review (PDR), Critical Design Review (CDR), System
Integration Review (SIR), Operational Readiness Review (ORR), and PIR LCRs in figures 2-2, 2-3,
2-4, and 2-5. LCRs that do not require an SRB will be convened by the Center Director (or
designee) of the Center responsible for the program or project management.
a. The program or project manager determines whether one- or two-step reviews will be conducted.
(See the NASA/SP-20230001306, NASA Standing Review Board Handbook and the NASA Space
Flight Program and Project Management Handbook for further guidance on the review processes
conducted by the SRB, including one- and two-step reviews.)
2.2.5.1 NASA accords special importance to the policies and procedures established to ensure the
integrity of the SRB’s independent review process and to comply with Federal law. The Conflict of
Interest (COI) procedures detailed in the NASA Standing Review Board Handbook shall be strictly
adhered to.
2.2.5.2 The portion of the LCRs conducted by the SRB shall be convened by the Convening
Authorities in accordance with Table 2-2. The scope and requirements for this review will be
documented in a Terms of Reference (ToR), for which there is a template in the NASA Standing
Review Board Handbook.
Table 2-2 Convening Authorities for Standing Review Board
Decision Authority Technical Authority
Chief
Financial
Officer**
NASA AA MDAA NASA CE* Center Director(s)
Programs Approve Approve Concur Approve Concur
Category 1 Projects Approve Approve Concur Approve Concur
Category 2 Projects Approve Concur Approve Concur
Category 3 Projects Approve Approve Concur
NASA CE = NASA Chief Engineer
*Concurrence is obtained via coordination with designated Mission Directorate Chief Engineer.
** Concurrence is obtained via coordination with designated OCFO point of contact (POC) embedded in the Mission
Directorate.
NOTE: LCR entrance and success criteria in NPR 7123.1 and the life-cycle phase and
KDP information in the NASA Space Flight Program and Project Management Handbook
provide specifics for addressing the six criteria required to demonstrate the program or
project has met expected maturity state.
2.2.5.3 The program or project manager, the SRB chair, and the Center Director (or designated
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 24 of 147
NPR 7120.5F -- Chapter2 Page 24 of 147
2.2.5.3 The program or project manager, the SRB chair, and the Center Director (or designated
Engineering Technical Authority (ETA) representative) shall mutually assess the program or
project's expected readiness for the LCR and report any disagreements to the Decision Authority for
final decision. The assessment occurs approximately 30 to 90 calendar days prior to the LCR.
2.2.5.4 The Decision Authority may request the SRB to conduct other reviews identified on figures
2-2, 2-3, 2-4, and 2-5 or special reviews identified in Section 2.2.9. The Decision Authority may
also request other special reviews that may or may not be conducted by the SRB. Examples of
situations that may prompt such reviews include long periods of time (as determined at the
discretion of the Decision Authority) between LCRs, between an LCR and when the subsequent
KDP is scheduled, and between KDPs; key junctures in the life cycles of major programs, projects,
or missions; and key aspect(s) of programs, projects, or missions of particular interest to the Agency.
(See the NASA Space Flight Program and Project Management Handbook, Sections 3.1.3 and 4.1.3
for more information about special reviews.) The Decision Authority may also request informational
briefings.
2.2.6 In preparation for these LCRs, the program or project manager shall generate the appropriate
documentation per the Appendix I tables of this document, NPR 7123.1, and Center practices, as
necessary, to demonstrate that the program’s or project’s definition and associated plans are
sufficiently mature to execute the follow-on phase(s) with acceptable technical, safety, and
programmatic risk.
2.2.6.1 For a single-project program that is implemented through separate program and project
structures, the MDAA and single-project program manager will determine which of the documents
in the tables are produced by the program and which are produced by the project. In both
management approaches, the Program and Project Plans may be combined if approved by the
MDAA.
2.2.7 Each program and project proceeds through the KDPs identified in its respective life-cycle
figure. A KDP is the event where the Decision Authority determines the readiness of a program or
project to progress to the next phase of the life cycle and establishes the content, cost, and schedule
commitments for the ensuing phase(s). Transition to the following phase occurs immediately
following KDP approval except for the transition from Phase D to E, where transition occurs
following on-orbit checkout. KDPs associated with uncoupled, loosely coupled, and tightly coupled
programs are designated with Roman numerals and zero. The first KDP is KDP 0; the second is KDP
I, etc. KDPs for projects and single-project programs are designated with letters, i.e., KDP A, KDP
B, etc.
2.2.7.1 For missions selected as a result of an AO, KDP A is the selection of a Step 1 proposal for
concept development. In a one-step AO process, projects enter Phase A after selection (KDP A) and
the process becomes conventional. In a two-step AO process, projects are down-selected following
evaluation of concept study reports and the down-selection serves as KDP B. Following this
selection, the process becomes conventional with the exception that products normally required at
KDP B that require Mission Directorate input or approval will be finished as early in Phase B as
feasible.
2.2.8 Projects, single-project programs (and other programs at the discretion of the MDAA) with a
life-cycle cost (LCC) or initial capability cost (see Section 2.4.1.3.b) estimated to be greater than
$250M shall perform earned value management (EVM) and comply with EIA-748, Earned Value
Management Systems for all portions of work including in-house and contracted portions of the
project. To ensure that projects meet KDP C requirements, EVM System (EVMS) setup and
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 25 of 147
NPR 7120.5F -- Chapter2 Page 25 of 147
implementation efforts begin as soon as a project begins to develop the WBS, Organizational
Breakdown Structure, and Integrated Master Schedule (IMS). EVM reporting to the performance
measurement baseline begins during Phase B and continues as long as EVM applies for the
remaining phases.
2.2.8.1 Program and project managers with programs and projects subject to EVM shall utilize the
NASA EVM Capability Process for in-house work. NASA's EVM Capability Process can be found
on the Program and Project Management Community of Practice at https://nen.nasa.gov/web/evm
by selecting “Document Repository” under the “Community Navigation” section. For programs and
projects with an LCC or initial capability cost less than $250M, EVM is optional on the in-house
work portion, however EVM may be implemented at the discretion of the project manager. An
EVMS is not required on non-developmental work, steady state operations, or basic and applied
research.
2.2.8.2 EVM system requirements for contracted work shall be applied to suppliers in accordance
with the NASA Federal Acquisition Regulation (FAR) Supplement, independent of phase and the
$250M threshold (https://www.hq.nasa.gov/office/procurement/regs/NFS.pdf.). For contracts that
require EVM, an Integrated Program Management Report (IPMR) and WBS are the Data
Requirements Descriptions (DRDs) that are included in the contract and/or agreement.
2.2.8.3 Integrated Baseline Reviews (IBRs) are required whenever EVM is required. Mission
Directorates shall conduct an IBR in preparation for KDP C and for major changes that significantly
impact the cost and schedule baseline. For contracts, refer to the NASA FAR Supplement for IBR
requirements.
2.2.8.4 EVMS surveillance shall be conducted on contracts and on programs and projects with
in-house work to ensure continued compliance with EIA-748, Earned Value Management Systems.
2.2.9 The Office of the Administrator, MDAA, or the Center Director (or designee) may also
convene special reviews as they determine the need. In these cases, the MDAA or a Technical
Authority forms a special review team composed of relevant members of the SRB and additional
outside expert members as needed. The process followed for these reviews is the same as for other
reviews. The special review team is dissolved following resolution of the issue(s) that triggered its
formation.
2.2.10 Program and project managers shall complete and maintain a Compliance Matrix (see
Appendix C) for this NPR and attach it to the Formulation Agreement for projects in Formulation
and/or the Program or Project Plan. The program or project will use the Compliance Matrix to
demonstrate how it is complying with the applicable program or project requirements of this
document.
2.2.11 Single-project programs and projects shall develop a Project Protection Plan that addresses
NASA-STD-1006, Space System Protection Standard in accordance with NPR 1058.1, NASA
Enterprise Protection Program. (A copy of the Project Protection Plan Template can be found at
https://nen.nasa.gov/web/sap.)
2.3 Program and Project Oversight and Approval
2.3.1 Each program and project shall have a Decision Authority, the Agency’s responsible individual
who determines whether and how the program or project proceeds through the life cycle and the key
program or project cost, schedule, and content parameters that govern the remaining life-cycle
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 26 of 147
NPR 7120.5F -- Chapter2 Page 26 of 147
program or project cost, schedule, and content parameters that govern the remaining life-cycle
activities. For programs and Category 1 projects, the Decision Authority is the NASA AA. The
NASA AA may delegate this authority to the MDAA. For Category 2 and 3 projects, the Decision
Authority is the MDAA. The MDAA may delegate some of their Programmatic Authority to
appropriate Mission Directorate staff or to Center Directors. Decision authority may be delegated to
a Center Director for determining whether Category 2 and 3 projects may proceed through KDPs
into the next phase of the life cycle. However, the MDAA will retain authority for all program-level
requirements, funding limits, launch dates, and any external commitments.
2.3.1.1 The MDAA shall inform the NASA AA and Administrator via email on all Agency Baseline
Commitments (ABCs) per the following: inform the NASA AA on ABCs for single-project
programs and projects with a LCC or initial capability cost (see Section 2.4.1.3.b) greater than
$250M; and inform the NASA Administrator on ABCs for all single-project programs and projects
with a LCC or initial capability cost greater than $1B and all Category 1 projects. (See Section
2.4.1.5 for more information on ABCs.)
2.3.2 To ensure the appropriate level of management oversight, NASA has established two levels of
PMCs—the Agency PMC (APMC) and Mission Directorate PMCs (DPMCs). The PMCs have the
responsibility for periodically evaluating the technical, safety, health and medical, and programmatic
performance (including cost, schedule, risk, and risk mitigation) and content of a program or project
under their purview. These evaluations focus on whether the program or project is meeting its
commitments to the Agency. Each program and project shall have a governing PMC. For all
programs and Category 1 projects, the governing PMC is the APMC; for Category 2 and 3 projects,
the governing PMC is the DPMC. The PMC function may be delegated by the Decision Authority to
the Center Management Council (CMC) in the event the Decision Authority is delegated to the
Center.
2.3.3 The Decision Authority and governing PMC for the program or project are documented in the
applicable authority documents: Program Commitment Agreement (PCA), Formulation
Authorization Document (FAD), Formulation Agreement, Program Plan, and Project Plan.
Delegations of Decision Authority and delegations of governing PMCs are documented in the
applicable authority documents (PCA, Formulation Agreement, Program Plan, Project Plan).
Templates for the PCA, FAD, Formulation Agreement, Program Plan, and Project Plan are provided
in appendices D, E, F, G, and H, respectively. These templates identify what is documented in each
authority document.
2.3.4 The Center Director (or designee) shall oversee programs and projects usually through the
CMC, which monitors and evaluates all program and project work (regardless of category) executed
at that Center. The CMC evaluation focuses on whether Center engineering, Safety and Mission
Assurance (SMA), health and medical, and management best practices (e.g., program and project
management, resource management, procurement, institutional best practices) are being followed by
the program or project under review and whether Center resources support program/project
requirements. The CMC also assesses program and project risk and evaluates the status and progress
of activities to identify and report trends and provide guidance to the Agency and affected programs
and projects. The CMC provides its findings and recommendations to program or project managers
and to the appropriate PMCs regarding the performance and technical and management viability of
the program or project prior to KDPs.
2.3.4.1 For programs and projects that are conducted by multiple Centers, an Integrated Center
Management Council (ICMC) should be used where the Center Director (or designee) of each
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 27 of 147
NPR 7120.5F -- Chapter2 Page 27 of 147
Center with substantial contributions is a member of the ICMC. The ICMC is chaired by the Center
Director (or representative) responsible for the program/project management.
2.3.5 Following each LCR, the independent SRB chair and the program or project manager shall
brief the applicable management councils on the results of the LCR to support the councils’
assessments. The final LCR in a given life-cycle phase provides essential information for the KDP,
which marks the end of that life-cycle phase except for transition from Phase D to E, where
transition occurs following on-orbit checkout and initial operations. To support the Decision
Authority’s determination of the readiness of a program or project to progress to the next phase of
the life cycle, the program manager (for projects in their program), the Center Director, the MDAA
(for programs and Category 1 projects), and the governing PMC provide their assessments and
recommendations with supporting data, as necessary. Tables 2-3 through 2-6 define for each LCR
and each KDP the LCR objectives and the expected maturity state at the subsequent KDP. (The
NASA Space Flight Program and Project Management Handbook provides further details.)
Table 2-3 Expected Maturity State Through the Life Cycle
of Uncoupled and Loosely Coupled Programs
KDP
Review
Associated
Life-cycle
Review
LCR Objectives
Overall Expected Maturity
State at KDP
KDP 0 SRR
To evaluate whether the
program functional and
performance requirements are
properly formulated and
correlated with the Agency and
Mission Directorate strategic
objectives and assess the
credibility of the program’s
estimated budget and schedule.
Program addresses critical NASA
needs and can likely be achieved
as conceived.
KDP I SDR
To evaluate the proposed
program requirements/
architecture and allocation of
requirements to initial projects,
assess the adequacy of project
pre-Formulation efforts, and
determine whether the maturity
of the program’s definition and
associated plans are sufficient to
begin implementation.
Program is in place and stable,
addresses critical NASA needs,
has adequately completed
Formulation activities, has an
acceptable plan for
Implementation that leads to
mission success, has proposed
projects that are feasible within
available resources, and has risks
that are commensurate with the
Agency’s expectations.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 28 of 147
NPR 7120.5F -- Chapter2 Page 28 of 147
KDP II
to KDP
n
PIR
To evaluate the program’s
continuing relevance to the
Agency’s Strategic Plan, assess
performance with respect to
expectations, and determine the
program’s ability to execute the
implementation plan with
acceptable risk within cost and
schedule constraints.
Program still meets Agency needs
and is continuing to meet Agency
commitments, as planned.
NOTE: LCR entrance and success criteria in NPR 7123.1 and the life-cycle phase and
KDP information in the NASA Space Flight Program and Project Management Handbook
provide specifics for addressing the six criteria required to demonstrate the program or
project has met expected maturity state.
Table 2-4 Expected Maturity State
Through the Life Cycle of Tightly Coupled Programs
KDP
Review
Associated
Life-cycle
Review
LCR Objectives
Overall Expected
Maturity State at KDP
KDP 0
SRR
To evaluate whether the functional
and performance requirements
defined for the system are responsive
to the Mission Directorate
requirements on the program and its
projects and represent achievable
capabilities.
Program addresses critical
NASA needs, and projects
are feasible within
available resources.
SDR
To evaluate the credibility and
responsiveness of the proposed
program requirements/architecture to
the Mission Directorate requirements
and constraints, including available
resources, and allocation of
requirements to projects. To
determine whether the maturity of
the program’s mission/system
definition and associated plans are
sufficient to begin preliminary
design.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 29 of 147
NPR 7120.5F -- Chapter2 Page 29 of 147
KDP I PDR
To evaluate the
completeness/consistency of the
program’s preliminary design,
including its projects, in meeting all
requirements with appropriate
margins, acceptable risk, and within
cost and schedule constraints, and to
determine the program’s readiness to
proceed with the detailed design
phase of the program.
Program is in place and
stable, addresses critical
NASA needs, has
adequately completed
Formulation activities,
and has an acceptable
plan for Implementation
that leads to mission
success. Proposed projects
are feasible with
acceptable risk within
Agency cost and schedule
baselines.
KDP II
CDR
To evaluate the integrity of the
program integrated design, including
its projects and ground systems. To
meet mission requirements with
appropriate margins and acceptable
risk within cost and schedule
constraints. To determine if the
integrated design is appropriately
mature to continue with the final
design and fabrication phase.
Program is still on plan.
The risk is commensurate
with the projects’ payload
classifications. The
program is ready for
Assembly, Integration,
and Test (AI&T) with
acceptable risk within
Agency cost and schedule
baselines.
SIR
To evaluate the readiness of the
program, including its projects and
supporting infrastructure, to begin
system AI&T with acceptable risk
and within cost and schedule
constraints.
KDP III
ORR
To evaluate the readiness of the
program, including its projects,
ground systems, personnel,
procedures, and user documentation.
To operate the flight system and
associated ground systems in
compliance with program
requirements and constraints during
the operations phase.
Program is ready for
launch and early
operations with acceptable
risk within Agency cost
and schedule baselines.
FRR or
MRR
To evaluate the readiness of the
program and its projects, ground
systems, personnel, and procedures
for a safe and successful launch and
flight/mission.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 30 of 147
NPR 7120.5F -- Chapter2 Page 30 of 147
flight/mission.
Non-KDP
Mission
Operations
Reviews
PLAR
To evaluate the in-flight
performance of the program and its
projects. To determine the program's
readiness to begin the operations
phase of the life cycle and transfer
responsibility to the operations
organization.
PLAR Expected State:
Project is ready to conduct
mission operations with
acceptable risk within
Agency cost and schedule
baselines.
CERR
To evaluate the readiness of the
program and its projects to execute a
critical event during the flight
operations phase of the life cycle.
Mission CERR Expected
State: Project is ready to
conduct critical mission
activity with acceptable
risk.
PFAR
To evaluate how well mission
objectives were met during a human
space flight mission. To evaluate the
status of the flight and ground
systems, including the identification
of any anomalies and their
resolution.
PFAR Expected State: All
anomalies that occurred in
flight are identified, and
actions necessary to
mitigate or resolve these
anomalies are in place.
KDP IV to
KDP n-1
PIR
To evaluate the program's continuing
relevance to the Agency's Strategic
Plan, assess performance with
respect to expectations, and
determine the program's ability to
execute the implementation plan
with acceptable risk within cost and
schedule constraints.
Program still meets
Agency needs and is
continuing with
acceptable risk within
Agency cost and schedule
baselines.
KDP n DR
To evaluate the readiness of the
program and its projects to conduct
closeout activities, including final
delivery of all remaining
program/project deliverables and
safe decommissioning/disposal of
space flight systems and other
program/project assets.
Program
decommissioning is
consistent with program
objectives and is ready for
final analysis and archival
of mission and science
data and safe disposal of
its assets.
CERR Critical Events Readiness Review PLAR Post-Launch Assessment Review
FRR Flight Readiness Review PFAR Post-Flight Assessment Review
MRR Mission Readiness Review DR Decommissioning Review
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 31 of 147
NPR 7120.5F -- Chapter2 Page 31 of 147
NOTE: LCR entrance and success criteria in NPR 7123.1 and the life-cycle phase and
KDP information in the NASA Space Flight Program and Project Management Handbook
provide specifics for addressing the six criteria required to demonstrate the program or
project has met expected maturity state.
Table 2-5 Expected Maturity State Through the Life Cycle of
Projects and Single-Project Programs
KDP
Review
Associated
Life-cycle
Review
LCR Objectives
Overall Expected
Maturity State at KDP
KDP A MCR
To evaluate the feasibility of the
proposed mission concept(s) and
its fulfillment of the program’s
needs and objectives. To determine
whether the maturity of the concept
and associated planning are
sufficient to begin Phase A.
Project addresses critical
NASA need. Proposed
mission concept(s) is
feasible. Associated
planning is sufficiently
mature to begin Phase A,
and the mission can likely
be achieved as conceived.
KDP B
SRR
To evaluate whether the functional
and performance requirements
defined for the system are
responsive to the program’s
requirements on the project and
represent achievable capabilities.
Proposed mission/system
architecture is credible and
responsive to program
requirements and
constraints, including
resources. The maturity of
the project’s mission/system
definition and associated
plans is sufficient to begin
Phase B, and the mission
can likely be achieved
within available resources
with acceptable risk.
MDR or
SDR
To evaluate the credibility and
responsiveness of the proposed
mission/system architecture to the
program requirements and
constraints, including available
resources. To determine whether
the maturity of the project’s
mission/system definition and
associated plans are sufficient to
begin Phase B.
To evaluate the
completeness/consistency of the
planning, technical, cost, and
schedule baselines developed
Project’s planning,
technical, cost, and schedule
baselines developed during
Formulation are complete
and consistent. The
preliminary design complies
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 32 of 147
NPR 7120.5F -- Chapter2 Page 32 of 147
KDP C PDR
during Formulation. To assess
compliance of the preliminary
design with applicable
requirements and to determine if
the project is sufficiently mature to
begin Phase C.
preliminary design complies
with its requirements. The
project is sufficiently
mature to begin Phase C,
and the cost and schedule
are adequate to enable
mission success with
acceptable risk.
KDP D
CDR
To evaluate the integrity of the
project design and its ability to
meet mission requirements with
appropriate margins and acceptable
risk within defined project
constraints, including available
resources. To determine if the
design is appropriately mature to
continue with the final design and
fabrication phase.
Project is still on plan. The
risk is commensurate with
the project’s payload
classification, and the
project is ready for AI&T
with acceptable risk within
its ABC.
PRR
To evaluate the readiness of system
developer(s) to produce the
required number of systems within
defined project constraints for
projects developing multiple
similar flight or ground support
systems. To evaluate the degree to
which the production plans meet
the system’s operational support
requirements.
SIR
To evaluate the readiness of the
project and associated supporting
infrastructure to begin system
AI&T, evaluate whether the
remaining project development can
be completed within available
resources, and determine if the
project is sufficiently mature to
begin Phase D.
KDP E
ORR
To evaluate the readiness of the
project to operate the flight system
and associated ground system(s) in
compliance with defined project
requirements and constraints
during the operations/sustainment
phase of the project life cycle.
Project and all supporting
systems are ready for safe,
successful launch and early
operations with acceptable
risk within ABC.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 33 of 147
NPR 7120.5F -- Chapter2 Page 33 of 147
MRR or
FRR
To evaluate the readiness of the
project and all project and
supporting systems for a safe and
successful launch and
flight/mission.
KDP En
(applies
only to
Single-
Project
Programs)
PIR
To evaluate the program’s
continuing relevance to the
Agency’s Strategic Plan, assess
performance with respect to
expectations, and determine the
program’s ability to execute the
implementation plan with
acceptable risk within cost and
schedule constraints.
Program still meets Agency
needs and is continuing to
meet Agency commitments,
as planned.
Non-KDP
Reviews
PLAR
To evaluate in-flight performance
of the flight system early in the
mission and determine whether the
project is sufficiently prepared to
begin Phase E.
PLAR Expected State:
Project is ready to conduct
mission operations with
acceptable risk within ABC.
CERR
To evaluate the readiness of the
project and the flight system for
execution of a critical event during
the flight operations phase of the
life cycle.
Mission CERR Expected
State: Project is ready to
conduct critical mission
activity with acceptable risk.
PFAR
To evaluate how well mission
objectives were met during a
human space flight mission and to
evaluate the status of the returned
vehicle.
PFAR Expected State: All
anomalies that occurred in
flight are identified. Actions
necessary to mitigate or
resolve these anomalies are
in place.
KDP F DR
To evaluate the readiness of the
project to conduct closeout
activities including final delivery of
all remaining project deliverables
and safe decommissioning of space
flight systems and other project
assets. To determine if the project
is appropriately prepared to begin
Phase F.
Project decommissioning is
consistent with program
objectives and project is
ready for safe
decommissioning of its
assets and closeout of
activities, including final
delivery of all remaining
project deliverables and
disposal of its assets.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 34 of 147
NPR 7120.5F -- Chapter2 Page 34 of 147
Non-KDP
Disposal
Readiness
Review
DRR
To evaluate the readiness of the
project and the flight system for
execution of the spacecraft disposal
event.
Mission DRR Expected
State: Project ready to
conduct disposal activity
with acceptable risk.
MCR Mission Concept Review
PRR Production Readiness Review
DRR Disposal Readiness Review
NOTE: LCR entrance and success criteria in NPR 7123.1 and the life-cycle phase and
KDP information in the NASA Space Flight Program and Project Management Handbook
provide specifics for addressing the six criteria required to demonstrate the program or
project has met expected maturity state.
Table 2-6 Objectives for Other Reviews
Review Name Review Objective
System Acceptance
Review (SAR)
To evaluate whether a specific end item is sufficiently mature to be
shipped from the supplier to its designated operational facility or
launch site.
Safety and Mission
Success Review
(SMSR)
To prepare Agency safety, engineering, and health and medical
management to participate in program final readiness reviews
preceding flights or launches, including experimental/test launch
vehicles or other reviews as determined by the Chief, Safety and
Mission Assurance. The SMSR provides the knowledge, visibility,
and understanding necessary for senior safety, engineering, and
health and medical management to either concur or nonconcur in
program decisions to proceed with a launch or significant flight
activity.
Launch Readiness
Review (LRR)
To evaluate a program/project and its ground, hardware, and
software systems for readiness for launch.
2.4 Approving and Maintaining Program and Project Plans,
Baselines, and Commitments
2.4.1 After reviewing the supporting material and completing discussions with concerned parties, the
Decision Authority determines whether and how the program or project proceeds into the next phase
and approves any additional actions. The decisions by the Decision Authority on whether and how
the program or project proceeds into the next phase shall be summarized and recorded in the
Decision Memorandum signed at the conclusion of the governing PMC by all parties with
supporting responsibilities, accepting their respective roles. Once signed, the Decision Memorandum
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 35 of 147
NPR 7120.5F -- Chapter2 Page 35 of 147
supporting responsibilities, accepting their respective roles. Once signed, the Decision Memorandum
is appended to the project Formulation Agreement, Program Plan, or Project Plan, as appropriate.
(Decision Memorandum templates may be found at
https://community.max.gov/pages/viewpage.action?pageId=1232962906. Additional information on
the Decision Memorandum is provided in the NASA Space Flight Program and Project Management
Handbook, Section 5.5.6.)
2.4.1.1 The Decision Memorandum shall describe the constraints and parameters within which the
Agency, the program manager, and the project manager will operate; the extent to which changes in
plans may be made without additional approval; any additional actions that came out of the KDP;
and the supporting data (e.g., the cost and schedule data sheet) that provide further details. The
NASA Space Flight Program and Project Management Handbook provides an example of the
Decision Memorandum to illustrate the level and types of information that are documented.
2.4.1.2 The Management Agreement contained within the Decision Memorandum defines the
parameters and authorities over which the program or project manager has management control. A
program or project manager has the authority to manage within the Management Agreement and is
accountable for compliance with the terms of the agreement. The Management Agreement, which is
documented at every KDP, may be changed between KDPs as the program or project matures and in
response to internal and external events. The Management Agreement should be viewed as a
contract between the Agency and the program or project manager. A divergence from the
Management Agreement that any signatory identifies as significant shall be accompanied by an
amendment to the Decision Memorandum.
2.4.1.3 During Formulation, the Decision Memorandum shall establish a target LCC or initial
capability cost range (and schedule range, if applicable) as well as the Management Agreement
addressing the schedule and resources required to complete Formulation.
a. For single-project programs and projects with a LCC or initial capability cost greater than or equal
to $1B, the Decision Memorandum shall establish a high and low value for cost and schedule with
the corresponding JCL value at KDP B. (See Section 2.4.3.1.) (This requirement does not apply to
two-step AO missions.)
b. Single-project programs and projects that plan continuing operations and production, including
integration of capability upgrades, with an unspecified Phase E end point, (e.g., SLS, EGS, Orion)
define the scope of an initial capability in the KDP B Decision Memorandum and establish an initial
capability cost.
2.4.1.4 The Decision Memorandum also documents any additional resources beyond those explicitly
estimated or requested by the program/project (e.g., additional schedule margin) when the Decision
Authority determines that this is appropriate. This includes Unallocated Future Expenses (UFE),
which are costs that are expected to be incurred but cannot yet be allocated to a specific WBS
sub-element of a program’s or project’s plan. Management control of some UFE may be retained
above the level of the project (i.e., Agency, Mission Directorate, or program). (See Figure 2-6,
Example of Agreements and Commitments in Terms of Cost for Projects.)
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 36 of 147
NPR 7120.5F -- Chapter2 Page 36 of 147
Figure 2 6 Example of Agreements and Commitments in Terms of Cost for Projects
2.4.1.5 All single-project program managers and project managers shall document the Agency’s
LCC estimate or initial capability cost estimate and other parameters in the Decision Memorandum
for Implementation (KDP C), and this becomes the ABC. The ABC is the baseline against which the
Agency’s performance is measured during the Implementation Phase. The ABC for programs and
projects with a LCC of $250M or more forms the basis for the Agency’s external commitment to
OMB and Congress.
a. For all single-project programs and projects with a definite Phase E end point, the Agency’s LCC
estimate and other parameters shall become the ABC.
b. For single-project programs and projects that plan continuing operations and production,
including integration of capability upgrades, with an unspecified Phase E end point, the initial
capability cost estimate and other parameters shall become the ABC.
2.4.1.6 For single-project programs and projects that plan continuing operations and production,
including integration of capability upgrades, with an unspecified Phase E end point, the Phase E cost
estimate for the continuing operations and production phase is established as part of the ORR and
KDP E for the five years after initial capability and subsequently updated and documented annually
for the next 5-year period. Upgrades during Phase E meeting the Agency criteria for a major project
for external reporting will be treated as projects for the purposes of their own ABC outside the Phase
E cost estimate. Other upgrades will be reflected in the Phase E cost estimate.
2.4.1.7 Tightly coupled programs shall document their LCC estimate in accordance with the
life-cycle scope defined in the FAD or PCA, and other parameters in their Decision Memorandum at
KDP I and update it at subsequent KDPs.
2.4.1.8 Programs or projects shall be rebaselined when: (1) the estimated development cost
7
exceeds
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 37 of 147
NPR 7120.5F -- Chapter2 Page 37 of 147
the ABC development cost by 30 percent or more (for projects over $250M, also that Congress has
reauthorized the project); (2) the NASA AA judges that events external to the Agency make a
rebaseline appropriate; or (3) the NASA AA judges that the program or project scope defined in the
ABC has been changed or the project has been interrupted. ABCs for projects are not rebaselined to
reflect cost or schedule growth that does not meet one or more of these criteria. When an ABC is
rebaselined, the Decision Authority directs that a review of the new baseline be conducted by the
SRB or as determined by the Decision Authority.
7
Development cost includes all project costs from authorization to proceed to Implementation (Phase C) through operational
readiness at the end of Phase D.
2.4.2 All programs and projects develop cost estimates and planned schedules for the work to be
performed in the current and following life-cycle phases (see Appendix I tables). The program or
project shall document the basis of estimate (BOE) for cost estimates and planned schedules in
retrievable program or project records.
2.4.3 Single-project programs (regardless of LCC or initial capability cost) and projects with an
estimated LCC or initial capability cost greater than $250M develop probabilistic analyses of cost
and schedule estimates to obtain a quantitative measure of the likelihood that the estimate will be
met in accordance with the following requirements. (In this section, for programs and projects that
plan continuing operations and production, including integration of capability upgrades, with an
unspecified Phase E end point, the initial capability cost is used instead of LCC.)
2.4.3.1 At KDP B:
a. Single-project programs with an estimated LCC under $1B and projects with an estimated LCC
greater than $250M and under $1B shall provide a range of cost and a range for schedule, each range
(with confidence levels identified for the low and high values of the range) established by a
probabilistic analysis and based on identified resources and associated uncertainties by fiscal year.
Separate analyses of cost and schedule, each with associated confidence levels, meet the
requirement. A joint cost and schedule confidence level (JCL) is not required but may be used.
b. Single-project programs and projects with an estimated LCC greater than or equal to $1B shall
develop a JCL and provide a high and low value for cost and schedule with the corresponding JCL
value (e.g., 50 percent, 70 percent).
8
The JCL is informed by a probabilistic analysis of development
cost and schedule duration.
9
The JCL measures the likelihood of completing all remaining work at
or below the budgeted levels and on or before the planned completion of Phase D.
8
This requirement is not applicable to two-step Announcement of Opportunity missions due to acquisition down-selection serving
as KDP B (Section 2.2.7.1).
9
The methodology for JCL analysis at KDP B is not limited to a probabilistic analysis of the coupled cost and schedule specified
for KDP C (see Section 2.4.3.2). Other parametric and bivariate methodologies may be applied.
2.4.3.2 At KDP C, single-project programs (regardless of LCC) and projects with an estimated LCC
greater than $250M shall develop a cost-loaded schedule and perform a risk-informed probabilistic
analysis that produces a JCL. The JCL at KDP C is the product of a probabilistic analysis of the
coupled cost and schedule.
2.4.3.3 At CDR, single-project programs and projects with an estimated LCC greater than or equal to
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 38 of 147
NPR 7120.5F -- Chapter2 Page 38 of 147
$1B shall update their KDP C JCL and communicate the updated JCL values for the ABC and
Management Agreement to the APMC for informational purposes.
2.4.3.4 At KDP D, single-project programs and projects with an estimated LCC greater than or equal
to $1B shall update their JCL if current reported development costs have exceeded the development
ABC cost by 5 percent or more and document the updated JCL values for the ABC and Management
Agreement in the KDP D Decision Memorandum.
2.4.3.5 When a single-project program (regardless of LCC) or project with an estimated LCC greater
than $250M is rebaselined, a JCL shall be calculated and evaluated as a part of the rebaselining
approval process.
2.4.4 Mission Directorates plan, budget, and ensure funding for single-project programs (regardless
of LCC or initial capability cost) and projects with an estimated LCC or initial capability cost
greater than $250M in accordance with the following requirements. (In this section, for programs
and projects that plan continuing operations and production, including integration of capability
upgrades, with an unspecified Phase E end point, the initial capability cost is used instead of LCC.)
2.4.4.1 At KDP B, Mission Directorates shall plan and budget single-project programs and projects
with an estimated LCC greater than or equal to $1B based on a 70 percent JCL or as approved by the
Decision Authority.
2.4.4.2 At KDP C, Mission Directorates shall plan and budget single-project programs (regardless of
LCC) and projects with an estimated LCC greater than
$250M based on a 70 percent JCL or as approved by the Decision Authority.
2.4.4.3 At KDP B and KDP C, any JCL approved by the Decision Authority at less than 70 percent
shall be justified and documented in a Decision Memorandum.
2.4.4.4 At KDP C, Mission Directorates shall ensure funding for single-project programs (regardless
of LCC) and projects with an estimated LCC greater than $250M is consistent with the Management
Agreement and in no case less than the equivalent of a 50 percent JCL or as approved by the
Decision Authority.
2.4.4.5 At KDP C, any funding approved by the Decision Authority that is inconsistent with the
Management Agreement or less than 50 percent JCL shall be justified and documented in a Decision
Memorandum.
2.4.5 Tightly coupled, loosely coupled, and uncoupled programs are not required to develop
program cost and schedule confidence levels. Tightly coupled, loosely coupled, and uncoupled
programs shall provide analysis of the program’s risk posture to the governing PMC as each new
project reaches KDP B and C or when a project’s ABC is rebaselined.
NPR 7120.5F -- Chapter2
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 39 of 147
NPR 7120.5F -- Chapter2 Page 39 of 147
Chapter 3. Program and Project Management
Roles and Responsibilities
3.1 Governance
3.1.1 The fundamental principles of NASA governance are defined in NPD 1000.0, NASA
Governance and Strategic Management Handbook. The governance model prescribes a management
structure that employs checks and balances among key organizations to ensure that decisions have
the benefit of different points of view and are not made in isolation. This structure is made up of two
authorities: Programmatic and Institutional. Programmatic Authority consists of the Mission
Directorates and their respective programs and projects. The Institutional Authority consists of those
organizations not in the Programmatic Authority. As part of Institutional Authority, NASA
established the Technical Authority (TA) process as a system of checks and balances to provide
independent oversight of programs and projects in support of safety and mission success through the
selection of specific individuals with delegated levels of authority. Individuals with these formal
delegations are Technical Authorities. The requirements related to TA are contained in Section 3.3.
3.2 Roles and Responsibilities
3.2.1 The roles and responsibilities of NASA management are defined in NPD 1000.0, NASA
Governance and Strategic Management Handbook and further outlined in NPD 1000.3, The NASA
Organization. The key roles and responsibilities specific to programs and projects can be
summarized as follows:
a. The Administrator leads the Agency and is accountable to the President for all aspects of the
Agency's mission, including establishing and articulating the Agency's vision and strategic priorities
and ensuring successful implementation of supporting policies, programs, and performance
assessments. The Administrator performs all necessary functions to govern NASA operations and
exercises the powers vested in NASA by law.
b. The NASA Associate Administrator is responsible for the technical and programmatic integration
of programs at the Agency level and serves as the Decision Authority for programs and Category 1
projects with the advice of the APMC. He or she monitors the status and performance of the
programs and projects via reports from the MDAA; Center Director; and through Agency-level
review, such as the APMC and the Baseline Performance Review (BPR) process. The NASA AA
may delegate Decision Authority to MDAAs. Within the Office of the NASA AA, the NASA
CPMO establishes policy, oversight, and assessment of the NASA program/project management
processes. In addition, the CPMO holds responsibility for Agency compliance with the PM
Improvement Accountability Act and is responsible for leading the Agency-level program/project
management integration function with support from OCE and OCFO and in partnership with the
Mission Directorates and Centers.
10
10
See the NASA Program Management Improvement and Accountability Act (PMIAA) Implementation Plan, which can be
found in NODIS on the OCE tab under the "Other NASA-Level Documents" menu.
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 40 of 147
NPR 7120.5F -- Chapter3 Page 40 of 147
c. MDAAs are responsible for Programmatic Authority in managing programs and projects within
their Mission Directorate. They establish directorate policies applicable to programs, projects, and
supporting elements; support the Agency's strategic acquisition process; initiate new programs and
projects; recommend assignment of programs and Category 1 projects to Centers; assign Category 2
and 3 projects to Centers; serve as the KDP Decision Authority for Category 2 and 3 projects; are
responsible for all program-level requirements; establish program and project budgets; approve
Formulation Agreements and Program and Project Plans; oversee program and project performance
via the DPMC; report on program and project progress including deviations in performance (e.g.,
cost, schedule, technical, and risk) that could impact Agency commitments and performance goals
with external organizations and stakeholders to Agency forums; and approve launch readiness. The
MDAAs may delegate some of their Programmatic Authority to deputy associate administrators,
division directors, or their equivalent, such as program directors, and Center Directors. The MDAAs
also plan and manage independent reviews with support from Centers for the Mission Directorate
program and project portfolio; organize and staff the independent review teams; ensure reviews are
conducted in accordance with documented review expectations (e.g., Terms of Reference (ToR));
monitor execution of the reviews; and capture lessons learned with support from Centers, the OCFO,
Office of the General Counsel (OGC), Office of Safety and Mission Assurance (OSMA), OCHMO,
and OCE. The MDAAs proactively work with Center Directors to develop constructive solutions for
the formulation and implementation of programs and projects conducted at their Centers and to
resolve issues as they arise.
d. Center Directors are responsible and accountable for all activities assigned to their Center. They
are responsible for the institutional activities and for ensuring the proper planning for and successful
execution of programs and projects assigned to the Center. This includes:
(1) Performing their delegated Technical Authority duties in accordance with Section 3.3;
(2) Ensuring the Center is capable of accomplishing the programs, projects, and other activities
assigned to it in accordance with Agency policy and the Center's best practices and institutional
policies by establishing, developing, and maintaining institutional capabilities (processes and
procedures, human capital--including trained/certified program/project personnel, facilities, and
infrastructure) required for the execution of programs and projects;
(3) Allocating resources to support program and project requirements and schedules, including
project management, engineering, and safety and mission assurance;
(4) Establishing and maintaining on-going processes and forums, including the CMC, to monitor the
status and progress of programs and projects at their Center;
(5) Performing periodic program and project reviews, as well as special reviews, to assess technical
and programmatic progress to ensure performance in accordance with their Center's and the
Agency's requirements, procedures, processes, etc.;
(6) Reporting the executability of all aspects of their programs and projects (programmatic,
technical, and all others) along with major risks, mitigation strategies, and significant concerns to the
Decision Authority and other appropriate forums, including Agency and Mission Directorate
Program Management Councils;
(7) Working with the Mission Directorate and the programs and project managers, once assigned, to
assemble the program/project team(s) and to provide needed Center resources;
(8) Providing support and guidance to programs and projects in resolving technical and
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 41 of 147
NPR 7120.5F -- Chapter3 Page 41 of 147
programmatic issues and risks;
(9) Concurring on the adequacy of cost/schedule estimates and the consistency of these estimates
with Agency requirements, workforce, and other resources stipulated in proposed Program and
Project Plans;
(10) Working proactively with the Mission Directorates, programs, projects, and other Institutional
Authorities to find constructive solutions to problems to benefit both the programs and projects and
the overall Agency long-term health;
(11) Certifying that programs and/or projects have been accomplished properly as part of the launch
approval process; and
(12) Supporting Mission Directorates to plan and manage independent reviews.
e. The program manager is responsible for the formulation and implementation of the program in
accordance with this document. This includes responsibility and accountability for the program
safety; technical integrity; technical, cost, and schedule performance; and mission success. (Refer to
the NASA Space Flight Program and Project Management Handbook and NASA/SP-2016-3424,
NASA Project Planning and Control Handbook for additional information.)
f. The project manager is responsible for the formulation and implementation of the project in
accordance with this document. This includes responsibility and accountability for the project safety;
technical integrity; technical, cost, and schedule performance; and mission success. (Refer to the
NASA Space Flight Program and Project Management Handbook and the NASA Project Planning
and Control Handbook for additional information.)
g. The Chief Financial Officer (CFO) oversees all financial management, budget, strategic planning,
and performance activities relating to the programs and operations of the Agency. The Office of the
Chief Financial Officer (OCFO) provides Agency programmatic (cost and schedule) analysis
capability leadership; establishes cost and schedule analyses policies, methods, and standards; and
assists in identification of personnel with analytical expertise to support in-line programmatic
activities of NASA programs and projects, as well as independent programmatic assessments (e.g.,
SRB).
h. The NASA Chief Engineer establishes policy, oversight, and assessment of the NASA
engineering processes; implements the Engineering Technical Authority process; and serves as
principal advisor to the Administrator and other senior officials on matters pertaining to the technical
capability and readiness of NASA programs and projects to execute according to plans. The Chief
Engineer directs the NASA Engineering and Safety Center (NESC) and ensures that
programs/projects respond to requests from the NESC for data and information needed to make
independent technical assessments and then respond to NESC assessments. The Chief Engineer leads
the mission and program/project performance assessment for the BPR; ensures that mission
resiliency and protection functional support is provided to NASA missions and management,
including development and review of project protection plans; and co-chairs the Safety and Mission
Success Review (SMSR) with the Office of Safety and Mission Assurance (OSMA) and the Office
of the Chief Health and Medical Officer (OCHMO).
i. The Chief, Safety and Mission Assurance (SMA) ensures the existence of robust safety and
mission assurance processes and activities through the development, implementation, assessment,
and functional oversight of Agency-wide safety, reliability, maintainability, quality, and risk
management policies and procedures. The Chief, SMA serves as principal advisor to the
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 42 of 147
NPR 7120.5F -- Chapter3 Page 42 of 147
Administrator and other senior officials on Agency-wide safety, reliability, maintainability, and
quality; performs independent program and project compliance verification audits and assessments
of safety and mission success practice; implements the SMA Technical Authority process; monitors,
collects, and assesses Agency-wide safety and mission assurance financial and performance results;
oversees the prompt investigation of NASA mishaps and ensures the appropriate closure; and
co-chairs the SMSR with the OCE and OCHMO.
j. The NASA Chief Health and Medical Officer (CHMO) is the focal point for policy formulation,
oversight, coordination, and management of all NASA health and medical matters in all
environments, and medical emergency preparedness, contingency operations, and response; The
CHMO implements the Health and Medical Technical Authority (HMTA) process for all health and
medical requirements and matters and is the principal advisor to the Administrator and other senior
officials on matters pertaining to human health in all Agency programs and projects. The CHMO is
responsible for Agency-level health and medical standards and policies; independently reviews all
programs and projects to ensure compliance with all health, medical, and human performance policy,
requirements, and standards; and co-chairs the SMSR with the OCE and OSMA.
k. The Chief Information Officer (CIO) is the principal Agency advisor to the Administrator and
other senior officials on matters pertaining to IT, the NASA Enterprise Architecture (EA),
cybersecurity, records management, and privacy. The CIO develops, maintains, and facilitates
implementation of the NASA EA, which is the framework for ensuring that IT investments and
plans enable the mission and are integrated, efficient, and secure. The CIO also leads and
implements NASA's Cybersecurity Program, ensuring appropriate confidentiality, integrity, and
availability of all NASA's information assets throughout the system life cycle. The CIO exercises
Mission Support Authority for IT and signs the Authority to Operate IT systems (e.g., corporate,
mission, ground, air, and space). This authorization is the official management decision given by a
senior organizational official to authorize operation of an information system and to explicitly accept
the risk to organizational operations (including mission, functions, image, or reputation),
organizational assets, individuals, other organizations, and the Nation based on implementing an
agreed-upon set of security controls.
l. The Mission Support Directorate (MSD) Associate Administrator establishes policy and
procedures for institutional oversight for mission support functional areas (e.g., procurement).
m. Roles and responsibilities for other NASA organizations can be found in NPD 1000.3.
3.3 Technical Authority
3.3.1 Programs and projects shall follow the Technical Authority (TA) process established in this
Section 3.3. NASA established this process as part of its system of checks and balances to provide
independent oversight of programs and projects in support of safety and mission success through the
selection of specific individuals with delegated levels of authority. These individuals are the
Technical Authorities (TAs). In this document, the term TA is used to refer to such an individual but
is also used to refer to elements of the TA process. The responsibilities of a program or project
manager are not diminished by the implementation of TA. The program or project manager is
ultimately responsible for the safe conduct and successful outcome of the program or project in
conformance with governing requirements. This includes meeting programmatic, institutional,
technical, safety, cost, and schedule commitments. Further detail on TA is provided in
NASA/SP-20220009501, NASA Space Flight Program and Project Management Handbook.
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 43 of 147
NPR 7120.5F -- Chapter3 Page 43 of 147
3.3.2 TA originates with the Administrator and is formally delegated to the NASA AA and then to
the NASA Chief Engineer for Engineering TA; the Chief, Safety and Mission Assurance for SMA
TA; and then to the Center Directors. The Administrator delegates Health and Medical Technical
Authority (HMTA) to the NASA CHMO. Subsequent TA delegations are made to selected
individuals who are funded independent of the Programmatic Authority. Such delegations are formal
and traceable to the Administrator. TAs located at Centers remain part of their Center organization,
and their personnel performance appraisal is signed by the management of that Center organization.
The Center Director (or designee) is responsible for establishing and maintaining Center TA policies
and practices, consistent with Agency policies and standards.
3.3.3 Other Technical Authority Roles
3.3.3.1 Top-level documents developed by a program detailing Agency-level requirements for
human-rated systems are signed by the Administrator or his/her formally delegated designee.
3.3.3.2 On decisions related to technical and operational matters involving safety and mission
success residual risk, formal concurrence by the responsible TAs (Engineering, Safety and Mission
Assurance, and/or Health and Medical) is required. This concurrence is to be based on the technical
merits of the case. For residual risks to personnel or high-value hardware, the cognizant safety
organization needs to agree that the risk is acceptable. For matters involving human safety risk, the
actual risk taker(s) (or official spokesperson(s) and their supervisory chain) need to formally consent
to taking the risk and the responsible program, project, or operations manager needs to formally
accept the risk.
3.3.4 At the program or project level, the responsibilities common to each of the individuals with
delegated TA (ETA, SMA TA, and HMTA) are delineated below. (See Sections 3.3.7 to 3.3.10 for
unique aspects of each of the TAs.) These individuals:
a. Serve as members of program or project control boards, change boards, and internal review
boards.
b. Work with the Center management and other TA personnel, as necessary, to ensure that the
quality and integrity of program or project processes, products, and standards of performance related
to engineering, SMA, and health and medical reflect the level of excellence expected by the Center
or, where appropriate, by the NASA TA community.
c. Ensure that requests for waivers or deviations from TA requirements are submitted to and acted
on by the appropriate level of TA. ("Technical Authority requirements" is defined in Appendix A.)
d. Assist the program or project in making risk-informed decisions that properly balance technical
merit, cost, schedule, and safety across the system.
e. Provide the program or project with the TA view of matters based on their knowledge and
experience and raise a Formal Dissent (see Section 3.4) on a decision or action, when appropriate.
f. Serve as an effective part of NASA's overall system of checks and balances.
3.3.5 The day-to-day involvement of the TAs in program or project activities ensures that significant
views from the TAs will be available to the program or project in a timely manner and should be
handled during the normal program/project processes. TAs are expected to keep their discipline
chain of authority informed of issues as they arise, including direct communication between the
Center's engineering director, SMA director (or equivalent), and lead HMTA Integration Centers
with their counterparts at NASA HQ.
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 44 of 147
NPR 7120.5F -- Chapter3 Page 44 of 147
with their counterparts at NASA HQ.
3.3.6 Infrequent circumstances may arise when a TA and the program or project manager disagree
on a proposed programmatic or technical action and judge that the issue rises to a level of
significance that should be brought to the attention of the next higher level of management (i.e., a
Formal Dissent exists). In such circumstances:
a. Resolution occurs prior to Implementation whenever possible. However, if considered to be in the
best interest of the program/project, the program/project manager has the authority to proceed at risk
in parallel with the pursuit of a resolution. In such circumstances, the next higher level of
Programmatic and TA is informed of the decision to proceed at risk.
b. Resolution is jointly attempted at successively higher levels of Programmatic Authority and TA
until resolved. Final appeals are made to the NASA Administrator.
3.3.7 The Engineering Technical Authority (ETA) establishes and is responsible for the
engineering design processes, specifications, rules, best practices, etc., necessary to fulfill
programmatic mission performance requirements.
3.3.7.1 The NASA Chief Engineer provides overall leadership for the ETA process for programs and
projects, including Agency engineering policy direction, requirements, and standards. The NASA
Chief Engineer approves the appointment of the Center engineering directors (or equivalent) and of
ETAs on programs and Category 1 projects and is notified of the appointment of other Engineering
TAs. The NASA Chief Engineer hears appeals of engineering decisions when they cannot be
resolved at lower levels.
3.3.7.2 The Center Director (or designee) develops the Center's ETA policies and practices,
consistent with Agency policies and standards. The following individuals are responsible for
implementing ETA at the Center:
a. Center Director--The Center Director (or the Center Engineering Director or designee) is the
Center ETA responsible for Center engineering design processes, specifications, rules, best
practices, etc., necessary to fulfill mission performance requirements for programs, projects, and/or
major systems implemented by the Center. The Center Director delegates Center ETA
implementation responsibility to an individual in the Center's engineering leadership. The Center
ETA supports the TAs in processing changes to, and waivers or deviations from, requirements that
are the responsibility of the ETA. This includes all applicable Agency and Center engineering
directives, requirements, procedures, and standards. The Center Director appoints, with the approval
of the NASA Chief Engineer, individuals for the position of Center engineering director (or
equivalent) and for the ETA positions down to and including program chief engineers and Category
1 project chief engineers (or equivalents).
11
The Center Director or designee appoints Category 2
and 3 project chief engineers and lead discipline engineers.
11
Centers may use an equivalent term for these positions, such as program/project systems engineer.
b. Program/Project Chief Engineer (PCE)--The PCE is the position to which the
program/project-level ETA has been delegated. Different Centers use different titles for this
position.
c. Lead Discipline Engineer (LDE)--The LDE is a senior technical engineer in a specific discipline
at the Center. Different Centers use different titles for this position. The LDE assists the
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 45 of 147
NPR 7120.5F -- Chapter3 Page 45 of 147
program/project through direct involvement with working-level engineers to identify engineering
requirements in accordance with NPR 7120.10, Technical Standards for NASA Programs and
Projects and other documents and to develop solutions that comply with the requirements. The LDE
works through and with the PCE to ensure the proper application and management of
discipline-specific engineering requirements and Agency standards.
3.3.7.3 The ETA for the program or project leads and manages the engineering activities, including
systems engineering, design, development, sustaining engineering, and operations. A Center may
have more than one engineering organization and delegates ETA to different areas as needed. To
support the program/project and maintain ETA independence and an effective check and balance
system:
a. The program/project manager concurs in the appointment of the program/project-level ETAs.
b. The ETA cannot approve a request for relief from a non-technical derived requirement established
by a Programmatic Authority.
c. An ETA may approve a request for relief from a technical derived requirement if he/she ensures
that the appropriate independent Institutional Authority subject matter expert who is the steward for
the involved technology has concurred in the decision to approve the requirement relief.
3.3.8 Although a limited number of individuals make up the ETAs, their work is enabled by the
contributions of the program's or project's working-level engineers and other supporting personnel
(e.g., contracting officers). The working-level engineers do not have formally delegated TA and
consequently may not serve in an ETA capacity. These engineers perform the detailed engineering
and analysis for the program/project with guidance from their Center management and/or LDEs and
support from the Center engineering infrastructure. They deliver the program/project products (e.g.,
hardware, software, designs, analysis, and technical alternatives) that conform to applicable
programmatic, Agency, and Center requirements. They are responsible for raising issues to the
program/project manager, Center engineering management, and/or the PCE, as appropriate, and are
a key resource for resolving these issues.
3.3.9 The Safety and Mission Assurance (SMA) TA establishes and is responsible for the SMA
processes, specifications, rules, best practices, etc., necessary to fulfill safety and programmatic
mission performance requirements. (Refer to NPR 8715.3, NASA General Safety Program
Requirements.) The following individuals are responsible for implementing SMA TA at the Center:
3.3.9.1 The Chief, SMA--The Chief, SMA hears appeals of SMA decisions when issues cannot be
resolved below the Agency level.
3.3.9.2 Center Director--The Center Director (or the Center safety and mission assurance director or
designee) is the Center SMA TA responsible for Center safety and mission assurance processes,
specifications, rules, best practices, etc., necessary to fulfill mission performance requirements for
programs, projects, and/or major systems implemented by the Center. The Center Director (or
designee) also monitors, collects, and assesses institutional, program, and project SMA financial
metrics and performance results. The Center Director delegates Center SMA TA implementation
responsibility to an individual in the Center's safety and mission assurance leadership. The Center
SMA TA supports the lower level SMA TAs in processing changes to and waivers or deviations
from requirements that are the responsibility of the SMA TA. This includes all applicable Agency
and Center SMA directives, requirements, procedures, and standards. The Center Director appoints,
with the approval of the NASA Chief, SMA, individuals for the position of Center SMA director (or
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 46 of 147
NPR 7120.5F -- Chapter3 Page 46 of 147
equivalent). The Center SMA director, in consultation with the NASA Chief, SMA, appoints
program- and project-level chief safety and mission assurance officers to exercise the TA role within
programs and projects.
3.3.10 The Health and Medical Technical Authority (HMTA) establishes and is responsible for
the health and medical Agency-level policy, requirements, and standards necessary to fulfill
programmatic mission performance requirements. (Refer to NPR 7120.11, NASA Health and
Medical Technical Authority (HMTA) Implementation).
3.4 Process for Handling Formal Dissent
3.4.1 Programs and projects shall follow the Formal Dissent process in this Section 3.4. NASA
teams have full and open discussions with all facts made available to understand and assess issues.
Diverse views are to be fostered and respected in an environment of integrity and trust with no
suppression or retribution. In the team environment in which NASA operates, team members often
have to determine where they stand on a decision. In assessing a decision or action, a member has
three choices: agree, disagree but be willing to fully support the decision, or disagree and raise a
Formal Dissent. Unresolved issues of any nature (e.g., programmatic, safety, engineering, health and
medical, acquisition, accounting) within a team should be quickly elevated to achieve resolution at
the appropriate level.
3.4.2 Whenever a Formal Dissent is raised, it is documented and communicated by the dissenter in
coordination with the disagreeing party at a minimum of two levels of management above the
original program or project decision.
3.4.3 When time permits, the disagreeing parties jointly document the issue, including agreed-to
facts, discussion of the differing positions with rationale and impacts, and the parties,
recommendations. The joint documentation needs to be approved by the representative of each view,
concurred with by affected parties, and provided to the next higher level of the involved authorities
with notification to the second higher level of management. This may involve a single authority
(e.g., the Programmatic Authority) or multiple authorities (e.g., Programmatic and TAs). In cases of
urgency, the disagreeing parties may jointly present the information stated above orally with all
affected organizations represented, advance notification to the second-higher level of management,
and documentation followup.
3.4.4 A Center Director may request an expedited escalation of a Formal Dissent at the Agency
level up to and including the NASA Administrator based on his or her judgment that a rapid
resolution of the Formal Dissent is in the best interests of the Agency and the dissenting individual
or organization.
3.4.5 Management's decision on the dissent memorandum (or oral presentation) is documented and
provided to the dissenter and to the notified managers and becomes part of the program or project
record. If the dissenter is not satisfied with the process or outcome, the dissenter may appeal to the
next higher level of management. The dissenter has the right to take the issue upward in the
organization, even to the NASA Administrator, if necessary.
3.5 Principles Related to Tailoring Requirements
3.5.1 Programs and projects shall follow the tailoring process in this Section 3.5. NASA policy is
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 47 of 147
NPR 7120.5F -- Chapter3 Page 47 of 147
that all prescribed requirements (requirements levied on a lower organizational level by a higher
organizational level) are complied with unless relief is formally granted. Relief from a requirement
may be granted in the form of a ruling that a requirement is non-applicable or in the form of a
waiver or a deviation. Policy also recognizes that each program or project has unique aspects that
must be accommodated to achieve mission success in an efficient and economical manner. Tailoring
is the process used to adjust or seek relief from a prescribed requirement to meet the needs of a
specific program or project. Tailoring is both an expected and accepted part of establishing proper
requirements.
a. Programs, Category 1 projects, and projects that are of high importance or visibility to NASA will
coordinate with the CPMO to determine their tailoring approach. The CPMO-coordinated tailoring
approach may need to be presented by the program or project to the NASA Program and Project
Management Board (PPMB), as determined by the CPMO. The CPMO point(s)-of-contact for
coordination of the program and project tailoring approach and PPMB coordination are provided on
the Agency Tailoring Web site available at https://appel.nasa.gov/npr-7120-5-tailoring-resources.
b. For requests for relief from requirements that are the responsibility of the Chief, SMA, NPR
8715.3, NASA General Safety Program Requirements contains the SMA-specific process. For
requests for relief from requirements that are the responsibility of the CHMO, NPR 7120.11
contains the HMTA specific process.
c. Refer to the NASA Space Flight Program and Project Management Handbook for additional
explanation and guidance related to the tailoring process. The handbook can be found in NODIS on
the OCE tab under the "Other NASA-Level Documents" menu.
3.5.2 The evaluation and disposition of requests for tailoring (including Agency-level requirements
and standards) comply with the following:
a. The request for relief from a requirement includes the rationale, a risk evaluation, and reference to
all material that provides the justification supporting acceptance. The request for requirement relief
is referred to as a "deviation" or "waiver" depending on the timing of the request. Deviations apply
before a requirement is put under configuration control at the level the requirement will be
implemented, and waivers apply after.
b. The organization submitting the tailoring request informs the next higher level of involved
management in a timely manner of the tailoring request.
c. The organization at the level that established the requirement dispositions the request for tailoring
of that requirement unless this authority has been formally delegated elsewhere. Such delegations
will maintain the separation of Programmatic and Institutional Authorities required by governance.
d. The dispositioning organization consults with the other organizations that were involved in the
establishment of the specific requirement and obtains the concurrence of those organizations having
a substantive interest.
e. Approved tailoring requests become part of the retrievable program or project records.
3.5.3 A prescribed requirement that is not relevant and/or not capable of being applied to a specific
program, project, system, or component can be approved as Non-Applicable (NA) by the individual
who has been delegated oversight authority by the organization that established the requirement.
This approval can be granted at the level where the requirement was specified for implementation
(e.g., the project-level ETA could approve an NA designation for an engineering requirement). The
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 48 of 147
NPR 7120.5F -- Chapter3 Page 48 of 147
request and approval documentation become part of the retrievable program or project records. No
other formal deviation or waiver process is required.
3.5.4 A request for a permanent change to a prescribed requirement in an Agency or Center
document that is applicable to all programs and projects shall be submitted as a "change request" to
the office responsible for the requirement policy document unless formally delegated elsewhere.
3.5.5 Tailoring NPR 7120.5
3.5.5.1 Requests for tailoring of NPR 7120.5 requirements may be submitted in the form of the
Compliance Matrix (Appendix C) and/or by using a documented waiver request individually or in
groups. (See the NASA Space Flight Program and Project Management Handbook for additional
information on this request.) If requested separately from the Compliance Matrix, a waiver still
needs to be recommended by the MDAA, concurred with by the Center Director, and approved by
the requirement owner or as delegated.
3.5.5.2 Guidance and resources to assist programs and projects in tailoring NPR 7120.5 requirements
have been established and/or developed by the Agency, Mission Directorates, and Centers.
Appendix C provides:
a. The Compliance Matrix, which includes the NPR requirements, the organization or individual
responsible for each requirement with authority for approving tailoring, and whether tailoring
authority for the requirement is delegated or held at HQ. (See Table C-1.)
b. The process for documenting and obtaining approval for tailoring.
c. Information on different options related to the Compliance Matrix. (See Section C.1.)
d. Consultation and assistance for tailoring. (See Section C.2.)
e. Resources for developing the tailoring approach. (See Section C.3.)
An Agency Tailoring Web site, which includes many of these resources, is available at
https://appel.nasa.gov/npr-7120-5-tailoring-resources.
3.6 Reimbursable Space Flight Work
Center Directors negotiating reimbursable space flight work with another agency shall propose NPR
7120.5 as the basis by which it will perform the space flight work. If the sponsoring agency does not
want NPR 7120.5 requirements (or a subset of those requirements) to be followed, then the
interagency Memorandum of Understanding/Memorandum of Agreement or the contract needs to
explicitly identify those requirements that will not be followed, along with the substitute
requirements for equivalent processes and any additional program/project management requirements
the sponsoring agency wants. The Center obtains a formal waiver by the CPMO for the NASA AA
for those NPR 7120.5 requirements that are not to be followed or the Center cannot accept the work.
3.7 Use of the Metric System
The International System of Units (commonly known as the Systeme Internationale (SI) or metric
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 49 of 147
NPR 7120.5F -- Chapter3 Page 49 of 147
system of measurement) is to be used for all new space flight projects and programs, especially in
cooperative efforts with International Partners. 15 U.S.C. §205b and Executive Order 12770 provide
relief from this preferential use of SI if it is found that obtaining components in SI units would result
in a substantial increase in cost or unacceptable delays in schedule. Each program and project shall
perform and document an assessment to determine an approach that maximizes the use of SI. This
assessment will document an integration strategy if both SI and U.S. customary units are used in a
project or program. The assessment is to be completed and documented in the Program Plan or
Project Plan no later than the SDR.
NPR 7120.5F -- Chapter3
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 50 of 147
NPR 7120.5F -- Chapter3 Page 50 of 147
Appendix A. Definitions
Acquisition. Obtaining, or advancing the development of, the systems, research, services,
construction, and supplies to fulfill the Agency's mission and other activities which advance the
Agency's statutory objectives. (The definition of acquisition in this document is used in a broader
context than the FAR definition to encompass the spectrum of various NASA acquisition authorities
and approaches to achieve the Agency's mission and activities).
Acquisition Strategy. The integrated strategy that enables a program or project to meet its mission
objectives and provides the best value to NASA. (See a description in Section 3.4 of the Program
Plan and Project Plan templates, appendices G and H.)
Acquisition Strategy Council. The ASC serves as the Agency's senior decision-making body for
matters of long-term, annual, and tactical acquisition strategy planning and for matters of policy and
performance assessment pertaining to the Agency's acquisition approaches. The scope and authority
of the ASC includes the strategic acquisition process as defined in NPD 1000.5, Policy for NASA
Acquisition. The ASC conducts Decision Framing Meetings or Pre-ASMs, and ASMs for large,
high-profile programs and projects following thresholds and requirements specified in NPD 1000.5.
Acquisition Strategy Meeting. A decision-making forum where senior Agency management
reviews and approves program and project acquisition strategies. The ASM focuses on
considerations such as impacting the Agency workforce, maintaining core capabilities, make-or- buy
decisions, supporting Center assignments, potential partnerships, and risk. (See NPD 1000.5 Policy
for NASA Acquisition, and NASA Advisory Implementing Instruction (NAII) 1000.2 Acquisition
Strategy Meeting (ASM) Guide for more information on ASMs.
Agency Baseline Commitment. Establishes and documents an integrated set of project
requirements, cost, schedule, technical content, and an agreed-to JCL that forms the basis for
NASA’s commitment to the external entities of OMB and Congress. Only one official baseline
exists for a NASA program or project, and it is the Agency Baseline Commitment.
Agency Program Management Council. The senior management group, chaired by the NASA
Associate Administrator or designee that is responsible for reviewing Formulation performance,
recommending approval, and overseeing implementation of programs and Category 1 projects
according to Agency commitments, priorities, and policies.
Agreement. The statement (oral or written) of an exchange of promises. Parties to a binding
agreement can be held accountable for its proper execution and a change to the agreement requires a
mutual modification or amendment to the agreement or a new agreement.
Analysis of Alternatives. A formal analysis method that compares alternative approaches by
estimating their ability to satisfy mission requirements through an effectiveness analysis and by
estimating their life-cycle costs through cost analysis. The results of these two analyses are used
together to produce a cost-effectiveness comparison that allows decision makers to assess the
relative value or potential programmatic returns of the alternatives. An analysis of alternatives
broadly examines multiple elements of program/project alternatives (including technical
performance, risk, LCC or initial capability cost, and programmatic aspects).
Announcement of Opportunity. An AO is one form of a NASA Broad Agency Announcement,
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 51 of 147
NPR 7120.5F -- AppendixA Page 51 of 147
Announcement of Opportunity. An AO is one form of a NASA Broad Agency Announcement,
which is a form of public/private competition. NASA solicits, accepts, and evaluates proposals
submitted by all categories of proposers in response to an AO, including academia, industry,
not-for-profits, Government laboratories, Federally Funded Research and Development Centers
(FFRDC), NASA Centers, and the Jet Propulsion Laboratory. Regulatory coverage of AOs appears
in NASA Federal Acquisition Regulation (FAR) Supplement (NFS) Part 1872. NASA typically uses
a one-step or a two-step AO process. In a one-step AO process, proposals for new projects are
evaluated competitively and selected for Formulation in a single step. In two-step competitions,
several proposals for new projects may be selected in Step 1 and given time to mature their concepts
in a funded concept study before the Step 2 down-selection.
Approval. Authorization by a required management official to proceed with a proposed course of
action. Approvals are documented.
Approval (for Implementation). Acknowledgment by the Decision Authority that the program
/project has met stakeholder expectations and Formulation requirements and is ready to proceed to
Implementation. By approving a program/project, the Decision Authority commits the budget
resources necessary to continue into Implementation. Approval (for Implementation) is documented.
Baseline (document context). Implies the expectation of a finished product, though updates may be
needed as circumstances warrant. All approvals required by Center policies and procedures have
been obtained.
Baseline (general context). An agreed-to set of requirements, cost, schedule, designs, documents,
etc., that will have changes controlled through a formal approval and monitoring process.
Baseline Performance Review. A monthly Agency-level independent assessment to inform senior
leadership of performance and progress toward the Agency’s mission and program/project
performance. The monthly meeting encompasses a review of crosscutting mission support issues and
all NASA mission areas.
Baseline Science Requirements. The mission performance requirements necessary to achieve the
full science objectives of the mission. (Also see Threshold Science Requirements.)
Basis of Estimate. The documentation of the ground rules, assumptions, and drivers used in
developing the cost and schedule estimates, including applicable model inputs, rationale or
justification for analogies, and details supporting cost and schedule estimates. The basis of estimate
is contained in material available to the SRB and management as part of the LCR and KDP process.
Budget. A financial plan that provides a formal estimate of future revenues and obligations for a
definite period of time for approved programs, projects, and activities. (See NPR 9420.1, Budget
Formulation and NPR 9470.1, Budget Execution for other related financial management terms and
definitions.)
Business Case (Infrastructure). An analysis of options for construction of new facilities or
infrastructure or significant modification of existing infrastructure. (See NPR 8800.15, Real Estate
Management Program and the NASA Business Case Guide for Real Property and Facilities Project
Investments.)
Capability Component. An individual capability within a capability portfolio or the larger
capability domain. It is a system comprising workforce (i.e., FTE/WYE), equipment, facilities,
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 52 of 147
NPR 7120.5F -- AppendixA Page 52 of 147
processes, resources, competencies, and technologies that delivers products and services; for
example, a wind tunnel and the workforce that manages, operates, and maintains it; or a complex
dedicated to an end-to-end process.
Capability Portfolio. A specific collection of functionally similar site-specific capability
components and enabling infrastructure strategically and centrally managed together to meet
NASA’s strategic goals and objectives. For example, the Space Environments Testing Management
Office (SETMO) capability portfolio includes testing in high enthalpy arc jets, flight simulators,
thermal vacuum chambers, and radiation laboratories. The program or project manager coordinates
with capability portfolio managers on any planned investments, divestments, acquisition strategies,
procurements, agreements, and changes to capability portfolio capability components in accordance
with requirements and strategic guidance included in NPR 8600.1, NASA Capability Portfolio
Management Requirements. NPR 8600.1 provides a link to the list of Capability Portfolios.
Center Management Council. The council at a Center that performs oversight of programs and
projects by evaluating all program and project work executed at that Center.
Change Request. A change to a prescribed requirement set forth in an Agency or Center document
intended for all programs and projects for all time.
Compliance Matrix. The Compliance Matrix (Appendix C) documents whether and how the
program or project complies with the requirements of NPR 7120.5. It provides rationale and
approvals for tailoring (waivers and deviations) requirements and is part of retrievable program and
project records.
Component Facilities. Complexes that are geographically separated from the NASA Center or
institution to which they are assigned but are still part of the Agency.
Concept Documentation. Documentation that captures and communicates a feasible concept that
meets the goals and objectives of the mission, including results of analyses of alternative concepts,
the concept of operations, preliminary risks, and potential descopes. It may include images, tabular
data, graphs, and other descriptive material.
Concurrence. A documented agreement by a management official that a proposed course of action
is acceptable.
Confidence Level. A probabilistic assessment of the level of confidence of achieving a specific
goal.
Configuration Management. A technical and management process applying appropriate processes,
resources, and controls to establish and maintain consistency between product configuration
information and the product throughout the product life cycle.
Conflict of Interest. A conflict of interest involves the abuse—actual, apparent, or potential—of the
trust that NASA has in its personnel. A conflict of interest is a situation in which financial or other
personal considerations have the potential to compromise or bias professional judgment and
objectivity. An apparent conflict of interest is one in which a reasonable person would think that the
individual’s judgment is likely to be compromised. A potential conflict of interest involves a
situation that may develop into an actual conflict of interest. A conflict of interest exists whether or
not decisions are affected by a personal interest; a conflict of interest implies only the potential for
bias, not likelihood.
Considerations for a PIR. See the NASA Space Flight Program and Project Management
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 53 of 147
NPR 7120.5F -- AppendixA Page 53 of 147
Considerations for a PIR. See the NASA Space Flight Program and Project Management
Handbook, Section 5.11.13.
Continuous Risk Management. A systematic and iterative process that efficiently identifies,
analyzes, plans, tracks, controls, communicates, and documents risks associated with
implementation of designs, plans, and processes.
Contract. A mutually binding legal relationship obligating the seller to furnish the supplies or
services (including construction) and the buyer to pay for them. It includes all types of commitments
that obligate the Government to an expenditure of appropriated funds and that, except as otherwise
authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited
to) awards and notices of awards; job orders or task letters issued under basic ordering agreements;
letter contracts; orders, such as purchase orders, under which the contract becomes effective by
written acceptance or performance; and bilateral contract modifications. Contracts do not include
grants and cooperative agreements.
Convening Authority. The management official(s) responsible for convening a program/project
review; establishing the Terms of Reference, including review objectives and success criteria;
appointing the SRB chair; and concurring in SRB membership. These officials receive the
documented results of the review.
Cost Analysis Data Requirement. A three-part document required for tightly coupled programs,
loosely coupled programs, single-project programs, and projects (regardless of Category or Class)
that provides critical data to assist NASA in developing high fidelity cost and schedule estimates for
new NASA projects. CADRe consists of Part A “Narrative” and Part B “Technical Data” in tabular
form, provided by the program or project using existing program or project material. The program or
project team produces the project life-cycle cost estimate, schedule, and risk identification which is
appended as Part C. For single-project programs and projects that plan continuing operations and
production, including integration of capability upgrades, with an unspecified Phase E end point, the
initial capability cost plus the current Phase E cost estimate is used instead of the life-cycle cost.
Cost-Loaded Schedule. In the context of the JCL requirement, a schedule that has costs and/or
resources assigned to its individual activities or summary tasks.
Decision Authority (program and project context). The individual authorized by the Agency to
make important decisions on programs and projects under their authority.
Decision Framing Meeting. A precursor meeting used in NASA Governance Councils, including as
a precursor to some ASMs, which aligns leadership and Chair expectations on how, when and under
what decision criteria future decisions will be made. Decision Framing Meetings may be used by
any ASM Convening Authority and are held at the discretion of the Convening Authority. (See NAII
1000.1 under NPD 1000.5 for additional details.)
Decision Memorandum. The document that summarizes the decisions made at KDPs or as
necessary in between KDPs. The decision memorandum includes the Agency Baseline Commitment
(if applicable), Management Agreement cost and schedule, UFE, and schedule margin managed
above the project, as well as life-cycle cost and schedule estimates, as required. For single-project
programs and projects that plan continuing operations and production, including integration of
capability upgrades, with an unspecified Phase E end point, the initial capability cost and the current
Phase E cost estimate are documented in the Decision Memorandum.
Decommissioning. The process of ending an operating mission and the attendant project as a result
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 54 of 147
NPR 7120.5F -- AppendixA Page 54 of 147
of a planned end of the mission or project termination. Decommissioning includes final delivery of
any remaining project deliverables, disposal of the spacecraft and all its various supporting systems,
closeout of contracts and financial obligations, and archiving of project/mission operational and
scientific data and artifacts. Decommissioning does not mean that scientific data analysis ceases,
only that the project will no longer provide the resources for continued research and analysis.
Derived Requirements. Requirements arising from constraints, consideration of issues implied but
not explicitly stated in the high-level direction provided by NASA HQ and Center institutional
requirements, factors introduced by the selected architecture, and the design. These requirements are
finalized through requirements analysis as part of the overall systems engineering process and
become part of the program/project requirements baseline. Derived non-technical requirements are
established by, and are the responsibility of, the Programmatic Authority. Derived technical
requirements are the responsibility of the Institutional Authority.
Design Documentation. A document or series of documents that captures and communicates to
others the specific technical aspects of a design. It may include images, tabular data, graphs, and
other descriptive material. Design documentation is different from the CADRe, though parts of
design documentation may be repeated in the latter.
Development Costs. The total of all costs from the period beginning with the approval to proceed to
Implementation at the beginning of Phase C through operational readiness at the end of Phase D.
Deviation. A documented authorization releasing a program or project from meeting a requirement
before the requirement is put under configuration control at the level the requirement will be
implemented.
Directorate Program Management Council. The forum that evaluates all programs and projects
executed within that Mission Directorate and provides input to the Mission Directorate Associate
Administrator (MDAA). For programs and Category 1 projects, the MDAA carries forward the
DPMC findings and recommendations to the Agency Program Management Council (APMC).
Disposal. The process of eliminating a project’s assets, including the spacecraft and ground systems.
Disposal includes the reorbiting, deorbiting, and/or passivation (i.e., the process of removing stored
energy from a space structure at the end of mission that could result in an explosion or deflagration
of the space structure) of a spacecraft.
Earned Value Management. A project management approach for measuring and assessing project
performance through the integration of technical scope with schedule and cost objectives during the
execution of the project. EVM provides quantification of technical progress with objective
performance measurement techniques, enabling management to gain insight into project status and
project completion costs and schedules. Two essential characteristics of successful EVM are EVM
system data integrity and carefully targeted monthly EVM data analyses (e.g., identification of risky
WBS elements).
Earned Value Management System. The integrated set of policies, processes, systems, and
practices that meet an organization’s implementation of EIA-748. This integrated management
system and its related subsystems allow for planning all work scope to completion; assignment of
authority and responsibility at the work performance level; integration of the cost, schedule, and
technical aspects of the work into a detailed baseline plan; objective measurement of progress
(earned value) at the work performance level; accumulation and assignment of actual costs; analysis
of variances from plans; summarization and reporting of performance data to higher levels of
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 55 of 147
NPR 7120.5F -- AppendixA Page 55 of 147
management for action; forecast of achievement of milestones and completion of events; forecast of
final costs; and disciplined baseline maintenance and incorporation of baseline revisions in a timely
manner.
Engineering Requirements. Requirements defined to achieve programmatic requirements and
relating to the application of engineering principles, applied science, or industrial techniques.
Ensure. To do or have what is necessary for success. (An example is: Connectivity will be ensured
by testing that a signal to noise ratio of ten is maintained in environmental testing.)
Environmental Compliance. The activity of ensuring that program and project actions and
decisions that may potentially affect or damage the environment are assessed during the
Formulation Phase and reevaluated throughout Implementation. This activity is performed according
to all NASA policy and Federal, State, Tribal government, and local environmental laws and
regulations.
Environmental Impact. The direct, indirect, or cumulative beneficial or adverse effect of an action
on the environment.
Evaluation. The continual self- and independent assessment of the performance of a program or
project and incorporation of the evaluation findings to ensure adequacy of planning and execution
according to plans.
Final (document context). Implies the expectation of a finished product. All approvals required by
Center policies and procedures have been obtained.
Final Mission Report. The Final Mission Report is a summary of what the mission accomplished
and is prepared at the end of a mission. It has also been called an End of Mission report, but this is
not to be confused with the End of Mission Plan (EOMP) required by NPR 8715.6, NASA
Procedural Requirements for Limiting Orbital Debris and Evaluating the Meteoroid and Orbital
Debris Environments. The Final Mission Report generally includes a summary of the mission
accomplishments, science data/samples collected, and a summary of the results achieved. This report
is prepared in conjunction with documenting the mission’s lessons learned as described in NPD
7120.6, Knowledge Policy for Programs and Projects and the project’s Knowledge Management
Plan. Projects need to ensure that resources are allocated to develop the Final Mission Report and
lessons learned. These provide a valuable historical record of NASA’s accomplishments and the
issues that were encountered and overcome as part of the mission.
Formal Dissent. A substantive disagreement with a decision or action that an individual judges is
not in the best interest of NASA and is of sufficient importance that it warrants a timely review and
decision by higher-level management.
Formulation. The identification of how the program or project supports the Agency’s strategic
needs, goals, and objectives; the assessment of feasibility, technology, and concepts; risk
assessment, team building, development of operations concepts, and acquisition strategies;
establishment of high-level requirements and success criteria; the preparation of plans, budgets, and
schedules essential to the success of a program or project; and the establishment of control systems
to ensure performance to those plans and alignment with current Agency strategies.
Formulation Agreement. The Formulation Agreement is prepared by the project to establish the
technical and acquisition work that needs to be conducted during Formulation and defines the
schedule and funding requirements during Phase A and Phase B for that work.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 56 of 147
NPR 7120.5F -- AppendixA Page 56 of 147
Formulation Authorization Document. The document issued by the MDAA to authorize the
formulation of a program whose goals will fulfill part of the Agency’s Strategic Plan and Mission
Directorate strategies and establish the expectations and constraints for activity in the Formulation
Phase. In addition, a FAD or equivalent is used to authorize the formulation of a project. (See
Appendix E.)
Formulation Phase. The first part of a program or project life cycle where Formulation activities
are completed. The Formulation Phase begins at Approval for Formulation and ends at Approval for
Implementation as depicted in life-cycle figures 2-2 through 2-5 of this NPR.
Funding (budget authority). The authority provided by law to incur financial obligations that will
result in expenditures. There are four basic forms of budget authority, but only two are applicable to
NASA: appropriations and spending authority from offsetting collections (reimbursables and
working capital funds). Budget authority is provided or delegated to programs and projects through
the Agency’s funds distribution process.
Health and Medical Requirements. Requirements defined by the Office of the Chief Health and
Medical Officer (OCHMO).
Human Systems Integration. A required interdisciplinary integration of the human as an element
of the system to ensure that the human and software/hardware components cooperate, coordinate,
and communicate effectively to perform a specific function or mission successfully.
Implementation. The execution of approved plans for the development and operation of the
program/project and the use of control systems to ensure performance to approved plans and
continued alignment with the Agency’s strategic needs, goals, and objectives.
Implementation Phase. The second part of a program or project life cycle where Implementation
activities are completed. The Implementation Phase begins at Approval for Implementation and
continues through the end of the program or project as depicted in life-cycle figures 2-2 through 2-5
of this NPR.
In-House (EVM). Project work scope conducted solely using NASA HQ and/or Center personnel or
other NASA resources (i.e., facilities, equipment), including support contractors that augment
NASA resources to achieve the objectives of the project. There is no prime contractor, university,
laboratory, institution, or foreign partner involvement in in-house work.
Independent Assessment(s) (includes reviews, evaluations, audits, analysis oversight,
investigations). Assessments are independent to the extent the involved personnel apply their
expertise impartially and without any conflict of interest or inappropriate interference or influence,
particularly from the organization(s) being assessed.
Independent Funding (context of Technical Authority). The funding of Technical Authorities is
considered independent if funding originating from the Mission Directorate or other Programmatic
Authorities is provided to the Center in a manner that cannot be used to influence the technical
independence or security of Technical Authorities.
Industrial Base. The capabilities residing in either the commercial or government sector required to
design, develop, manufacture, launch, and service the program or project. This encompasses related
manufacturing facilities, supply chain operations and management, a skilled workforce, launch
infrastructure, research and development, and support services.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 57 of 147
NPR 7120.5F -- AppendixA Page 57 of 147
Information Technology. Any equipment or interconnected system or subsystem of equipment that
is used in the automatic acquisition, storage, manipulation, management, movement, control,
display, switching, interchange, transmission, or reception of data or information by an executive
Agency. Information technology also includes computers; ancillary equipment (including imaging
peripherals, input, output, and storage devices necessary for security and surveillance); peripheral
equipment designed to be controlled by the central processing unit of a computer; software;
firmware; and similar procedures, services (including support services), and related resources. It
does not include any equipment acquired by a Federal contractor incidental to a Federal contract.
Infrastructure Requirements. The facilities real property (buildings and/or other structures) and
environmental, aircraft, personal property, collateral equipment, and associated system resources
that are needed to support programs and projects. Utilization of the capability afforded by the
infrastructure includes consideration of the life-cycle cost (design, construction, commissioning,
outfitting, special test equipment, utilities, operations and maintenance, and future disposal cost) and
other liabilities it presents. The construction of real property infrastructure or the modification of
existing infrastructure above a defined dollar amount must go through the Agency’s Construction of
Facilities account (CECR). (See NPR 9250.1, Property, Plant, and Equipment and Operating
Materials and Supplies, NPD 8800.14, Policy for Real Estate Management, and NPR 8820.2,
Facility Project Requirements.)
Initial Capability. For single-project programs and projects that plan continuing operations and
production, including integration of capability upgrades, with an unspecified Phase E end point, the
initial capability is the first operational mission flight or as defined as part of the KDP B review
plan. The scope of the initial capability is documented in the KDP B Decision Memorandum.
Institutional Authority. Institutional Authority encompasses all those organizations and authorities
not in the Programmatic Authority. This includes engineering, safety and mission assurance, and
health and medical organizations; mission support organizations; and Center Directors.
Institutional Requirements. Requirements that focus on how NASA does business that are
independent of the particular program or project. There are five types: engineering, program/project
management, safety and mission assurance, health and medical, and mission support requirements.
Integrated Baseline Review. A risk-based review conducted by Program/Project Management to
ensure a mutual understanding between the customer and supplier of the risks inherent in the
supplier’s Performance Measurement Baseline (PMB) and to ensure that the PMB is realistic for
accomplishing all of the authorized work within the authorized schedule and budget.
Integrated Center Management Council. The forum used by projects and programs that are being
implemented by more than one Center and includes representatives from all participating Centers.
The ICMC will be chaired by the director of the Center (or representative) responsible for program
or project management.
Integrated Logistics Support. The management, engineering activities, analysis, and information
management associated with design requirements definition, material procurement and distribution,
maintenance, supply replacement, transportation, and disposal that are identified by space flight and
ground systems supportability objectives.
Integrated Master Schedule. A logic network-based schedule that reflects the total project scope of
work, traceable to the WBS, as discrete and measurable tasks/milestones and supporting elements
that are time phased through the use of valid durations based on available or projected resources and
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 58 of 147
NPR 7120.5F -- AppendixA Page 58 of 147
well-defined interdependencies.
Integrated Program Management Report. The standard report format to communicate
program/project monthly cost/schedule performance and status between a contractor and the
Government. The IPMR consists of seven report formats that provide program/project managers
information to: integrate cost and schedule performance data with technical performance measures,
identify the magnitude and impact of actual and potential problem areas causing significant cost and
schedule variances, forecast schedule completions, and provide valid, timely program/project status
information to higher management for effective decision making. This is a contract data requirement
when EVM is required.
Integration Plan. The integration plan defines the configuration of expected aggregates of system
elements and the order of assembly of these aggregates to carry out efficient verification and
validation actions. The integration plan is structured to bring the elements together to assemble each
subsystem and to bring all of the subsystems together to assemble the system/product. The primary
purposes of the integration plan are: (1) to describe this coordinated integration effort that supports
the implementation strategy, (2) to describe for the participants what needs to be done in each
integration step, and (3) to identify the required resources and when and where they will be needed.
Interface Control Document. An agreement between two or more parties on how interrelated
systems will interface with each other. It documents interfaces between things like electrical
connectors (e.g., what type, how many pins, what signals will be on each of the pins, etc.); fluid
connectors (type of connector or of fluid being passed, flow rates of the fluid, etc.); mechanical
(types of fasteners, bolt patterns, etc.); and any other interfaces that might be involved.
Joint Cost and Schedule Confidence Level. The probability that cost will be equal to or less than
the targeted cost and schedule will be equal to or less than the targeted schedule date. The JCL
calculation includes consideration of the risk associated with all elements, regardless of whether or
not they are funded from appropriations or managed outside of the project (e.g., risk impacts of a
foreign contribution behind schedule, risk impacts of the Launch Vehicle). JCL calculations include
content from the milestone at which the JCL is calculated through the completion of Phase D
activities. (See the NASA Cost Estimating Handbook for more information on JCL.)
Key Decision Point. The event at which the Decision Authority determines the readiness of a
program/project to progress to the next phase of the life cycle (or to the next KDP).
Knowledge Management. A collection of policies, processes, and practices relating to the use of
intellectual and knowledge-based assets in an organization.
Lessons Learned. Captured knowledge or understanding gained through experience which, if
shared, would benefit the work of others. Unlike a best practice, lessons learned describes a specific
event that occurred and provides recommendations for obtaining a repeat of success or for avoiding
reoccurrence of an adverse work practice or experience.
Life-Cycle Cost. The total of the direct, indirect, recurring, nonrecurring, and other related expenses
both incurred and estimated to be incurred in the design, development, verification, production,
deployment, prime mission operation, maintenance, support, and disposal of a project, including
closeout, but not extended operations. The LCC of a project or system can also be defined as the
total cost of ownership over the project or system’s planned life cycle from Formulation (excluding
Pre-Phase A) through Implementation (excluding extended operations). The LCC includes the cost
of the launch vehicle.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 59 of 147
NPR 7120.5F -- AppendixA Page 59 of 147
Life-Cycle Review. A review of a program or project designed to provide a periodic assessment of
the technical and programmatic status and health of a program or project at a key point in the life
cycle (e.g., Preliminary Design Review (PDR) or Critical Design Review (CDR)). Certain life-cycle
reviews provide the basis for the Decision Authority to approve or disapprove the transition of a
program/project at a KDP to the next life-cycle phase.
Loosely Coupled Programs. These programs address specific objectives through multiple space
flight projects of varied scope. While each individual project has an assigned set of mission
objectives, architectural and technological synergies and strategies that benefit the program as a
whole are explored during the Formulation process. For instance, Mars orbiters designed for more
than one Mars year in orbit are required to carry a communication system to support present and
future landers.
Management Agreement. Within the Decision Memorandum, the parameters and authorities over
which the program or project manager has management control constitute the program or project
Management Agreement. A program or project manager has the authority to manage within the
Management Agreement and is accountable for compliance with the terms of the agreement.
Margin. The allowances carried in budget (See Unallocated Future Expenses), projected schedules,
and technical performance parameters (e.g., weight, power, or memory) to account for uncertainties
and risks. Margins are allocated in the formulation process, based on assessments of risks, and are
typically consumed as the program/project proceeds through the life cycle.
Metric. A measurement taken over a period of time that communicates vital information about the
status or performance of a system, process, or activity.
Mission. A major activity required to accomplish an Agency goal or to effectively pursue a
scientific, technological, or engineering opportunity directly related to an Agency goal. Mission
needs are independent of any particular system or technological solution.
Mission Operations Plan. The Mission Operations Plan describes the activities required to perform
the mission. It describes how the program or project will implement the associated facilities,
hardware, software, and procedures required to complete the mission. It describes mission
operations plans, rules, and constraints; the Mission Operations System (MOS); and the Ground
Data System (GDS).
Mission Resilience. The ability of a mission system to withstand or recover from adverse conditions
such as intrusion, subversion, disruption, degradation, or destruction from environmental or hostile
causes.
Mission Support Office Requirements. Requirements defined by mission support offices (e.g.,
procurement and infrastructure).
Non-Applicable Requirement. Any requirement that is not relevant or not capable of being
applied. The non-applicable requirement provision is intended to provide an efficient means to grant
and document relief from a requirement not relevant or not capable of being applied to the specific
mission. The need for relief from the requirement is obvious and the judgment of non-applicable is
likely to be the same regardless of who makes the determination. For example, the requirement to
produce a Human-Rating Certification Package is non-applicable for a robotic project.
Operations Concept Documentation. A description of how the flight system and the ground
system are used together to ensure that the concept of operation is reasonable. This might include
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 60 of 147
NPR 7120.5F -- AppendixA Page 60 of 147
how mission data of interest, such as engineering or scientific data, are captured, returned to Earth,
processed, made available to users, and archived for future reference. The Operations Concept
documentation should describe how the flight system and ground system work together across
mission phases for launch, cruise, critical activities, science observations, and end of mission to
achieve the mission.
Operations Handbook. The Operations Handbook provides information essential to the operation
of a spacecraft and other components of a mission. It generally includes a description of the
spacecraft and other mission components and the operational support infrastructure; operational
procedures, including step-by-step operational procedures for activation and deactivation;
malfunction detection procedures; and emergency procedures. The handbook identifies the
commands for the spacecraft and other mission components, defines the functions of these
commands, and provides supplemental reference material for use by the operations personnel. The
main emphasis is placed on command types, command definitions, command sequences, and
operational constraints. Additional document sections may describe uploadable operating
parameters, the telemetry stream data contents (for both the science and the engineering data), the
Mission Operations System displays, and the spacecraft and other mission component health
monitors.
Orbital Debris. Any object placed in space by humans that remains in orbit and no longer serves
any useful function. Objects range from spacecraft to spent launch vehicle stages to components and
also include materials, trash, refuse, fragments, and other objects that are overtly or inadvertently
cast off or generated.
Performance Measurement Baseline. The time-phased budget plan for accomplishing all
authorized work scope in a project’s life cycle, which includes both NASA internal costs and
supplier costs. The PMB is used to measure project performance using EVM, if required, or other
performance measurement techniques if EVM is not required. It is formed by the budgets assigned
to scheduled control accounts and the applicable indirect budgets. For future effort, not planned to
the control account level, the PMB also includes budgets assigned to higher level WBS elements and
undistributed budgets. The PMB does not include UFE, or management reserve (MR) for
contractors.
Pre-Acquisition Strategy Meeting. A precursor meeting to an ASM, reserved for complex or
multi-part acquisitions, such as those involving an integrated observatory, campaign, or other
coupled programs with multiple mission elements. Pre-ASMs may also be used for multi-phase
acquisitions, such as an extended contracted study/demonstration phase prior to acquisition of final
elements or services. Pre-ASMs are held at the discretion of the Convening Authority. (See NAII
1000.1 under NPD 1000.5 for additional details.)
Preliminary (document context). Implies that the product has received initial review in accordance
with Center best practices. The content is considered correct, though some TBDs may remain. All
approvals required by Center policies and procedures have been obtained. Major changes are
expected.
Prescribed Requirement. A requirement levied on a lower organizational level by a higher
organizational level.
Principal Investigator. A person who conceives an investigation and is responsible for carrying it
out and reporting its results. In some cases, PIs from industry and academia act as project managers
for smaller development efforts with NASA personnel providing oversight.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 61 of 147
NPR 7120.5F -- AppendixA Page 61 of 147
Procurement Strategy Meeting. A forum where management reviews and approves the approach
for the Agency’s major and other selected procurements. Chaired by the Assistant Administrator for
Procurement (or designee), the Procurement Strategy Meeting (PSM) addresses and documents
information, activities, and decisions required by the FAR and NFS and incorporates NASA
strategic guidance and decisions from the ASM strategic acquisition meeting to ensure the alignment
of the individual procurement action with NASA’s portfolio and mission.
Program. A strategic investment by Mission Directorates or mission support offices that has a
defined architecture and/or technical approach, requirements, funding level, and management
structure that initiates and directs one or more projects. A program implements a strategic direction
that the Agency has identified as needed to accomplish Agency goals and objectives. (See Section
2.1.2.)
Program Commitment Agreement. The contract between the NASA AA and the responsible
MDAA that authorizes transition from Formulation to Implementation of a program. (See Appendix
D.)
Program/Project Management Requirements. Requirements that focus on how NASA and
Centers perform program and project management activities.
Program Plan. The document that establishes the program’s baseline for Implementation, signed by
the MDAA, Center Director(s), and program manager.
Program (Project) Team. All participants in program (project) Formulation and Implementation.
This includes all direct reports and others that support meeting program (project) responsibilities.
Programmatic Authority. Programmatic Authority includes the Mission Directorates and their
respective program and project managers. Individuals in these organizations are the official voices
for their respective areas. Programmatic Authority sets, oversees, and ensures conformance to
applicable programmatic requirements.
Programmatic Requirements. Requirements set by the Mission Directorate, program, project, and
PI, if applicable. These include strategic scientific and exploration requirements, system
performance requirements, safety requirements, and schedule, cost, and similar nontechnical
constraints.
Project. A space flight project is a specific investment identified in a Program Plan having defined
requirements, a life-cycle cost, a beginning, and an end. A project also has a management structure
and may have interfaces to other projects, agencies, and international partners. A project yields new
or revised products that directly address NASA’s strategic goals.
Project Plan. The document that establishes the project’s baseline for Implementation, signed by
the responsible program manager, Center Director, project manager, and the MDAA, if required.
(See Appendix H.)
Project Scientist. For PI-led competed projects, the project scientist is part of the PI team and works
closely with the PI. The project scientist is typically delegated the responsibility to monitor the
scientific output of the project and ensure that the project achieves each of its science requirements.
For directed projects, there is no mission PI. The project scientist is nominated by the Center and
approved by the Mission Directorate and is responsible for a more significant fraction of the
project-level management than in a competed project. The project scientist works closely with the
project manager and is directly responsible for all science related tasks. Project scientists are
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 62 of 147
NPR 7120.5F -- AppendixA Page 62 of 147
project manager and is directly responsible for all science related tasks. Project scientists are
primarily associated with SMD projects.
Rebaselining. The process that results in a change to a project’s Agency Baseline Commitment.
Reimbursable Program/Project. A project (including work, commodities, or services) for
customers other than NASA for which reimbursable agreements have been signed by both the
customer and NASA. The customer provides funding for the work performed on their behalf.
Replanning. The process by which a program or project updates or modifies its plans.
Request for Action/Review Item Discrepancy. The most common names for the comment forms
that reviewers submit during life-cycle reviews that capture their comments, concerns, and/or issues
about the product or documentation.
Residual Risk. The remaining risk that exists after all mitigation actions have been implemented or
exhausted in accordance with the risk management process. (See NPD 8700.1, NASA Policy for
Safety and Mission Success.)
Risk. In the context of mission execution, risk is the potential for performance shortfalls, which may
be realized in the future, with respect to achieving explicitly established and stated performance
requirements. The performance shortfalls may be related to any one or more of the following
mission execution domains: (1) safety, (2) technical, (3) cost, and (4) schedule. (See NPR 8000.4,
Agency Risk Management Procedural Requirements.)
Risk Assessment. An evaluation of a risk item that determines: (1) what can go wrong, (2) how
likely is it to occur, (3) what the consequences are, (4) what the uncertainties are that are associated
with the likelihood and consequences, and (5) what the mitigation plans are.
Risk Management. Risk management includes risk-informed decision making (RIDM) and
continuous risk management (CRM) in an integrated framework. RIDM informs systems
engineering decisions through better use of risk and uncertainty information in selecting alternatives
and establishing baseline requirements. CRM manages risks over the course of the development and
the Implementation Phase of the life cycle to ensure that safety, technical, cost, and schedule
requirements are met. This is done to foster proactive risk management, to better inform decision
making through better use of risk information, and then to more effectively manage Implementation
risks by focusing the CRM process on the baseline performance requirements emerging from the
RIDM process. (See NPR 8000.4, Agency Risk Management Procedural Requirements.) These
processes are applied at a level of rigor commensurate with the complexity, cost, and criticality of
the program.
Risk-Informed Decision Making. A risk-informed decision-making process that uses a diverse set
of performance measures (some of which are model-based risk metrics) along with other
considerations within a deliberative process to inform decision making.
Risk-Informed Probabilistic Analysis. Analysis informed by all appropriate discrete risks and
uncertainties including those that may not be discretely managed in the risk management system.
Safety. Freedom from those conditions that can cause death, injury, occupational illness, damage to
or loss of equipment or property, or damage to the environment.
Safety and Mission Assurance Requirements. Requirements defined by the SMA organization
related to safety and mission assurance.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 63 of 147
NPR 7120.5F -- AppendixA Page 63 of 147
Security. Protection of people, property, and information assets owned by NASA that covers
physical assets, personnel, IT, communications, and operations.
Signature. A distinctive mark, characteristic, or thing that indicates identity; one’s name as written
by oneself.
Single-Project Programs. These programs tend to have long development and/or operational
lifetimes, represent a large investment of Agency resources, and have contributions from multiple
organizations/agencies. These programs frequently combine program and project management
approaches, which they document through tailoring.
Stakeholder. An individual or organizational customer having an interest (or stake) in the outcome
or deliverable of a program or project.
Standards. Formal documents that establish a norm, requirement, or basis for comparison, a
reference point to measure or evaluate against. A technical standard, for example, establishes
uniform engineering or technical criteria, methods, processes, and practices. (Refer to NPR 7120.10,
Technical Standards for NASA Programs and Projects.)
Standing Review Board. The board responsible for conducting independent reviews (life cycle and
special) of a program/project and providing objective, expert judgments to the convening authorities.
The reviews are conducted in accordance with approved Terms of Reference (ToR) and life-cycle
requirements per this document and NPR 7123.1.
Success Criteria. That portion of the top-level requirements that defines what is to be achieved to
successfully satisfy NASA Strategic Plan objectives addressed by the program or project.
Suppliers. Each project office is a customer having a unique, multi-tiered hierarchy of suppliers to
provide it products and services. A supplier may be a contractor, grantee, another NASA Center,
university, international partner, or other government agency. Each project supplier is also a
customer if it has authorized work to a supplier lower in the hierarchy.
Supply Chain. The specific group of suppliers and their interrelationships that is necessary to
design, develop, manufacture, launch, and service the program or project. This encompasses all
levels within a space system, including providers of raw materials, components, subsystems,
systems, systems integrators, and services.
System. The combination of elements that function together to produce the capability required to
meet a need. The elements include all hardware, software, equipment, facilities, personnel,
processes, and procedures needed for this purpose.
Systems Engineering. Per NPR 7123.1, NASA systems engineering is a logical systems approach
performed by multidisciplinary teams to engineer and integrate NASA’s systems to ensure NASA
products meet the customer’s needs. Implementation of this systems approach will enhance NASA’s
core engineering capabilities while improving safety, mission success, and affordability. This
systems approach is applied to all elements of a system (i.e., hardware, software, and human) and all
hierarchical levels of a system over the complete program/project life cycle.
Tailoring. The process used to adjust or seek relief from a prescribed requirement to accommodate
the needs of a specific task or activity (e.g., program or project). The tailoring process results in the
generation of deviations and waivers depending on the timing of the request.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 64 of 147
NPR 7120.5F -- AppendixA Page 64 of 147
Technical Authority. Part of NASA’s system of checks and balances that provides independent
oversight of programs and projects in support of safety and mission success through the selection of
individuals at delegated levels of authority. These individuals are the Technical Authorities.
Technical Authority delegations are formal and traceable to the Administrator. Individuals with
Technical Authority are funded independently of a program or project.
Technical Authority Requirements. Requirements invoked by OCE, OSMA, and Office of the
Chief Health and Medical Officer (OCHMO) documents (e.g., NPRs or technical standards cited as
program or project requirements) or contained in Center institutional documents. These requirements
are the responsibility of the office or organization that established the requirement unless delegated
elsewhere.
Technical Standard. Common and repeated use of rules, conditions, guidelines, or characteristics
for products or related processes and production methods and related management systems
practices; the definition of terms, classification of components; delineation of procedures;
specification of dimensions, materials, performance, designs, or operations; measurement of quality
and quantity in describing materials, processes, products, systems, services, or practices; test
methods and sampling procedures; or descriptions of fit and measurements of size or strength.
(Source: OMB Circular No. A-119, Federal Participation in the Development and Use of Voluntary
Consensus Standards and in Conformity Assessment Activities.) (See NPR 7120.10, Technical
Standards for NASA Programs and Projects.)
Technology Readiness Level. Provides a scale against which to measure the maturity of a
technology. TRLs range from 1, Basic Technology Research, to 9, Systems Test, Launch, and
Operations. Typically, a TRL of 6 (i.e., technology demonstrated in a relevant environment) is
required for a technology to be integrated into a flight system. (See NASA Systems Engineering
Handbook NASA/SP-2016-6105 Rev 2 for more information on TRL levels and technology
assessment, and SP-20205003605, Technology Readiness Assessment Best Practices Guide.)
Termination Review. A special review convened to determine whether to continue or terminate a
program or project. Circumstances that could trigger a Termination Review include the anticipated
inability of the program or project to meet its commitments, an unanticipated change in Agency
strategic planning, or an unanticipated change in the NASA budget. (See NASA/SP-20220009501,
NASA Space Flight Program and Project Management Handbook for information on a Termination
Review.)
Terms of Reference. A document specifying the nature, scope, schedule, and ground rules for an
independent review or independent assessment.
Threshold Science Requirements. The mission performance requirements necessary to achieve the
minimum science acceptable for the investment. In some AOs used for competed missions,
threshold science requirements may be called the “science floor” for the mission. (Also see Baseline
Science Requirements.)
Tightly Coupled Programs. Programs with multiple projects that execute portions of a mission(s).
No single project is capable of implementing a complete mission. Typically, multiple NASA Centers
contribute to the program. Individual projects may be managed at different Centers. The program
may also include other agency or international partner contributions.
Unallocated Future Expenses. The portion of estimated cost required to meet a specified
confidence level that has not been allocated to the specific project WBS sub-elements because the
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 65 of 147
NPR 7120.5F -- AppendixA Page 65 of 147
probabilistic estimate includes risks and uncertainties. For additional information on UFE, see the
NASA Space Flight Program and Project Management Handbook.
Uncoupled Programs. Programs implemented under a broad theme and/or a common program
implementation concept, such as providing frequent flight opportunities for cost-capped projects
selected through AO or NASA Research Announcements. Each such project is independent of the
other projects within the program.
Validation. The process of showing proof that the product accomplishes the intended purpose based
on stakeholder expectations. May be determined by a combination of test, analysis, demonstration,
and inspection. (Answers the question, “Am I building the right product?”)
Verification. Proof of compliance with requirements. Verification may be determined by a
combination of test, analysis, demonstration, and inspection. (Answers the question, “Did I build the
product right?”)
Waiver. A documented authorization releasing a program or project from meeting a requirement
after the requirement is put under configuration control at the level the requirement will be
implemented.
Work Breakdown Structure. A product-oriented hierarchical division of the hardware, software,
services, and data required to produce the program’s or project’s end product(s), structured
according to the way the work will be performed and reflecting the way in which program/project
costs and schedule, technical, and risk data are to be accumulated, summarized, and reported.
NPR 7120.5F -- AppendixA
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 66 of 147
NPR 7120.5F -- AppendixA Page 66 of 147
Appendix B. Acronyms
AA Associate Administrator
ABC Agency Baseline Commitment
AI&T Assembly, Integration, and Test
AO Announcement of Opportunity
APMC Agency Program Management Council
ASC Acquisition Strategy Council
ASM Acquisition Strategy Meeting
BOE Basis of Estimate
BPR Baseline Performance Review
CADRe Cost Analysis Data Requirement
CDR Critical Design Review
CE Chief Engineer
CERR Critical Events Readiness Review
CFO Chief Financial Officer
CHMO Chief Health and Medical Officer
CIO Chief Information Officer
CMC Center Management Council
COI Conflict of Interest
COOP Continuity of Operations
CPD Center Policy Directive
CPMO Chief Program Management Officer
CPR Center Procedural Requirements
CRM Continuous Risk Management
DFM Decision Framing Meeting
DPMC Mission Directorate Program Management Council
DR Decommissioning Review
DRR Disposal Readiness Review
ELV Expendable Launch Vehicle
EMD Environmental Management Division
EOMP End of Mission Plan
NPR 7120.5F -- AppendixB
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 67 of 147
NPR 7120.5F -- AppendixB Page 67 of 147
ETA Engineering Technical Authority
EVM Earned Value Management
EVMS EVM System
FAD Formulation Authorization Document
FAR Federal Acquisition Regulation
FC Fully Compliant
FFRDC Federally Funded Research and Development Centers
FRED Facilities Real Estate Division
FRR Flight Readiness Review
FTE Full-Time Equivalent
GDS Ground Data System
HMTA Health and Medical Technical Authority
HQ Headquarters
HSI Human Systems Integration
IBR Integrated Baseline Review
ICD Interface Control Document
ICMC Integrated Center Management Council
ILS Integrated Logistics Support
IMS Integrated Master Schedule
IPMR Integrated Program Management Report
IT Information Technology
JCL Joint Cost and Schedule Confidence Level
KDP Key Decision Point
LCC Life-Cycle Cost
LCR Life-Cycle Review
LDE Lead Discipline Engineer
LMD Logistics Management Division
LRR Launch Readiness Review
MCR Mission Concept Review
MDAA Mission Directorate Associate Administrator
MdM Meta-Data Manager
MDR Mission Definition Review
NPR 7120.5F -- AppendixB
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 68 of 147
NPR 7120.5F -- AppendixB Page 68 of 147
MOS Mission Operations System
MOU Memorandum of Understanding
MRR Mission Readiness Review
MSD Mission Support Directorate
NA Non-Applicable
NEN NASA Engineering Network
NEPA National Environmental Policy Act
NESC NASA Engineering and Safety Center
NFS NASA Federal Acquisition Regulation (FAR) Supplement
NID NASA Interim Directive
NOA New Obligation Authority
NODIS NASA Online Directives Information System
NPD NASA Policy Directive
NPR NASA Procedural Requirements
OCE Office of the Chief Engineer
OCFO Office of the Chief Financial Officer
OCHMO Office of the Chief Health and Medical Officer
OCIO Office of the Chief Information Officer
OComm Office of Communications
ODAR Orbital Debris Assessment Report
OGC Office of the General Counsel
OIIR Office of International and Interagency Relations
OMB Office of Management and Budget (Executive Office of the White House)
OPS Office of Protective Services
ORR Operational Readiness Review
OSI Office of Strategic Infrastructure
OSMA Office of Safety and Mission Assurance
PCA Program Commitment Agreement
PCE Program (or Project) Chief Engineer
PDR Preliminary Design Review
POC Point of Contact
PFAR Post-Flight Assessment Review
NPR 7120.5F -- AppendixB
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 69 of 147
NPR 7120.5F -- AppendixB Page 69 of 147
PI Principal Investigator
PIR Program Implementation Review
PLAR Post-Launch Assessment Review
PMB Performance Measurement Baseline
PMC Program Management Council
PMIAA Program Management Improvement and Accountability Act
PPBE Planning, Programming, Budgeting, and Execution
PRA Probabilistic Risk Assessment
Pre-ASM Pre-Acquisition Strategy Meeting
PRR Production Readiness Review
PSM Procurement Strategy Meeting
RFA Request for Action
RFP Request for Proposal
RID Review Item Discrepancy
RIDM Risk-Informed Decision Making
SAR System Acceptance Review
SDR System Definition Review
SEMP Systems Engineering Management Plan
SI Système Internationale (or metric) system of measurement
SID Strategic Investments Division
SIR System Integration Review
SMA Safety and Mission Assurance
SMD Science Mission Directorate
SMSR Safety and Mission Success Review
SRB Standing Review Board
SRR System Requirements Review
TA Technical Authority
TBD To Be Determined
TBR To Be Resolved
TRL Technology Readiness Level
ToR Terms of Reference
UFE Unallocated Future Expenses
NPR 7120.5F -- AppendixB
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 70 of 147
NPR 7120.5F -- AppendixB Page 70 of 147
WBS Work Breakdown Structure
WYE Work Year Equivalent
NPR 7120.5F -- AppendixB
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 71 of 147
NPR 7120.5F -- AppendixB Page 71 of 147
STUFF
NPR 7120.5F --
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 72 of 147
NPR 7120.5F -- Page 72 of 147
Appendix C. Compliance Matrix and Tailoring Guidance and Resources
Guidance and resources to assist programs and projects in tailoring NPR 7120.5, NASA Space Flight Program and Project Management Requirements, requirements have been established
and/or developed by the Agency, Mission Directorates, and Centers. These include compliance matrices (see Section C.1), consultation and assistance for tailoring (see Section C.2), and
resources for developing the tailoring approach (see Section C.3). An Agency Tailoring Web site which includes many of these resources is available at
https://appel.nasa.gov/npr-7120-5-tailoring-resources.
C.1 Compliance Matrix
C.1.1 The Compliance Matrix documents the program’s or project’s compliance with the requirements of NPR 7120.5 or how the program or project is tailoring the requirements in
accordance with Section 3.5. It is submitted as part of the Formulation Agreement, Program Plan, or Project Plan. The Compliance Matrix is provided to streamline the tailoring (waiver and
deviation) process described in Section 3.5 and may be used to document approval for designating requirements as non-applicable. (See Section 3.5.3.) If the Compliance Matrix is
completed in accordance with these instructions, it meets the requirements for requesting tailoring and for designating requirements as non-applicable and serves as a group submittal for
waivers to NPR 7120.5. Once the Formulation Agreement or Program or Project Plan is signed, tailoring and non-applicable designations are approved. A copy is forwarded to the CPMO
and OCE for programs and Category 1 projects and to OCE for Category 2 and 3 projects. If the Compliance Matrix changes or if compliance is phased for existing programs or projects,
updated versions of the Compliance Matrix are incorporated into an approved Formulation Agreement or Program or Project Plan revision.
C.1.2 Compliance Matrix options have been developed to facilitate the tailoring process. Programs and projects may use the full Compliance Matrix, or, if applicable, a pre-customized
Compliance Matrix template, or a pre-approved Blanket Tailoring Compliance Matrix. (See Agency Tailoring Web site for examples of these Compliance Matrices and templates.) The
project manager or program manager should coordinate with the program or the Mission Directorate, respectively, to select and obtain the appropriate approval for using a Compliance
Matrix other than the full Compliance Matrix. Instructions for completing a Compliance Matrix are provided below.
a. Full Compliance Matrix: The full Compliance Matrix is provided in Table C-1 and on the Agency Tailoring Web site. It is also available on the OCE tab under the “Other NASA-Level
Documents” menu in NODIS.
b. Pre-customized Compliance Matrix Templates: These Compliance Matrix templates eliminate non-applicable requirements for specific types of programs and projects. Programs and
projects may choose to use the applicable pre-customized template instead of the full Compliance Matrix in Table C-1 to document and obtain approval for tailoring. Examples of
pre-customized compliance matrix templates include templates for Uncoupled and Loosely Coupled Programs, Tightly Coupled Programs, Single-Project Programs, and projects.
c. Pre-approved Blanket Tailoring Compliance Matrices: Mission Directorates and programs may and are encouraged to develop tailored Compliance Matrices and obtain approval for
tailoring specific types of programs and projects under their purview. Mission Directorates and programs are required to follow the instructions outlined in “Template Instructions” (see
below) for identifying tailored requirements, developing justifications for tailoring, and obtaining approval for tailoring from requirement owners and from the CPMO for the NASA AA to
establish a pre-approved blanket tailoring Compliance Matrix. Programs and projects that are eligible to invoke these pre-approved Compliance Matrices are not required to obtain approval
for the tailored requirements since that approval has already been obtained by the Mission Directorate or program. (Approval for additional tailoring is required.) For example, the STMD
Technology Demonstration Program has a pre-approved Compliance Matrix.
C.1.3 Template Instructions
C.1.3.1 The Compliance Matrix lists:
a. The paragraph reference.
b. The NPR 7120.5 requirement statement.
c. The “requirement owner” (the organization or individual responsible for the requirement).
d. Whether tailoring authority for the requirement is delegated or held at HQ.
e. The organization or individual to whom the requirement applies (MDAA, CD, PM).
f. A “comply?” column to describe applicability or intent to tailor.
g. The “justification” column to justify the rationale for tailoring and how tailoring is to be applied.
h. The “approval” column when signatures are required to approve tailoring.
C.1.3.2 The “Requirement Owner” column designates which organization is responsible for maintaining the requirement for the Agency. The head of the requirement owner’s organization
has the authority for approving tailoring unless this authority has been formally delegated. The “Delegated” column indicates whether the HQ’s requirement owner has delegated or retained
approval authority for tailoring of the requirement.
a. “Yes” in the “Delegated” column indicates that tailoring authority has been delegated by the requirement owner.
b. “No” in the “Delegated” column indicates that tailoring authority has been retained by the requirement owner.
c. Check the Agency Tailoring Web site for the POC who can provide the name of the HQ person with tailoring approval authority or the organization to which the authority is delegated.
d. If the “Delegated” column is blank, programs and projects should:
(1) Check the Agency Tailoring Web site for information on delegation by the requirement owner and/or
(2) Check the Agency Tailoring Web site for the HQ requirement owner’s POC and work with the POC to determine if tailoring authority has been retained or delegated.
C.1.3.3 The next three columns (“MDAA,” “CD,” and “PM”) designate to whom the requirement applies. An “A” in the column indicates applicability. Programs and projects do not need to
address requirements that are not applicable to “PM.”
C.1.3.4 The “Comply?” column is filled in by the program or project to identify the program’s or project’s approach to the requirement. The project inserts an “FC” for “fully compliant,”
“T” for “tailored,” or “NA” for a requirement that is “non-applicable,” per Section 3.5.3. (See Appendix A for the definition of a Non-Applicable Requirement.)
C.1.3.5 The column titled “Justification” documents the rationale for tailoring, documents how the requirement will be tailored, or justifies why the requirement is not applicable. It is
expected that much of the rationale will already have been developed in retrievable program and/or project records and can simply be referenced (in an appropriate, accessible form). The
level of documentation should be commensurate with the significance of departure from the norm and is determined by the requirement owner or as delegated. In the case where evaluation
indicates that the tailoring of a requirement increases risk, evidence of official acceptance of that risk should be provided as referenced in retrievable program or project records. Columns in
the Compliance Matrix can be adjusted to accommodate the necessary information.
C.1.3.6 The “Approval” column is used to indicate approval for tailored requirements. The name, title, and signature of the responsible authority (requirement owner or delegate) in this
column indicates that approval and any required concurrences have been obtained. The requirement owner consults with the other organizations that were involved in the establishment of
the specific requirement and obtains the concurrence of those organizations having a substantive interest.
a. The name, title, and signature of the responsible authority indicating approval of tailoring is required only for tailored requirements, i.e., those requirements with a “T” in the “Comply”
column. This is not required for requirements with “NA” in the “Comply” column.
b. For requirements for which tailoring authority has been retained, program and project managers should work with the HQ requirement owners’ POCs to obtain the names of individuals
with tailoring approval authority.
c. For requirements that have been delegated, program and project managers should work with the delegated representative or with the HQ requirement owners’ POCs to obtain information
specific to the delegated authorities.
C.1.3.7 Redundant signatures are not required in the “Approval” column of the Compliance Matrix, if the requirement owner is already a required signatory (e.g., MDAA, Center Director,
program manager, and project manager) on the Formulation Agreement, Program Plan, or Project Plan. An example of this would be OCE requirements that have been delegated to the
Center Director. In this case, a separate signature by the Center Director is not required in the “Approval” column since the Center Director is a signatory on the plan. However, if tailoring
was proposed for a requirement by an owner who isn’t normally a signatory on the Formulation Agreement, Program Plan, or Project Plan (e.g., OSMA), the program or project manager
should obtain the signature of the approving official in the “Approval” column of the Compliance Matrix prior to submitting the Formulation Agreement, Program Plan, or Project Plan for
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 73 of 147
NPR 7120.5F -- AppendixC Page 73 of 147
final signature.
C.2 Consultation and Assistance for Tailoring
C.2.1 HQ requirements owners and some Mission Directorates have identified points-of-contact for consulting with and assisting programs and projects in developing their tailoring
approach and in obtaining approval for tailoring as described below. A list of these points-of-contact is provided on the Agency Tailoring Web site.
a. Points-of-contact for HQ requirements owners are available to assist programs and projects in identifying the tailoring authority designated to approve tailoring of requirements owned by
their organization, i.e., either the name of the HQ person or the organization to which the authority is delegated. In addition, some HQ requirements owners provide documented information
on delegation of tailoring authority.
b. CPMO point(s)-of-contact are available to provide consultation to programs and projects in developing their tailoring approach. The level of support depends on the extent of tailoring
needed and may range from a simple phone conversation to identifying a group of tailoring SMEs (at HQ and/or Centers) that can help a program or project develop and gain agreement for
their tailoring approach.
c. Programs, Category 1 projects, and projects that are of high importance or visibility to NASA will coordinate with the CPMO to determine their tailoring approach. The
CPMO-coordinated tailoring approach may need to be presented by the program or project to the NASA Program and Project Management Board (PPMB), as determined by the CPMO.
d. Mission Directorates may designate points-of-contact to obtain tailoring approval from requirement owners for programs and projects.
e. The PPMB may assist programs and projects in tailoring requirements and provide guidance through the tailoring process. The PPMB may be engaged to determine whether to endorse the
program’s or project’s tailoring and adjudicate issues related to tailoring between requirement owners and programs and projects. Individual requirement owners retain the responsibility
and authority to approve tailoring of requirements. Program and project managers interested in assistance from the PPMB should contact the CPMO PPMB Manager or their Center
representative to the PPMB. The CPMO PPMB Manager is identified in the points-of-contact list on the Agency Tailoring Web site. Additionally, the NASA Program/Project Management
Board Charter is available on the Agency Tailoring Web site.
C.3 Resources for Developing the Tailoring Approach
C.3.1 Resources available to programs and projects for developing their tailoring approach are provided on the Agency Tailoring Web site. These resources include:
C.3.2 Tailoring Guidance: Information, various forms of guidance, and implementation plans for developing a program’s or project’s tailoring approach provided by some requirements
owners and Mission Directorates, such as:
a. Guidance provided by "Requirement Owners," including the CPMO for the NASA AA and OCFO, for developing a program’s or project’s tailoring approach. An example is OCFO's
MOU template for tailoring a requirement.
b. Guidance from some Mission Directorates for tailoring specific types of projects, such as SMD’s Class D Tailoring/Streamlining Decision Memorandum and Class D
Tailoring/Streamlining Implementation Plan.
C.3.3 General Overview of Tailoring Approaches: Summary information on tailoring approaches common across multiple programs and projects and requirements that are frequently
tailored.
C.3.4 Specific Tailoring Approaches and Examples: Numerous examples of how specific programs and projects have successfully tailored NPR 7120.5 requirements.
C.3.5 Tailoring Tools: Tools to assist programs and projects in developing their tailoring approach have been developed by some Centers. These tools may also be helpful for programs
and projects hosted at other Centers.
Approver Acronyms:
CPMO Chief Program Management Officer
EMD Environmental Management Division
FRED Facilities Real Estate Division
LMD Logistics Management Division
OCE Office of the Chief Engineer
OCFO Office of the Chief Financial Officer
OCIO Office of the Chief Information Officer
OGC Office of the General Counsel
OIIR Office of International and Interagency Relations
OPS Office of Protective Services
OSI Office of Strategic Infrastructure
OSMA Office of Safety and Mission Assurance
SID Strategic Investments Division
Table C-1 Compliance Matrix
[Program or Project Name]
(See Section C.1.3 for explanation of notation in Table C-1.
I-Table products marked as “Best Practice” (BP) are not included in the Compliance Matrix.
See Section I.1.d for explanation of “Best Practice”.)
Para # NPR 7120.5 Requirement Statement Require-ment Owner Dele-gated
MD
AA
CD PM Com-ply? Justification Approval
2.1.1.2 Regardless of the structure of a program or project meeting
the criteria of Section P.2, this NPR shall apply to the full
scope of the program or project and all the activities under it.
NASA AA No A
2.1.3.1 Projects are Category 1, 2, or 3 and shall be assigned to a
category based initially on: (1) the project life-cycle cost
(LCC) estimate, the inclusion of significant radioactive
material, and whether or not the system being developed is
for human space flight; and (2) the priority level, which is
related to the importance of the activity to NASA, the extent
of international participation (or joint effort with other
government agencies), the degree of uncertainty surrounding
the application of new or untested technologies, and
spacecraft/payload development risk classification.
NASA AA No A
2.1.3.2 For Category 1 projects, the assignment of a project to a
Center or implementing organization shall be with the
concurrence of the NASA AA.
NASA AA No A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 74 of 147
NPR 7120.5F -- AppendixC Page 74 of 147
2.1.4.1 Programs and projects with a LCC or initial capability cost
(see Section 2.4.1.3.b) greater than $250M shall be managed
by program and project managers who have been certified in
compliance with Office of Management and Budget (OMB)’s
promulgated Federal acquisition program/project
management certification requirements.
NASA AA No A
2.2.1 Program and project managers shall follow their appropriate
life cycle as identified in each program and project respective
life- cycle figure. Life cycles include life-cycle phases, gates,
and major events; performing KDPs and major life-cycle
reviews (LCRs); developing principal documents that govern
the conduct of each phase; and re-entering the life cycle
when program or project changes warrant such action.
NASA AA No A
2.2.2 Program and project managers shall organize the work
required for each phase using a product-based WBS
developed in accordance with the Program and Project Plan
templates (appendices G and H).
OCFO Yes A
2.2.3 The documents shown on the life-cycle figures and described
below shall be prepared in accordance with the templates in
appendices D, E, F, G, and H.
NASA AA No A
2.2.4 Each program and project shall perform the LCRs in
accordance with NPR 7123.1, applicable Center practices,
and the requirements of this document.
OCE Yes A
2.2.5 Program or project managers and an independent Standing
Review Board (SRB) shall conduct the System Requirements
Review (SRR), System Definition Review (SDR)/ Mission
Definition Review (MDR), Preliminary Design Review
(PDR), Critical Design Review (CDR), System Integration
Review (SIR), Operational Readiness Review (ORR), and
PIR LCRs in figures 2-2, 2-3, 2-4, and 2-5.
NASA AA No A
2.2.5.1 The Conflict of Interest (COI) procedures detailed in the
NASA Standing Review Board Handbook shall be strictly
adhered to.
OGC No A A A
2.2.5.2 The portion of the LCRs conducted by the SRB shall be
convened by the Convening Authorities in accordance with
Table 2-2.
NASA AA No A A A
2.2.5.3 The program or project manager, the SRB chair, and the
Center Director (or designated Engineering Technical
Authority (ETA) representative) shall mutually assess the
program’s or project’s expected readiness for the LCR and
report any disagreements to the Decision Authority for final
decision.
NASA AA No A A
2.2.6 In preparation for these LCRs, the program or project
manager shall generate the appropriate documentation per the
Appendix I tables of this document, NPR 7123.1, and Center
practices, as necessary, to demonstrate that the program’s or
project’s definition and associated plans are sufficiently
mature to execute the follow-on phase(s) with acceptable
technical, safety, and programmatic risk.
NASA AA No A
Table I-1 Uncoupled and Loosely Coupled Program
Milestone Products and Control Plans Maturity Matrix
Table
I-1
1. FAD [Baseline at approval for Formulation] [Required per
NPR 7120.5]
NASA AA No A A
Table
I-1
2. PCA [Baseline at KDP I] [Required per NPR 7120.5] NASA AA No A
Table
I-1
3. Program Plan [Baseline at SDR] [Required per NPR
7120.5]
NASA AA No A A A
Table
I-1
3.a. Mission Directorate requirements and constraints
[Baseline at SRR] [Required per NPR 7123.1]
OCE Yes A A
Table
I-1
3.b. Traceability of program-level requirements on projects to
the Agency strategic goals and Mission Directorate
requirements and constraints [Baseline at SDR] [Required
per NPR 7123.1]
OCE Yes A A
Table
I-1
3.c. Documentation of driving ground rules and assumptions
on the program [Baseline at SDR] [Required per NPR 7120.5]
NASA AA No A A
Table
I-1
4. Interagency and international agreements [Baseline at SDR] NASA AA No A A
Table
I-1
5. ASM Decision Memorandum [additional information in
NPD 1000.5]
NASA AA No A A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 75 of 147
NPR 7120.5F -- AppendixC Page 75 of 147
Table
I-1
6. Risk mitigation plans and resources for significant risks
[Required per NPR 7120.5]
NASA AA No A
Table
I-1
7. Documented Cost and Schedule Baselines [Baseline at
SDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-1
8. Documentation of Basis of Estimate (cost and schedule)
[Baseline at SDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-1
9. Documentation of performance against plan/baseline,
including status/closure of formal actions from previous KDP
[Required per NPR 7120.5]
NASA AA No A
Table
I-1
10. Industrial Base and Supply Chain Risk Management
(SCRM) Strategy and Status [Baseline at SDR] [Required
per NPR 8735.2]
OSMA No A
Program Plan Control Plans
Table
I-1
1. Technical, Schedule, and Cost Control Plan [Baseline at
SDR] [Required per NPR 7120.5]
NASA AA No A
Table
I-1
2. Safety and Mission Assurance Plan [Baseline at SDR]
[Required per NPRs 8705.2 and 8705.4]
OSMA Yes A
Table
I-1
3. Risk Management Plan [Baseline at SDR]
OSMA Yes A
Table
I-1
4. Acquisition Strategy [Baseline at SDR] [Required per
NPD 1000.5]
NASA AA No A
Table
I-1
6. Systems Engineering Management Plan
[Baseline at SDR] [Required per NPR 7123.1]
OCE Yes A
Table
I-1
7. System Security Plan [Baseline at SDR] [Required per
NPR 2810.1]
OCIO No A
Table
I-1
8. Review Plan [Baseline at SRR] [Required per NPR 7120.5] NASA AA No A
Table
I-1
9. NEPA Compliance Plan [Baseline at SDR] [Required per
NPR 8580.1]
OSI-EMD No A
Table
I-1
10. Configuration Management Plan [Baseline at SDR]
[Required per NPR 7120.5; additional information in NPR
7123.1 and SAE/EIA 649]
OCE Yes A
Table
I-1
11. Security Plan [Baseline at SDR]
[Required per NPR 1040.1 and NPR 1600.1]
OPS No A
Table
I-1
12. Technology Transfer (formerly Export) Control Plan
[Baseline at SDR] [Required per NPR 2190.1]
OIIR No A
Table
I-1
15. Quality Assurance Surveillance Plan [Baseline at SDR]
[Required per NPR 8735.2 and NASA FAR Supplement part
1837.604]
OSMA Yes A
Table I-2 Tightly Coupled Program Milestone
Products Maturity Matrix
Table
I-2
1. FAD [Baseline at approval for Formulation] [Required per
NPR 7120.5]
NASA AA No A A
Table
I-2
2. PCA [Baseline at PDR] [Required per NPR 7120.5] NASA AA No A
Table
I-2
3. Program Plan [Baseline at SDR] [Required per NPR
7120.5]
NASA AA No A A A
Table
I-2
3.a. Mission Directorate requirements and constraints
[Baseline at SRR] [Required per NPR 7123.1]
OCE Yes A A
Table
I-2
3.b. Traceability of program-level requirements on projects to
the Agency strategic goals and Mission Directorate
requirements and constraints
[Baseline at SDR] [Required per NPR 7123.1]
OCE Yes A A
Table
I-2
3.c. Documentation of driving ground rules and assumptions
on the program
[Baseline at SDR] [Required per NPR 7120.5]
NASA AA No A A
Table
I-2
4. Interagency and international agreements
[Baseline at SDR]
NASA AA No A A
Table
I-2
5. ASM Decision Memorandum [additional information in
NPD 1000.5]
NASA AA No A A
Table
I-2
6. Risk mitigation plans and resources for significant risks
[Required per NPR 7120.5]
NASA AA No A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 76 of 147
NPR 7120.5F -- AppendixC Page 76 of 147
Table
I-2
7. Documented Cost and Schedule Baselines
[Baseline at PDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-2
8. Documentation of Basis of Estimate (cost and schedule)
[Baseline at PDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-2
9. CADRe [Baseline at SRR] [Required per NPR 7120.5] OCFO-SID No A
Table
I-2
10. Shared Infrastructure, Staffing, and Scarce Material
Requirements and Plans
NASA AA No A
Table
I-2
11. Documentation of performance against plan/baseline,
including status/closure of formal actions from previous KDP
[Required per NPR 7120.5]
NASA AA No A
Table
I-2
12. Industrial Base and Supply Chain Risk Management
(SCRM) Strategy and Status [Baseline at SDR] [Required
per NPR 8735.2]
OSMA No A
Table I-3 Tightly Coupled Program Plan Control
Plans Maturity Matrix
Table
I-3
1. Technical, Schedule, and Cost Control Plan
[Baseline at SDR] [Required per NPR 7120.5]
NASA AA No A
Table
I-3
2. Safety and Mission Assurance Plan [Baseline at SDR]
[Required per NPRs 8705.2 and 8705.4]
OSMA Yes A
Table
I-3
3. Risk Management Plan [Baseline at SDR]
[Required NPR 8000.4]
OSMA Yes A
Table
I-3
4. Acquisition Strategy [Baseline at SDR] [Required per
NPD 1000.5]
NASA AA No A
Table
I-3
6. Systems Engineering Management Plan
[Baseline at SDR] [Required per NPR 7123.1]
OCE Yes A
Table
I-3
7. Verification and Validation Plan [Baseline at PDR]
[Required per NPR 7120.5, additional information in NPR
7123.1]
OCE Yes A
Table
I-3
8. System Security Plan [Baseline at CDR]
[Required per NPR 2810.1]
OCIO No A
Table
I-3
9. Review Plan [Baseline at SRR] [Required per NPR 7120.5] NASA AA No A
Table
I-3
10. Mission Operations Plan [Baseline at ORR] [Required per
NPR 7120.5]
OCE Yes A
Table
I-3
11. NEPA Compliance Plan [Baseline at PDR] [Required per
NPR 8580.1]
OSI-EMD No A
Table
I-3
12. Integrated Logistics Support Plan [Baseline at PDR]
[Required per NPD 7500.1]
OSI-LMD No A
Table
I-3
14. Configuration Management Plan [Baseline at SDR]
[Required per NPR 7120.5; additional information in NPR
7123.1 and SAE/EIA 649]
OCE Yes A
Table
I-3
15. Security Plan [Baseline at PDR]
[Required per NPR 1040.1 and NPR 1600.1]
OPS No A
Table
I-3
16. Technology Transfer (formerly Export) Control Plan
[Baseline at PDR] [Required per NPR 2190.1]
OIIR No A
Table
I-3
19. Human-Rating Certification Package [Initial at SRR;
certified at MRR/FRR] [Required per NPR 8705.2]
OSMA No A
Table
I-3
20. Quality Assurance Surveillance Plan [Baseline at SDR]
[Required per NPR 8735.2 and NASA FAR Supplement part
1837.604]
OSMA Yes A
Table
I-3
21. Orbital Collision Avoidance Plan [Baseline at PDR]
[Required per NPR 8079.1]
OCE No A
Table
I-3
22. Human Systems Integration Approach [Baseline at SRR]
[additional information in NASA/SP-20210010952 NASA
HSI Handbook and NPR 7123.1]
OCE-OSMA-OCHMO1 No A
Table I-4 Project Milestone Products
Maturity Matrix
Headquarters and Program Products
Table
I-4
1. FAD [Baseline at MCR] [Required per NPR 7120.5] NASA AA No A A
Table
I-4
2. Program Plan [Baseline at MCR] [Required per NPR
7120.5]
NASA AA No A A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 77 of 147
NPR 7120.5F -- AppendixC Page 77 of 147
Table
I-4
2.a. Applicable Agency strategic goals [Baseline at MCR]
[Required per NPR 7123.1]
NASA AA No A A
Table
I-4
2.b. Documentation of program-level requirements and
constraints on the project (from the Program Plan) and
stakeholder expectations, including mission objectives/goals
and mission success criteria
[Baseline at SRR] [Required per NPR 7123.1]
OCE Yes A A
Table
I-4
2.c. Documentation of driving mission, technical, and
programmatic ground rules and assumptions
[Baseline at SDR/MDR] [Required per NPR 7120.5]
NASA AA No A A
Table
I-4
3. Partnerships and interagency and international agreements
[Baseline U.S. partnerships and agreements at SDR/MDR;
Baseline International agreements at PDR]
NASA AA No A A
Table
I-4
4. ASM Decision Memorandum [additional information in
NPD 1000.5]
NASA AA No A A
Table
I-4
5. Mishap Preparedness and Contingency Plan [Baseline at
SMSR] [Required per NPR 8621.1]
OSMA Yes A A
Project Technical Products
Table
I-4
1. Concept Documentation [Approve at MCR] [Required per
NPR 7123.1]
OCE Yes A
Table
I-4
2. Mission, Spacecraft, Ground, and Payload Architectures
[Baseline mission and spacecraft architecture at SRR;
Baseline ground and payload architectures at SDR/MDR]
[Required per NPR 7123.1]
OCE Yes A
Table
I-4
3. Project-Level, System, and Subsystem Requirements
[Baseline project-level and system-level requirements at
SRR; Baseline subsystem requirements at PDR] [Required
per NPR 7123.1]
OCE Yes A
Table
I-4
4. Design Documentation [Baseline at CDR] [Required per
NPR 7123.1]
OCE Yes A
Table
I-4
5. Operations Concept Documentation [Baseline at PDR]
[Required per NPR 7120.5]
OCE Yes A
Table
I-4
6. Technology Readiness Assessment Documentation
[Required per NPR 7120.5 Appendix F FA Template]
OCE Yes A
Table
I-4
7. Engineering Development Assessment Documentation
[Required per NPR 7120.5 Appendix F FA Template]
OCE Yes A
Table
I-4
8. Heritage Assessment Documentation [Required per NPR
7120.5 Appendix F FA Template]
OCE Yes A
Table
I-4
9. Systems Safety Analyses (e.g., safety data packages)
[Baseline at CDR] [Required per NPR 8715.3]
OSMA Yes A
Table
I-4
10. Payload Safety Process Deliverables [Baseline at SIR]
[Required per NPR 8715.7]
OSMA Yes A
Table
I-4
11. Verification and Validation Report
[Baseline at MRR/FRR] [Required per NPR 7123.1]
OCE Yes A
Table
I-4
12. Operations Handbook [Baseline at ORR] [additional
information in NPR 7120.5 Appendix A]
OCE Yes A
Table
I-4
13. Orbital Debris Assessment Report [Final at SMSR]
[Required per NPR 8715.6; additional information in
NASA-STD-8719.14]
OSMA No A A
Table
I-4
14. End of Mission Plans [Baseline at SMSR] [Required per
NPR 8715.6; additional information in NASA-STD-8719.14,
App B]
OSMA Yes A A
Table
I-4
16. Decommissioning/Disposal Plan [Baseline at ORR]
[Required per NPR 7123.1]
OCE Yes A
Table
I-4
17. Industrial Base and Supply Chain Risk Management
(SCRM) Strategy and Status [Baseline at PDR] [Required
per NPR 8735.2]
OSMA No A
Table
I-4
18. Criticality Identification Method for Hardware [Baseline
at PDR] [Required per NPR 8735.2]
OSMA No A
Project Management, Planning, and Control Products
Table
I-4
1. Formulation Agreement [Baseline for Phase A at MCR;
Baseline for Phase B at SDR/MDR] [Required per NPR
7120.5]
NASA AA No A A A
Table
I-4
2. Project Plan [Baseline at PDR] [Required per NPR 7120.5] NASA AA No A A A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 78 of 147
NPR 7120.5F -- AppendixC Page 78 of 147
Table
I-4
3. Documentation of performance against Formulation
Agreement (see #1 above) or against plans for work to be
accomplished during Implementation life-cycle phase,
including performance against baselines and status/closure of
formal actions from previous KDP [Required per NPR 7120.5]
NASA AA No A
Table
I-4
4. Project Baselines N/A N/A
Table
I-4
4.a. Top technical, cost, schedule and safety risks, risk
mitigation plans, and associated resources [Required per
NPR 7120.5]
NASA AA No A
Table
I-4
4.b. Staffing requirements and plans [Required per NPR
7120.5]
NASA AA No A
Table
I-4
4c.i. Infrastructure requirements and plans [Required per
NPR 9250.1, NPD 8800.14, and NPR 8820.2]
Business case analysis for infrastructure [Required per NPR
8800.15.]
OSI-FRED No A
Table
I-4
4.c.ii. Capitalization Determination Form (CDF) (NASA
Form 1739) [Required per NPR 9250.1]
OCFO No A
Table
I-4
4.d. Schedule [Baseline Integrated Master Schedule at PDR]
[Required per NPR 7120.5]
OCFO-SID No A
Table
I-4
4.e. Cost Estimate [Baseline at PDR] [Required per NPR
7120.5]
OCFO-SID No A
Table
I-4
4.f. Basis of Estimate (cost and schedule) [Required per NPR
7120.5]
OCFO-SID No A
Table
I-4
4.g. Confidence Level(s) and supporting documentation
[Baseline at PDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-4
4.h. External Cost and Schedule Commitments
[Baseline at PDR] [Required per NPR 7120.5]
OCFO-SID No A A
Table
I-4
4.i. CADRe [Baseline at SRR] [Required per NPR 7120.5] OCFO-SID No A
Table
I-4
4.j. PMB [Baseline at PDR] [Required per NPR 7120.5 and
NASA EVM Capability Process Documentation]
OCFO-SID No A
Table I-5 Project Plan Control Plans Maturity
Matrix
Table
I-5
1. Technical, Schedule, and Cost Control Plan
[Baseline at SDR/MDR] [Required per NPR 7120.5]
NASA AA No A
Table
I-5
2. Safety and Mission Assurance Plan [Baseline at SRR]
[Required per NPRs 8705.2 and 8705.4]
OSMA Yes A
Table
I-5
3. Risk Management Plan [Baseline at SRR]
[Required per NPR 8000.4]
OSMA Yes A
Table
I-5
4. Acquisition Strategy [Baseline at SRR] [Required per NPD
1000.5]
NASA AA No A
Table
I-5
6. Systems Engineering Management Plan [Baseline at SRR]
[Required per NPR 7123.1]
OCE Yes A
Table
I-5
7. System Security Plan [Baseline at CDR] [Required per
NPR 2810.1]
OCIO No A
Table
I-5
8. Software Management Plan(s) [Baseline at SDR/MDR]
[Required per NPR 7150.2; additional information in
NASA-STD-8739.8]
OCE No A
Table
I-5
9. Verification and Validation Plan [Baseline at PDR]
[Required per NPR 7120.5, additional information in NPR
7123.1]
OCE Yes A
Table
I-5
10. Review Plan [Baseline at SRR] [Required per NPR
7120.5]
NASA AA No A
Table
I-5
11. Mission Operations Plan [Baseline at ORR] [Required per
NPR 7120.5]
OCE Yes A
Table
I-5
12. NEPA Compliance Plan [Baseline at SDR/MDR]
[Required per NPR 8580.1]
OSI-EMD No A
Table
I-5
13. Integrated Logistics Support Plan [Baseline at PDR]
[Required per NPD 7500.1]
OSI-LMD No A
Table
I-5
15. Integration Plan [Baseline at PDR] [Required per NPR
7120.5]
OCE Yes A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 79 of 147
NPR 7120.5F -- AppendixC Page 79 of 147
Table
I-5
16. Configuration Management Plan [Baseline at SRR]
[Required per NPR 7120.5; additional information in NPR
7123.1 and SAE/EIA 649]
OCE Yes A
Table
I-5
17. Security Plan [Baseline at PDR]
[Required per NPR 1040.1 and NPR 1600.1]
OPS No A
Table
I-5
18. Project Protection Plan [Baseline at PDR] [Required per
NPR 1058.1; additional information in NASA-STD-1006]
OCE No A
Table
I-5
19. Technology Transfer (formerly Export) Control Plan
[Baseline at PDR] [Required per NPR 2190.1]
OIIR No A
Table
I-5
21. Human-Rating Certification Package [Initial at SRR;
certified at MRR/FRR] [Required per NPR 8705.2]
OSMA No A
Table
I-5
22. Planetary Protection Plan [Baseline at PDR]
[Required per NPD 8020.7 and NPR 8715.24]
OSMA No A
Table
I-5
23. Nuclear Launch Authorization Plan [Baseline at
SDR/MDR] [additional information in NPR 8715.26]
OSMA No A
Table
I-5
24. Range Safety Risk Management Process Documentation
[Baseline at SIR] [Required per NPR 8715.5]
OSMA Yes A
Table
I-5
26. Quality Assurance Surveillance Plan [Baseline at SDR]
[Required per NPR 8735.2 and NASA FAR Supplement part
1837.604]
OSMA Yes A
Table
I-5
27. Orbital Collision Avoidance Plan [Baseline at PDR]
[Required per NPR 8079.1]
OCE No A
Table
I-5
28. Human Systems Integration Approach [Baseline at SRR]
[additional information in NASA/SP-20210010952 NASA
HSI Handbook and NPR 7123.1]
OCE-OSMA-OCHMO1 No A
Table I-6 Single-Project Program Milestone
Products Maturity Matrix
Table
I-6
1. FAD [Baseline at MCR] [Required per NPR 7120.5] NASA AA No A A
Table
I-6
2. PCA [Baseline at PDR] [Required per NPR 7120.5] NASA AA No A
Table
I-6
3. Traceability of Agency strategic goals and Mission
Directorate requirements and constraints to
program/project-level requirements and constraints
[Baseline at SRR] [Required per NPR 7123.1]
OCE Yes A A
Table
I-6
4. Documentation of driving mission, technical, and
programmatic ground rules and assumptions [Baseline at
SDR/MDR] [Required per NPR 7120.5]
NASA AA No A A
Table
I-6
5. Partnerships and inter-agency and international agreements
[Baseline U.S. partnerships and agreements at SDR/MDR;
Baseline international agreements at PDR]
NASA AA No A A
Table
I-6
6. ASM Decision Memorandum [additional information in
NPD 1000.5]
NASA AA No A A
Table
I-6
7. Mishap Preparedness and Contingency Plan [Baseline at
SMSR] [Required per NPR 8621.1]
OSMA Yes A A
Single-Project Program Technical Products
Table
I-6
1. Concept Documentation [Required per NPR 7123.1] OCE Yes A
Table
I-6
2. Mission, Spacecraft, Ground, and Payload Architectures
[Baseline mission and spacecraft architecture at SRR;
baseline ground and payload architectures at SDR/MDR]
[Required per NPR 7123.1]
OCE Yes/td> A
Table
I-6
3. Project-Level, System, and Subsystem Requirements
[Baseline project-level and system-level requirements at
SRR; baseline subsystem requirements at PDR] [Required
per NPR 7123.1]
OCE No A
Table
I-6
4. Design Documentation [Baseline at CDR] [Required per
NPR 7123.1]
OCE No A
Table
I-6
5. Operations Concept Documentation [Baseline at PDR]
[Required per NPR 7120.5]
OCE Yes A
Table
I-6
6. Technology Readiness Assessment Documentation
[Required per NPR 7120.5 Appendix F FA Template]
OCE Yes A
Table
I-6
7. Engineering Development Assessment Documentation
[Required per NPR 7120.5 Appendix F FA Template]
OCE Yes A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 80 of 147
NPR 7120.5F -- AppendixC Page 80 of 147
Table
I-6
8. Heritage Assessment Documentation [Required per NPR
7120.5 Appendix F FA Template]
OCE Yes A
Table
I-6
9. Systems Safety Analyses (e.g., safety data packages)
[Baseline at CDR]
[Required per NPR 8715.3]
OSMA Yes A
Table
I-6
10. Payload Safety Process Deliverables [Baseline at SIR]
[Required per NPR 8715.7]
OSMA Yes A
Table
I-6
11. Verification and Validation Report [Baseline at
MRR/FRR] [Required per NPR 7123.1]
OCE Yes A
Table
I-6
12. Operations Handbook [Baseline at ORR] [additional
information in NPR 7120.5 Appendix A]
OCE Yes A
Table
I-6
13. Orbital Debris Assessment Report [Final at SMSR]
[Required per NPR 8715.6; additional information in
NASA-STD-8719.14]
OSMA No A A
Table
I-6
14. End of Mission Plans [Baseline at SMSR] [Required per
NPR 8715.6; additional information in NASA-STD-8719.14,
App B]
OSMA Yes A A
Table
I-6
16. Decommissioning/Disposal Plan [Baseline at ORR]
[Required per NPR 7123.1]
OCE Yes A
Table
I-6
17. Industrial Base and Supply Chain Risk Management
(SCRM) Strategy and Status [Baseline at PDR] [Required
per NPR 8735.2]
OSMA No A
Table
I-6
18. Criticality Identification Method for Hardware [Baseline
at PDR] [Required per NPR 8735.2]
OSMA No A
Single-Project Program Management, Planning, and Control
Products
Table
I-6
1. Formulation Agreement [Baseline for Phase A at MCR;
baseline for Phase B at SDR/MDR] [Required per NPR
7120.5]
NASA AA No A A A
Table
I-6
2. Program Plan [Baseline at PDR] [Required per NPR
7120.5]
NASA AA No A A A
Table
I-6
3. Project Plan [Baseline at PDR] [Required per NPR 7120.5] NASA AA No A A A
Table
I-6
4. Documentation of performance against Formulation
Agreement (see #1 above) or against plans for work to be
accomplished during Implementation life-cycle phase,
including performance against baselines and status/closure of
formal actions from previous KDP [Required per NPR 7120.5]
NASA AA No A
Table
I-6
5. Project Baselines N/A N/A
Table
I-6
5.a. Top technical, cost, schedule and safety risks, risk
mitigation plans, and associated resources [Required per
NPR 7120.5]
NASA AA No A
Table
I-6
5.b. Staffing requirements and plans [Required per NPR
7120.5]
NASA AA No A
Table
I-6
5.c.i. Infrastructure requirements and plans [Required per
NPR 9250.1, NPD 8800.14, and NPR 8820.2]
Business case analysis for infrastructure [Required per NPR
8800.15.]
OSI-FRED No A
Table
I-6
5.c.ii. Capitalization Determination Form (CDF) (NASA
Form 1739) [Required per NPR 9250.1]
OCFO No A
Table
I-6
5.d. Schedule [Baseline Integrated Master Schedule at PDR]
[Required per NPR 7120.5]
OCFO-SID No A
Table
I-6
5.e. Cost Estimate (Risk-Informed or Schedule-Adjusted
Depending on Phase) [Risk-informed and schedule-adjusted
baseline at PDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-6
5.f. Basis of Estimate (cost and schedule) [Required per NPR
7120.5]
OCFO-SID No A
Table
I-6
5.g. Confidence Level(s) and supporting documentation
[Baseline at PDR] [Required per NPR 7120.5]
OCFO-SID No A
Table
I-6
5.h. External Cost and Schedule Commitments [Baseline at
PDR] [Required per NPR 7120.5]
OCFO-SID No A A
Table
I-6
5.i. CADRe [Baseline at SRR] [Required per NPR 7120.5] OCFO-SID No A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 81 of 147
NPR 7120.5F -- AppendixC Page 81 of 147
Table
I-6
5.j. PMB [Baseline at PDR] [Required per NPR 7120.5 and
NASA EVM Capability Process Documentation]
OCFO-SID No A
Table I-7 Single-Project Program Plan Control Plans
Maturity Matrix
Table
I-7
1. Technical, Schedule, and Cost Control Plan [Baseline at
SDR/MDR] [Required per NPR 7120.5]
NASA AA No A
Table
I-7
2. Safety and Mission Assurance Plan [Baseline at SRR]
[Required per NPRs 8705.2 and 8705.4]
OSMA Yes A
Table
I-7
3. Risk Management Plan [Baseline at SRR] [Required per
NPR 8000.4]
OSMA Yes A
Table
I-7
4. Acquisition Strategy [Baseline at SRR] [Required per NPD
1000.5]
NASA AA No A
Table
I-7
6. Systems Engineering Management Plan [Baseline at SRR]
[per NPR 7123.1]
OCE Yes A
Table
I-7
7. System Security Plan [Baseline at CDR] [Required per
NPR 2810.1]
OCIO No A
Table
I-7
8. Software Management Plan(s) [Baseline at SDR/MDR]
[Required per NPR 7150.2; additional information in
NASA-STD-8739.8]
OCE No A
Table
I-7
9. Verification and Validation Plan [Baseline at PDR]
[Required per NPR 7120.5, additional information in NPR
7123.1
OCE Yes A
Table
I-7
10. Review Plan [Baseline at SRR] [Required per NPR
7120.5]
NASA AA No A
Table
I-7
11. Mission Operations Plan [Baseline at ORR] [Required per
NPR 7120.5]
OCE Yes A
Table
I-7
12. NEPA Compliance Plan [Baseline at SDR/MDR]
[Required per NPR 8580.1]
OSI-EMD No A
Table
I-7
13. Integrated Logistics Support Plan [Baseline at PDR]
[Required per NPD 7500.1]
OSI-LMD No A
Table
I-7
15. Integration Plan [Baseline at PDR] [Required per NPR
7120.5]
OCE Yes A
Table
I-7
16. Configuration Management Plan [Baseline at SRR]
[Required per NPR 7120.5; additional information in NPR
7123.1 and SAE/EIA 649]
OCE Yes A
Table
I-7
17. Security Plan [Baseline at PDR] [Required per NPR
1040.1 and NPR 1600.1]
OPS No A
Table
I-7
18. Project Protection Plan [Baseline at PDR] [Required per
NPR 1058.1; additional information in NASA-STD-1006]
OCE No A
Table
I-7
19. Technology Transfer (formerly Export) Control Plan
[Baseline at PDR] [Required per NPR 2190.1]
OIIR No A
Table
I-7
21. Human-Rating Certification Package [Initial at SRR;
certified at MRR/FRR] [Required per NPR 8705.2]
OSMA No A
Table
I-7
22. Planetary Protection Plan [Baseline at PDR] [Required
per NPD 8020.7 and NPR 8715.24]
OSMA No A
Table
I-7
23. Nuclear Launch Authorization Plan [Baseline at
SDR/MDR] [additional information in NPR 8715.26]
OSMA No A
Table
I-7
24. Range Safety Risk Management Process Documentation
[Baseline at SIR] [Required per NPR 8715.5]
OSMA Yes A
Table
I-7
26. Quality Assurance Surveillance Plan [Baseline at SDR]
[Required per NPR 8735.2 and NASA FAR Supplement part
1837.604]
OSMA Yes A
Table
I-7
27. Orbital Collision Avoidance Plan [Baseline at PDR]
[Required per NPR 8079.1]
OCE No A
Table
I-7
28. Human Systems Integration Approach [Baseline at SRR]
[additional information in NASA/SP-20210010952 NASA
HSI Handbook and NPR 7123.1]
OCE-OSMA-OCHMO1 No A
2.2.8 Projects, single-project programs (and other programs at the
discretion of the MDAA) with a life-cycle cost (LCC) or
initial capability cost (see Section 2.4.1.3.b) estimated to be
greater than $250M shall perform earned value management
(EVM) and comply with EIA-748, Earned Value
Management Systems for all portions of work including
in-house and contracted portions of the project.
OCFO-SID No A A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 82 of 147
NPR 7120.5F -- AppendixC Page 82 of 147
2.2.8.1 Program and project managers with programs and projects
subject to EVM shall utilize the NASA EVM Capability
Process for in-house work.
OCFO-SID No A
2.2.8.2 EVM system requirements for contracted work shall be
applied to suppliers in accordance with the NASA Federal
Acquisition Regulation (FAR) Supplement, independent of
phase and the $250M threshold
(https://www.hq.nasa.gov/office/procurement/regs/NFS.pdf.).
OCFO-SID No A A
2.2.8.3 Mission Directorates shall conduct an IBR in preparation for
KDP C and for major changes that significantly impact the
cost and schedule baseline.
OCFO-SID No A A
2.2.8.4 EVMS surveillance shall be conducted on contracts and
programs and projects with in-house work to ensure
continued compliance with EIA-748, Earned Value
Management Systems.
OCFO-SID No A A
2.2.10 Program and project managers shall complete and maintain a
Compliance Matrix (see Appendix C) for this NPR and attach
it to the Formulation Agreement for projects in Formulation
and/or the Program or Project Plan.
OCE No A
2.2.11 Single-project programs and projects shall develop a Project
Protection Plan that addresses NASA-STD-1006, Space
System Protection Standard in accordance with NPR 1058.1,
Enterprise Protection Program.
OCE No A
2.3.1 Each program and project shall have a Decision Authority the
Agency’s responsible individual who determines whether and
how the program or project proceeds through the life cycle
and the key program or project cost, schedule, and content
parameters that govern the remaining life-cycle activities.
NASA AA No A
2.3.1.1 The MDAA shall inform the NASA AA and Administrator
via email on all Agency Baseline Commitments (ABCs) per
the following: inform the NASA AA on ABCs for
single-project programs and projects with a LCC or initial
capability cost (see Section 2.4.1.3.b) greater than $250M;
and inform the NASA Administrator on ABCs for all
single-project programs and projects with a LCC or initial
capability cost greater than $1B and all Category 1 projects.
(See Section 2.4.1.5 for more information on ABCs.)
NASA AA No A
2.3.2 Each program and project shall have a governing PMC. NASA AA No A
2.3.4 The Center Director (or designee) shall oversee programs and
projects usually through the CMC, which monitors and
evaluates all program and project work (regardless of
category) executed at that Center.
NASA AA No A
2.3.5 Following each LCR, the independent SRB chair and the
program or project manager shall brief the applicable
management councils on the results of the LCR to support the
councils’ assessments.
NASA
AA
No A A A
2.4.1 The decisions by the Decision Authority on whether and how
the program or project proceeds into the next phase shall be
summarized and recorded in the Decision Memorandum
signed at the conclusion of the governing PMC by all parties
with supporting responsibilities, accepting their respective
roles.
NASA AA No A
2.4.1.1 The Decision Memorandum shall describe the constraints and
parameters within which the Agency, the program manager,
and the project manager will operate; the extent to which
changes in plans may be made without additional approval;
any additional actions that came out of the KDP; and the
supporting data (i.e., the cost and schedule datasheet) that
provide further details.
NASA AA No A A
2.4.1.2 A divergence from the Management Agreement that any party
identifies as significant shall be accompanied by an
amendment to the Decision Memorandum.
NASA AA No A A
2.4.1.3 During Formulation, the Decision Memorandum shall
establish a target LCC or initial capability cost range (and
schedule range, if applicable) as well as the Management
Agreement addressing the schedule and resources required to
complete Formulation.
OCFO-SID No A A
2.4.1.3 a For single-project programs and projects with a LCC or initial
capability cost greater than or equal to $1B, the Decision
Memorandum shall establish a high and low value for cost
and schedule with the corresponding JCL value at KDP B.
OCFO-
SID
No A A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 83 of 147
NPR 7120.5F -- AppendixC Page 83 of 147
2.4.1.5 All single-project program managers and project managers
shall document the Agency’s LCC estimate or initial
capability cost estimate and other parameters in the Decision
Memorandum for Implementation (KDP C), and this
becomes the ABC.
NASA AA No A A
2.4.1.5.a For all single-project programs and projects with a definite
Phase E end point, the Agency’s LCC estimate and other
parameters shall become the ABC.
NASA AA No A A
2.4.1.5.b For single-project programs and projects that plan continuing
operations and production, including integration of capability
upgrades, with an unspecified Phase E end point, the initial
capability cost estimate and other parameters shall become
the ABC.
NASA AA No A A
2.4.1.7 Tightly coupled programs shall document their LCC estimate
in accordance with the scope defined in the FAD or PCA, and
other parameters in their Decision Memorandum at KDP I
and update it at subsequent KDPs.
OCFO-SID No A A
2.4.1.8 Programs or projects shall be rebaselined when: (1) the
estimated development cost exceeds the ABC development
cost by 30 percent or more (for projects over $250M, also
that Congress has reauthorized the project); (2) the NASA
AA judges that events external to the Agency make a
rebaseline appropriate; or (3) the NASA AA judges that the
program or project scope defined in the ABC has been
changed or the project has been interrupted.
OCFO-SID No A A
2.4.2 The program or project shall document the basis of estimate
(BOE) for cost estimates and planned schedules in retrievable
program or project records.
OCFO-SID No A
2.4.3.1
a.
Single-project programs with an estimated LCC under $1B
and projects with an estimated LCC greater than $250M and
under $1B shall provide a range of cost and a range for
schedule, each range (with confidence levels identified for
the low and high values of the range) established by a
probabilistic analysis and based on identified resources and
associated uncertainties by fiscal year.
OCFO-SID No A
2.4.3.1
b.
Single-project programs and projects with an estimated LCC
greater than or equal to $1B shall develop a JCL and provide
a high and low value for cost and schedule with the
corresponding JCL value (e.g., 50 percent, 70 percent).
OCFO-SID No A
2.4.3.2 At KDP C, single-project programs (regardless of LCC) and
projects with an estimated LCC greater than $250M shall
develop a cost-loaded schedule and perform a risk-informed
probabilistic analysis that produces a JCL.
OCFO-SID No A
2.4.3.3 At CDR, single-project programs and projects with an
estimated LCC greater than or equal to $1B shall update their
KDP C JCL and communicate the updated JCL values for the
ABC and Management Agreement to the APMC for
informational purposes.
OCFO-SID No A
2.4.3.4 At KDP D, single-project programs and projects with an
estimated LCC greater than or equal to $1B shall update their
JCL if current reported development costs have exceeded the
development ABC cost by 5 percent or more and document
the updated JCL values for the ABC and Management
Agreement in the KDP D Decision Memorandum.
OCFO-SID No A
2.4.3.5 When a single-project program (regardless of LCC) or project
with an estimated LCC greater than $250M is rebaselined, a
JCL shall be calculated and evaluated as a part of the
rebaselining approval process.
OCFO-SID No A A
2.4.4.1 At KDP B, Mission Directorates shall plan and budget
single-project programs and projects with an estimated LCC
greater than or equal to $1B based on a 70 percent JCL or as
approved by the Decision Authority.
OCFO-SID No A
2.4.4.2 At KDP C, Mission Directorates shall plan and budget
single-project programs (regardless of LCC) and projects
with an estimated LCC greater than $250M based on a 70
percent JCL or as approved by the Decision Authority.
OCFO-SID No A
2.4.4.3 At KDP B and KDP C, any JCL approved by the Decision
Authority at less than 70 percent shall be justified and
documented in a Decision Memorandum.
OCFO-SID No A
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 84 of 147
NPR 7120.5F -- AppendixC Page 84 of 147
2.4.4.4 At KDP C, Mission Directorates shall ensure funding for
single-project programs (regardless of LCC) and projects
with an estimated LCC greater than $250M is consistent with
the Management Agreement and in no case less than the
equivalent of a 50 percent JCL or as approved by the
Decision Authority.
OCFO-SID No A
2.4.4.5 At KDP C, any funding approved by the Decision Authority
that is inconsistent with the Management Agreement or less
than 50 percent JCL shall be justified and documented in a
Decision Memorandum.
OCFO-SID No A
2.4.5 Tightly coupled, loosely coupled, and uncoupled programs
shall provide analysis of the program’s risk posture to the
governing PMC as each new project reaches KDP B and C or
when a project’s ABC is rebaselined.
OCFO-SID No A A
3.3.1 Programs and projects shall follow the Technical Authority
(TA) process established in this Section 3.3.
OCE No A A A
3.4.1 Programs and projects shall follow the Formal Dissent
process in this Section 3.4.
NASA AA No A A A
3.5.1 Programs and projects shall follow the tailoring process in
this Section 3.5.
NASA AA No A A A
3.5.5 A request for a permanent change to a prescribed
requirement in an Agency or Center document that is
applicable to all programs and projects shall be submitted as
a “change request” to the office responsible for the
requirement policy document unless formally delegated
elsewhere.
NASA AA No A A A
3.6.1 Center Directors negotiating reimbursable space flight work
with another agency shall propose NPR 7120.5 as the basis
by which it will perform the space flight work.
NASA AA No A
3.7.1 Each program and project shall perform and document an
assessment to determine an approach that maximizes the use
of SI.
OCE No A
1 The Human Systems Integration approach requirement is owned by the three TA offices OCHMO, OCE and OSMA. OCE is the POC for this requirement and will
coordinate verifications and relief from requirements with all TAs as necessary.
NPR 7120.5F -- AppendixC
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 85 of 147
NPR 7120.5F -- AppendixC Page 85 of 147
Appendix D. Program Commitment
Agreement Template
D.1 PCA Title Page
Figure D-1 Program Commitment Agreement Title Page
D.2 PCA Template
PROGRAM COMMITMENT AGREEMENT
(PROGRAM TITLE)
1.0 PROGRAM OBJECTIVES
Identify the broad program objectives. Describe the program's relationship to Mission Directorate
goals and objectives as documented in the Directorate's plan. Convey the public good of the program
to the taxpayer, stated in a way that can be understood by the average citizen.
2.0 PROGRAM OVERVIEW
NPR 7120.5F -- AppendixD
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 86 of 147
NPR 7120.5F -- AppendixD Page 86 of 147
Describe the strategy to achieve the above-mentioned objectives. Relationships with external
organizations, other agencies, or international partners should be addressed if achievement of the
program objectives is dependent on their performance. Identify the associated projects to be included
in the program as of the writing date. Specify the type of program (i.e., single-project, uncoupled,
loosely coupled, or tightly coupled) and the basis for that classification.
Specify if there are plans for continuing operations and production, including integration of
capability upgrades, with an unspecified Phase E end point, for:
• Each project
• Single-project programs
For such programs and projects, define the scope of the initial capability.
3.0 PROGRAM AUTHORITY
Describe the NASA organizational structure for managing the program and projects from the
MDAA to the NASA Center project managers. Include lines of authority and reporting, and
Center(s) responsibilities. Specifically identify the Decision Authority and governing Program
Management Council (PMC) for oversight of the program, and any delegated Decision Authority
and delegated governing PMC, per Section 2.3 of this NPR.
Document each project's Decision Authority and governing PMC or identify where this information
is documented.
Identify the approving official for new projects.
4.0 TECHNICAL PERFORMANCE COMMITMENT
Summarize the technical performance requirements, identifying baselines and thresholds needed to
achieve the program objectives, as applicable. If the objectives include a technical performance
target (goal) in addition to a threshold requirement, the commitment could be stated as a range.
Demonstrate traceability to Agency strategic goals, outcomes, and requirements.
5.0 SCHEDULE COMMITMENT
Identify the following key target milestones for each project in the program, such as:
1. Start of Formulation.
2. Target date or timeframe for the SDR or MDR.
3. Target date or timeframe for the PDR or the start of implementation.
4. Start of initial capability operations (for single-project programs and projects that plan continuing
operations and production, including integration of capability upgrades, with an unspecified Phase E
end point).
5. Start of operations.
6. End of prime operations and/or disposal, if applicable, or end of initial capability operations.
7. Other milestones or time periods, as appropriate, for a specific program/project.
NPR 7120.5F -- AppendixD
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 87 of 147
NPR 7120.5F -- AppendixD Page 87 of 147
6.0 COST COMMITMENT
Provide the estimated cost range for the program for the ten-year period beginning in the current
fiscal year at a level of detail that identifies the approved individual projects. Identify the constraints
and assumptions used to develop this estimated cost range and specifically identify those
assumptions that drive the range. This cost range should contain all costs necessary to perform the
program, including, but not limited to, customary project activities, required technology
developments, facilities costs, launch vehicles, tracking, operations and sustainment, data analysis,
and disposal. Either reference the most recent Agency budget to provide the first five years of the
estimated program cost or provide the budget required for the next five years. The cost range should
be updated when program content changes, such as the addition of new projects entering
Implementation or when the estimated cost changes. Reference the annual budget contained in the
Integrated Budget and Performance Document (IBPD) for cost phasing.
7.0 ACQUISITION STRATEGY
Provide a high-level summary of the Acquisition Strategy (described in Appendix G, Section 3.4) to
reflect the results of the process for acquisition and the Acquisition Strategy Meeting (ASM).
8.0 HIGH-RISK AREAS
Identify the areas of highest risk for the program (covering safety, technical, institutional, cost, and
schedule issues) in which failure may result in changes to the program/project baseline cost,
schedule, safety, or technical performance requirements. This section should identify, where
possible, the specific risk drivers, such as high-risk technologies upon which the program is
dependent, and mitigation options.
9.0 INTERNAL AGREEMENTS
If the program is dependent on other NASA activities outside of the MDAA's control to meet
program objectives, identify the required support and list any formal agreements required.
10.0 EXTERNAL AGREEMENTS
Explain the involvement of external organizations, other agencies, or international support necessary
to meet the program objectives. Include a brief overview of the program/project relationships with
such external organizations. Include an identification of the commitments being made by the
external organizations, other agencies, or international partners and a listing of the specific
agreements to be concluded. Any unique considerations affecting implementation of required NASA
policies and processes necessitated by the external involvement should be clearly identified, such as
commercial or other partners that will develop end products that are not owned by NASA but are
provided as services to NASA.
11.0 REVIEWS
Specify the program and project life-cycle reviews (per figures 2-2, 2-3, 2-4, and 2-5 in Chapter 2)
that are required to be conducted during the Implementation Phase. Include any other requirements
(e.g., the ASM) and any known unique considerations (e.g., acquisition strategies such as
commercial partnerships, international participation). Identify any planned tailoring to accommodate
aspects of the acquisition strategies (See Section 2.2.4.1) and when the tailoring approach will be
defined. Specify the considerations that will be used to trigger a discussion on the need for a PIR
with the NASA AA (See Section 2.2.4.2 and the NASA Space Flight Program and Project
Management Handbook, Section 5.11.3.)
NPR 7120.5F -- AppendixD
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 88 of 147
NPR 7120.5F -- AppendixD Page 88 of 147
Management Handbook, Section 5.11.3.)
12.0 OUTCOMES
Identify the discrete set of expected deliverables (outcomes) that flow from the Agency goals and
objectives, as defined in the Agency Strategic Plan.
13.0 WAIVERS AND DEVIATIONS
Identify known waivers or deviations that will be sought for the program. Provide a rationale
consistent with program characteristics such as scope, complexity, visibility, cost, safety, and
acceptable risk.
14.0 PCA ACTIVITIES LOG
Provide and maintain a log of all PCA activities, including revisions that reflect all waivers to the
original PCA. This log includes the information shown in Table D-1 and may be supplemented with
an attached addendum for each change, describing the change. The PCA should be updated to add
approved projects or whenever substantial change makes it necessary. The PCA should be
revalidated or updated at each KDP.
Table D-1 Sample Program Commitment Agreement Activities Log
Termination MDAA
Associate
Administrator
Date Event Change Addendum
Review
Req'd
Signature Signature
dd/mm/yy Revalidation None N/A No
dd/mm/yy Revalidation None N/A No
dd/mm/yy
Approval of
new project
Addition
of Project
N
Ref. #1 No
NPR 7120.5F -- AppendixD
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 89 of 147
NPR 7120.5F -- AppendixD Page 89 of 147
Appendix E. Formulation Authorization
Document Template
E.1 Program FAD Title Page
Figure E-1 Program Formulation Authorization Document Title Page
E.2 Project FAD Title Page
NPR 7120.5F -- AppendixE
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 90 of 147
NPR 7120.5F -- AppendixE Page 90 of 147
Figure E-2 Project Formulation Authorization Document Title Page
E.3 Program/Project FAD Template
[Program/Project Name] Formulation Authorization Document
[short title or acronym]
1.0 PURPOSE
Describe the purpose of the program/project, including a clear traceability from the goals and
objectives in the Mission Directorate Strategies or Program Plan, as applicable. This need is
independent of any particular technological solution and is stated in terms of functional capabilities.
2.0 AUTHORITY
Describe the NASA organizational structure for managing the Formulation process from the
Mission Directorate Associate Administrator (MDAA) to the NASA Center program/project
managers, as applicable. Include lines of authority, coordination, and reporting. For projects and
single-project programs, the Formulation Authorization Agreement (FAD) provides the basis for the
project's Formulation Agreement. Specifically identify the Decision Authority and the governing
Program Management Council (PMC) for oversight of the program/project, per Section 2.3 of this
NPR.
3.0 PROGRAM TYPE/PROJECT CATEGORY
For programs, identify the program type (uncoupled, loosely coupled, tightly coupled,
single-project). The MDAA determines the type of program with concurrence from the NASA AA.
For projects, identify the project category (Category 1, 2, or 3).
NPR 7120.5F -- AppendixE
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 91 of 147
NPR 7120.5F -- AppendixE Page 91 of 147
4.0 PROGRAM/PROJECT GOALS AND OBJECTIVES
Describe the level or scope of work, goals, and objectives to be accomplished in the Formulation
Phase, Formulation cost targets and constraints, the time available, and any other constraints.
5.0 ANALYSIS OF ALTERNATIVES
Describe plans for conducting analyses of alternatives (AoA) for selecting the mission architecture
and acquisition strategies for the program/project. Define the scope of the analyses and concepts to
be competed, recognizing that some of the AoA content may be developed and documented outside
the program at the Mission Directorate level. Document any assumptions and constraints applicable
to the analyses. Identify the selection criteria to be used, such as safety, cost, affordability, schedule,
and capability, to help ensure that the alternative selected best meets the mission needs. (Rankings
and results of the analyses of alternatives should be documented in the Program or Project Plan.) If
the program/project does not plan to conduct analyses of alternatives, document the justification for
not doing so.
6.0 INTERNAL PARTICIPANTS
Identify Mission Directorates, mission support offices, and Centers to be involved in the activity,
their scope of work, and any known constraints related to their efforts (e.g., the program/project will
be co-funded by a different Mission Directorate).
7.0 EXTERNAL PARTICIPANTS
Identify participation external to NASA to be involved in the activity, their scope of work, and any
known constraints related to their efforts (e.g., the program/project will be co-funded by the external
participant; commercial or other partners that will develop end products that are not owned by
NASA, but are provided as services to NASA; etc.).
8.0 BUDGET AND COST ESTIMATE
Identify, by fiscal year, the funding that will be committed to the program/project during each year
of Formulation. If the Formulation period is less than five years, provide estimated annual costs for
five years. For projects, provide an estimated life-cycle or initial capability cost range that is
consistent with this five fiscal-year cost runout.
9.0 SCHEDULE
For each project, provide the planned date for the completion of Phase A and estimated completion
of Phase B. Provide an estimated date (or range) for the completion of project development. Specify
the planned prime operations period or initial capability operations period.
10.0 LIFE-CYCLE REVIEWS
Specify the program and project life-cycle reviews (per figures 2-2, 2-3, 2-4, and 2-5 in Chapter 2 of
this NPR) that are required to be conducted during the Formulation Phase. Include any other
requirements (e.g., the Decision Framing Meeting or Pre-ASM, ASM) and any known unique
considerations (e.g., acquisition strategies such as commercial partnerships, international
participation). Identify any planned tailoring to accommodate aspects of the acquisition strategies
(See Section 2.2.4.1) and when the tailoring approach will be defined.
NPR 7120.5F -- AppendixE
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 92 of 147
NPR 7120.5F -- AppendixE Page 92 of 147
NPR 7120.5F -- AppendixE
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 93 of 147
NPR 7120.5F -- AppendixE Page 93 of 147
Appendix F. Project Formulation Agreement
Template
F.1 Formulation Agreement Template Instructions
F.1.1 The Formulation Agreement represents the project's or single-project program's response to
the Formulation Authorization Document. (See Appendix E.) It establishes technical and acquisition
work that needs to be conducted during Formulation and defines the schedule and funding
requirements during Phase A and Phase B for that work. The Agreement focuses on the project or
single-project program activities necessary to accurately characterize the complexity and scope of
the project or single-project program; increase understanding of requirements; and identify and
mitigate high technical, acquisition, safety, cost, and schedule risks. It identifies and prioritizes the
Phase A and Phase B technical and acquisition work that will have the most value and enables the
project or single-project program to develop high-fidelity cost and schedule range estimates or high
and low values for cost and schedule with the corresponding JCL values (for projects and
single-project programs with a life-cycle or initial capability cost greater than or equal to $1B) at
KDP B and high-fidelity cost and schedule commitments at KDP C.
F.1.2 The Formulation Agreement serves as a tool for communicating and negotiating the project's
or single-project program's Formulation plans and resource allocations with the program and
Mission Directorate. It allows for differences in approach between competed versus assigned
missions. Variances with NPR 7120.5 product maturities as documented in Appendix I of NPR
7120.5 are identified with supporting rationale in the Agreement. The approved Agreement serves as
authorization for these variances. The Agreement is approved and signed at KDP A and is updated
and resubmitted for signature at KDP B. The Formulation Agreement for KDP A includes detailed
Phase A information and preliminary Phase B information. The Formulation Agreement for KDP B
identifies the progress made during Phase A and updates and details Phase B.
F.1.3 Each section of the Formulation Agreement template is required. If a section is not applicable
to a particular project or single-project program, the project or single-project program indicates that
in the appropriate section and provides a rationale. If a section is applicable but the project or
single-project program desires to omit the section or parts of a section, then a waiver or deviation
needs to be obtained in accordance with the tailoring process for NPR 7120.5. (See Section 3.5.)
Approvals for waivers are documented in the Compliance Matrix, and the Compliance Matrix for
this NPR is attached to the Formulation Agreement. If the format of the completed project or
single-project Formulation Agreement differs from this template, a cross-reference table indicating
where the information for each template paragraph is needs to be provided with the document when
it is submitted for the MDAA signature.
F.1.4 The approval signatures of MDAA, the Center Director, and the program manager certify that
the Formulation Agreement implements all the Agency's applicable institutional requirements or that
the owner of those requirements (e.g., Safety and Mission Assurance) has agreed to the modification
of those requirements contained in the Formulation Agreement.
NPR 7120.5F -- AppendixF
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 94 of 147
NPR 7120.5F -- AppendixF Page 94 of 147
F.1.5 Products developed as part of or as a result of the Formulation Agreement may be
incorporated into the Project or Single-Project Program Plan, if appropriate, as the Project or
Single-Project Program Plan is developed during Formulation. The project or single-project program
may use the preliminary Project or Single-Project Program Plan to describe and control the project's
or single-project program's execution as long as the Project or Single-Project Program Plan does not
conflict with the Formulation Agreement.
F.2 Formulation Agreement Title Page
Figure F-1 Formulation Agreement Title Page
F.3 Formulation Agreement Template
[Project or Single-Project Program Name] Formulation Agreement
[short title or acronym]
1.0 Purpose
Describe the purpose of the program/project, including traceability from Formulation Authorization
Agreement (FAD). (See Appendix E.)
2.0 Project or Single-Project Program Formulation Framework
Identify the project or single-project program organization chart for Formulation; identify the initial
NPR 7120.5F -- AppendixF
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 95 of 147
NPR 7120.5F -- AppendixF Page 95 of 147
project or single-project program team, key personnel, and responsible Centers and partnerships (as
known) that will contribute during Formulation. Define major roles and responsibilities and identify
any Boards and Panels that will be used during Formulation for decision making and managing
project or single-project program processes.
Specifically identify the Decision Authority and governing Program Management Council (PMC)
for oversight of the program or project, and any delegated Decision Authority and delegated
governing PMC, per Section 2.3 of NPR 7120.5.
3.0 Project or Single-Project Program Plan and Project or Single-Project Program Control
Plans
Document the project's or single-project program's proposed milestones for delivery of the Project or
Single-Project Program Plan and project or single-project program control plans on the project or
single-project program schedule and provide rationale for any differences from requirements in
product maturities as documented in Appendix I of NPR 7120.5, NASA Space Flight Program and
Project Management Requirements.
4.0 Project or Single-Project Program, System, and Subsystem Requirements Flow Down
Document the project's or single-project program's proposed milestones for flow down of
requirements to the project or single-project program, system, and subsystem levels on the project or
single-project program schedule and provide rationale for any differences from requirements in
product maturities as documented in Appendix I of NPR 7120.5. Document the project or
single-project program schedule for development of any models needed to support requirements
development.
5.0 Mission Scenario, Architectures, and Interfaces
Document the project's or single-project program's proposed milestones for producing the mission
concept, mission scenario (or design reference mission), concept of operations, and mission,
spacecraft, payload, and ground systems architectures down to the level of subsystem interfaces.
Include these milestones on the project or single-project program schedule and provide rationale for
any differences from requirements documented in the tables in Appendix I of this NPR.
Reference documentation of the feasible concept, concepts already evaluated, and plans for
additional concepts to be evaluated during Formulation. Documentation should include ground
rules, assumptions, and constraints used for analysis; key architecture drivers, such as redundancy;
preliminary key performance parameters; top-level technical parameters and associated margins; and
preliminary driving requirements. Documentation should also include feasible candidate
architectures; open architecture issues and how and when those issues will be resolved; basic
descriptions of each element; and descriptions of interfaces between elements.
At KDP B update the approved concept and architecture, including a preliminary definition of the
operations concept and updated description of composition of payload/suite of instruments. Identify
the work required to close all architecture and architectural interface issues.
6.0 Trade Studies
Identify spacecraft and ground systems design trade studies planned during phases A and B,
including trade studies that address performance versus cost and risk.
7.0 Risk Mitigation
NPR 7120.5F -- AppendixF
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 96 of 147
NPR 7120.5F -- AppendixF Page 96 of 147
Document plans for managing risks during Formulation. Identify the project's or single-project
program's major technical, acquisition, safety, cost, and schedule risks to be addressed during
Formulation, including risks likely to drive the project's or single-project program's cost and
schedule range estimates or high and low values for cost and schedule with the corresponding JCL
values at KDP B, and cost and schedule estimates at KDP C. Describe the associated risk mitigation
plans. Provide rationale for addressing these risks during Formulation.
Document the project's or single-project program's risk mitigation schedule and funding
requirements. Include intermediate milestones and expected progress by KDP B and KDP C.
8.0 Technology Readiness Assessment and Development
Identify the specific new technologies (Technology Readiness Levels (TRL) less than six) that are
part of this project or single-project program; their criticality to the project's or single-project
program's objectives, goals, and success criteria; and the current status of each planned technology
development, including TRL and associated risks. Describe the specific activities and risk mitigation
plans, the responsible organizations, models, and key tests to ensure that the technology maturity
reaches TRL 6 by Preliminary Design Review (PDR). (Refer to NPR 7123.1, NASA Systems
Engineering Processes and Requirements, for TRL definitions and SP-20205003605, Technology
Readiness Assessment Best Practices Guide for technology readiness assessment best practices.)
Identify off-ramp decision gates and strategies for ensuring there are alternative development paths
available if technologies do not mature as expected. Identify potential cost, schedule, or performance
impacts if the technology developments do not reach the required maturity levels.
Provide technology development schedules, including intermediate milestones and funding
requirements, during phases A and B for each identified technology development to achieve TRL 6
by PDR. Describe expected status of each technology development at SRR, MDR/SDR, and PDR.
Reference the preliminary or final Technology Development Plan for details as applicable. Describe
how the program will transition technologies from the development stage to manufacturing,
production, and insertion into the end system. Identify any potential costs and risks associated with
the transition to manufacturing, production, and insertion. Develop and document appropriate
mitigation plans for the identified risks.
9.0 Engineering Development Assessment, Prototyping, and Software Models
Identify major engineering development risks and any engineering prototyping or software model
development that needs to be accomplished during phases A and B to reduce development risk
(Engineering development risks include components and assemblies that have not been previously
built or flown in the planned environment or that have been significantly modified in functionality,
interfaces, power consumption, size, or use of materials.). Provide rationale and potential impacts to
project or single-project program performance, cost, and schedule if development risks are not
addressed. Describe the scope of the prototyping and modeling activities and the expected reduction
of cost and risk by performing this work during Formulation. Include the project or single-project
program's testing philosophy, including functional, environmental, and qualification testing, any life
testing and protoflight test plans, and rationale.
Describe the prototypes and software models to be built, their fidelity (form, fit, and function, etc.),
test environments and objectives, and test dates. Identify any design alternatives if irresolvable
problems are encountered.
NPR 7120.5F -- AppendixF
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 97 of 147
NPR 7120.5F -- AppendixF Page 97 of 147
Provide prototype and software model development and test schedules, including intermediate
milestones and funding requirements during phases A and B. Describe expected status and
accomplishments for each prototype or software model at SRR, MDR/SDR, and PDR.]
Focus during Phase A should be on component and subassembly prototypes built to approximately
the correct size, mass, and power, with "flight-like" parts and materials, and tested in a laboratory
environment over the extremes of temperature and radiation (if relevant). Focus during Phase B
should be on testing form, fit, and function prototypes over the extremes of what will be experienced
during flight.
Identify key performance parameters, associated modeling methodologies, and methods for tracking
KPPs throughout Formulation. In addition, identify any planned investments, divestments,
acquisition strategies, procurements, agreements, and changes to capability portfolio capability
components in accordance with requirements and strategic guidance included in NPR 8600.1, NASA
Capability Portfolio Management Requirements. (See Appendix A for definitions of capability
portfolio and capability component.)
10.0 Heritage Assessment and Validation
Identify the major heritage hardware and software assumptions and associated risks and the
activities and reviews planned to validate those assumptions during Formulation. Identify schedule
and funding requirements for those activities. See SP-20205003605, Technology Readiness
Assessment Best Practices Guide.
11.0 Acquisition Strategy and Long-lead Procurements
Identify acquisition and partnership plans during Formulation. Document the project's or
single-project program's proposed milestones for in-house work and procurements, including
completing any Contract Statements of Work (SOW) and Requests for Proposal (RFP) during the
Formulation phase. Identify long-lead procurements to be initiated and provide associated rationale.
Identify procurements of material and services necessary for life-cycle sustainment. Identify
anticipated partnerships (other government agencies and U.S. and international partners), if any,
including roles and contributed items and plans for getting commitments for contributions and
finalizing open inter-agency agreements, domestic partnerships, and foreign contributions. Point to
the preliminary or final Acquisition Strategy for details, as applicable.
Identify major acquisition risks, including long-lead procurement risks and partnership risks.
Identify funding requirements for procurement activities, long-lead procurements, and partnerships.
12.0 Formulation Phase Reviews
Identify and provide schedules for the project or single-project program life-cycle reviews (SRR,
SDR/MDR) and the system and subsystem-level reviews to be held during Formulation. Include
inheritance reviews, prototype design reviews, technology readiness reviews, fault protection
reviews, etc., necessary to reduce risk and enable more accurate cost and schedule range estimates
or high and low values for cost and schedule with the corresponding JCL values at KDP B and more
accurate cost and schedule estimates at KDP C.
13.0 Formulation Phase Cost and Schedule Estimates
Document the project's or single-project program's Formulation Phase schedule and phased funding
requirements, including cost and schedule margins, aligned with the project or single-project
NPR 7120.5F -- AppendixF
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 98 of 147
NPR 7120.5F -- AppendixF Page 98 of 147
program Work Breakdown Structure (WBS). Identify the critical path.
Ensure that all funding requirements in this Agreement are included and clearly identifiable.
Summarize funding requirements both in dollars and estimated percent of total costs phases A-D.
Ensure that the schedules for all technology development, engineering prototyping, procurement and
risk mitigation activities, and milestones identified in this Agreement are included and clearly
identifiable. Provide schedule details to the appropriate level to justify Formulation funding
requirements (typically subsystem level).
Include any additional milestones required in product maturities as documented in Appendix I in
NPR 7120.5, including the development of life-cycle or initial capability cost and schedule ranges or
high and low values for cost and schedule with the corresponding JCL values due at KDP B and the
JCL at KDP C, if required.
Identify the schedule for developing the project's or single-project program's EVM capabilities, if
EVM is required.
14.0 Leading Indicators
Document the project's or single-project program's programmatic and technical leading indicators
for the Formulation Phase.
Project or single-project programs develop and maintain the status of a set of programmatic and
technical leading indicators to ensure proper progress and management of the project or
single-project program are achieved during Formulation. Status and trends of leading indicators
should be presented at LCRs and KDPs. These leading indicators include:
Requirement Trends (percent growth, TBD/TBR (to be resolved) closures, number of
requirement changes).
Interface Trends (percent Interface Control Document (ICD) approvals, TBD/TBR burn down,
number of interface requirement changes).
Review Trends (Review Item Discrepancy (RID)/Request for Action (RFA)/Action Item burn
down per review).
Formulation Cost Trends (Plan vs. actual, UFE).
Schedule Trends (critical path slack/float, critical milestone dates).
Staffing Trends (Full-Time Equivalent (FTE)/Work Year Equivalent (WYE) (plan vs. actual)).
Technical Performance Measures (Mass margin, power margin).
Additional project or single-project program-specific indicators, as needed.
These indicators are further explained in the NASA Space Flight Program and Project Management
Handbook, NASA/SP-20220009501; the NASA Project Planning and Control Handbook,
NASA/SP-2016-3424; and the NASA Common Leading Indicators Detailed Reference Guide at
https://nodis3.gsfc.nasa.gov/OCE_rep/OCE_list.cfm.
15.0 Appendices
Appendix A. Acronyms
Appendix B. Definitions
Appendix C. Compliance Matrix for this NPR
NPR 7120.5F -- AppendixF
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 99 of 147
NPR 7120.5F -- AppendixF Page 99 of 147
Appendix G. Program Plan Template
G.1 Template Instructions
G.1.1 The Program Plan is an agreement among the program manager, Center Director, and Mission
Directorate Associate Administrator (MDAA). Other Center Directors providing a significant
contribution to the program also concur with the Program Plan to document their commitment to
provide required Center resources. The Program Plan defines the goals and objectives of the
program, the environment within which the program operates, and the Management Agreement
commitments of the program, including identifying the high-level requirements on both the program
and each constituent project. These requirements on the project may be in the body of the Plan or
added as appendices. The Program Plan is to be updated and approved during the program life cycle
if warranted by changes in the stated Management Agreement commitments.
G.1.2 In this Program Plan template, all subordinate plans, collectively called control plans, are
required unless they are not applicable or are marked as "Best Practice" in the applicable table in
Appendix I (i.e., I-Table). (The expectation is that products marked as "Best Practice" will be
developed per the I-Table as part of normal program management activities.) They are based on
requirements in NASA Policy Directives (NPDs) and NASA Procedural Requirements (NPRs) that
affect program/project planning. If a control plan is not applicable to a particular program, indicate
that by stating it is not applicable in the appropriate section and provide a rationale. Control plans
can either be part of the Program Plan or separate stand-alone documents referenced in the
appropriate part of the Program Plan. Considerations for determining if a control plan should be a
stand-alone document include a requirement that the control plan be stand-alone in the NPR that
requires the control plan; differences between when the control plan is baselined and when the
Program Plan is baselined; how frequently the control plan will be updated; and how long the
control plan is. When the control plan is a stand-alone document, the Program Plan contains a
reference to the stand-alone document.
G.1.3 Each section of the Program Plan template is required. If a section is not applicable to a
particular program, indicate in the appropriate section and provide a rationale. If a section is
applicable but the program desires to omit the section or parts of a section, then a waiver needs to be
obtained in accordance with the requirement tailoring process for NPR 7120.5, NASA Space Flight
Program and Project Management Requirements. Approvals are documented in Part 4.0, Waivers or
Deviations Log, of the Program Plan. In addition, the program's Compliance Matrix for this NPR is
attached to the Program Plan. If the format of the completed Program Plan differs from this
template, a cross-reference table indicating where the information for each template paragraph is
needs to be provided with the document when it is submitted for MDAA signature.
G.1.4 The approval signatures of the MDAA, the Center Director, and the program manager certify
that the Program Plan implements all the Agency's applicable institutional requirements or that the
authority responsible for those requirements (e.g., Safety and Mission Assurance, have granted a
deviation or waiver to the modification of those requirements.
G.1.5 Single-project programs may combine the Program and Project Plans into a single document if
the MDAA agrees.
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 100 of 147
NPR 7120.5F -- AppendixG Page 100 of 147
G.2 Program Plan Title Page
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 101 of 147
NPR 7120.5F -- AppendixG Page 101 of 147
G.3 Program Plan Template
[Program Name] Program Plan
[short title or acronym]
1.0 PROGRAM OVERVIEW
1.1 Introduction
Briefly describe the background of the program and its current status, including results of
Formulation activities, decisions, and documentation. Specify the type of program (i.e.,
single-project, uncoupled, loosely coupled, or tightly coupled) and the basis for that classification.
Specify if there are plans for continuing operations and production, including integration of
capability upgrades, with an unspecified Phase E end point, for:
Each project.
Single-project programs.
1.2 Goals and Objectives
State program goals and specific objectives and provide clear traceability to the Agency's strategic
goals and to Mission Directorate strategic goals and objectives. Program performance goals and
their relationship to NASA program goals set forth in NPD 1001.0, NASA Strategic Plan should be
expressed in an objective, quantifiable, and measurable form. Goals and objectives should include
specific commitments to safety and mission success.
1.3 Program Architecture
Briefly describe the architecture of the program, its major components, and the way they will be
integrated. Describe how the major program components are intended to operate together, and with
legacy systems, as applicable, to achieve program goals and objectives.
Provide a summary-level technical description of the program, including constituent projects and
operations concepts. The description should also include mission description, program interfaces,
facilities, logistics concepts, planned mission results, and data analysis, archiving, and reporting.
Identify driving ground rules and assumptions and major constraints affecting program systems
development (e.g., cost, launch window, required launch vehicle, mission planetary environment,
fuel/engine design, human systems integration, and foreign partners).
For single-project programs and projects that plan continuing operations and production, including
integration of capability upgrades, with an unspecified Phase E end point, define the scope of the
initial capability.
Describe how the program will relate to other organizations within and outside NASA. Reference
Section 3.4, Acquisition Strategy in this template (below) or provide the following information here:
For organizations within NASA, describe the roles of each in the program, including technology
efforts, space communications, and launch services.
For organizations outside NASA, describe the role of each in the program, including other
government agencies, academia, industry, and international partners as they are known at the start of
the program.
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 102 of 147
NPR 7120.5F -- AppendixG Page 102 of 147
1.4 Stakeholder Definition
Identify the main stakeholders of the program (e.g., PI, science community, technology community,
public, education community, and Mission Directorate sponsor(s)) and the process to be used within
the program to ensure stakeholder advocacy.
1.5 Program Authority, Management Approach, and Governance Structure
Specifically identify the Decision Authority and governing Program Management Council (PMC)
for oversight of the program, and any delegated Decision Authority and delegated governing PMC,
per Section 2.3 of NPR 7120.5.
Describe the program management structure, including each participating organization's
responsibilities. Identify:
The Center where the program manager resides.
The Centers involved and each Center's responsibilities, as they relate to their respective
requirement allocations referenced in Section 2.1, Requirements Baseline below.
Describe the chain of accountability and decision path outlining the roles and responsibilities of the
Mission Directorate sponsor(s), program manager, Center Director, and other authorities (including
the Technical Authorities), as required. Provide a high-level description of the project's organization
within the program, showing the chain of accountability. Describe clear lines of authority from
projects and Centers to the program, and to the Mission Directorate, and frequency of reporting for
each. Illustrate the organization graphically. Describe the process by which projects are formulated,
approved, and terminated.
1.6 Implementation Approach
Describe briefly the implementation approach of the program, including any applicable guidance or
direction from the ASM review, the acquisition strategy (e.g., in-house, NASA Centers, and
contractor primes), partners, and partner contributions, including acquisition approaches such as
commercial or other partners who will develop end products that are not owned by NASA but
provided as services to NASA, if appropriate. Include make-or-buy decision plans and trade studies.
Identify and document concurrence for any investments, divestments, acquisition strategies,
procurements, agreements, and changes to capability portfolio capability components in accordance
with requirements and strategic guidance included in NPR 8600.1, NASA Capability Portfolio
Management Requirements. (See Appendix A for definitions of capability portfolio and capability
component.)
Document the agreements on the use of implementation policies and practices between the program
manager and participating NASA Centers in this section (or in appendices to the document), along
with the program's approach to ensuring that interfaces do not increase risk to mission success. (For
tightly coupled programs, the program manager, the NASA Chief Engineer, and the Center Chief
Engineers (or designees) participating in the program establish the engineering best practices for the
program. These decisions are documented here.)
2.0 PROGRAM BASELINES
2.1 Requirements Baseline
Program Requirements. Document the high-level program requirements, including performance,
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 103 of 147
NPR 7120.5F -- AppendixG Page 103 of 147
safety, and programmatic requirements and correlate them to Agency and Mission Directorate
strategic objectives and requirements. Describe the process by which program requirements are
verified for compliance. Describe the process for controlling changes to program requirements.
Document the traceability of requirements that flow down from Agency- and Center-level policy to
the program and from the program to projects.
Requirements Documentation. For tightly coupled programs and single-project programs,
decompose these high-level requirements into requirements on constituent projects or systems,
specified herein or in a separate, configuration-controlled, program requirements document to be
prepared by the program manager and approved by the MDAA. Additional concurrences may be
required at the option of the NASA AA. There may also be subordinate project requirements
documents controlled at lower levels.
For uncoupled or loosely coupled programs, apply these high-level requirements to generate the
program's requirements on each constituent project. This documentation is controlled by the Mission
Directorate and may be located in the body of the Program Plan or in a subsequent appendix.
Requirements thus documented, and any subsequent changes, require approval of the program
manager, MDAA, and participating Center Director(s).
Program Requirements on Projects. For each project, provide a top-level description, including
the mission's science or exploration objectives. Document the project's category, Decision Authority,
governing PMC, and risk classification or identify where this information is documented. Describe
the project's mission, performance, and safety requirements. For science missions, include baseline
science requirements, threshold science requirements, and mission data requirements. (See
Appendix A for definitions of baseline and threshold science requirements.) Identify the mission
success criteria for each project based on the threshold science requirements. State each requirement
in objective, quantifiable, and verifiable terms. Identify the project's principal schedule milestones,
including Preliminary Design Review (PDR), Critical Design Review (CDR), launch, mission
operational-critical milestones, and the planned decommissioning date. State the development and/or
total life-cycle or initial capability cost constraints on the project. Set forth any budget constraints
by fiscal year. State the specific conditions under which a project Termination Review would be
triggered. Describe any additional requirements on the project (e.g., international partners). If the
mission characteristics indicate a greater emphasis is necessary on maintaining technical, cost, or
schedule, then identify which is most important (e.g., state if the mission is cost capped; or if
schedule is paramount, as for a planetary mission; or if it is critical to accomplish all of the technical
objectives, as for a technology demonstration mission).
2.2 WBS Baseline
Provide the program's Work Breakdown Structure (WBS) and WBS dictionary down to the project
level developed in accordance with guidance provided by the NASA Work Breakdown Structure
(WBS) Handbook, NASA/SP-2010-3404, which can be found on the OCE tab under the "Other
NASA-Level Documents"; menu in NODIS. The WBS will support cost and schedule allocation
down to a project level that allows for unambiguous cost reporting.
2.3 Schedule Baseline
Present a summary of the program's integrated master schedule (IMS), including all critical
milestones, major events, life-cycle reviews, and KDPs throughout the program life cycle. The
summary of the master schedule should include the logical relationships (interdependencies) for the
various program elements and projects and critical paths, as appropriate. Identify driving ground
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 104 of 147
NPR 7120.5F -- AppendixG Page 104 of 147
rules, assumptions, and constraints affecting the schedule baseline.
2.4 Resource Baseline
Present the program's funding requirements by fiscal year. State the New Obligation Authority
(NOA) in real-year dollars for all years—prior, current, and remaining. The funding requirements are
to be consistent with the program’s WBS and include funding for all cost elements required by the
Agency’s full-cost accounting procedures. Funding requirements are to be consistent with the
budget. Provide a breakdown of the program’s funding requirements to the WBS Level 2 elements.
Present the program-specific (i.e., not individual project) workforce requirements by fiscal year,
consistent with the program’s funding requirements and WBS. Throughout the Implementation
Phase, baselines are to be based on the joint cost and schedule confidence level in accordance with
NPD 1000.5, Policy for NASA Acquisition and NPR 7120.5.
Describe the program infrastructure requirements (acquisition, renovations, and/or use of real
property/facilities, aircraft, personal property, and information technology). Identify means of
meeting infrastructure requirements through synergy with other existing and planned programs and
projects to avoid duplication of facilities and capabilities. Identify necessary upgrades or new
developments, including those needed for environmental compliance.
Identify driving ground rules, assumptions, and constraints affecting the resource baseline.
Document the constituent projects’ Commitment Baselines (i.e., ABC).
2.5 Joint Cost and Schedule Confidence Level
For single-project programs, document the joint cost and schedule confidence level approved by the
Decision Authority at KDP C. For single-project programs with an estimated life-cycle or initial
capability cost greater than or equal to $1B, update the joint cost and schedule confidence level at
CDR and at KDP D (if applicable).
3.0 PROGRAM CONTROL PLANS
3.1 Technical, Schedule, and Cost Control Plan
This control plan will include the following:
Describe the plan to monitor and control the program requirements, technical design, schedule, and
cost to achieve its high-level requirements.
Describe the program's performance measures in objective, quantifiable, and measurable terms and
document how the measures are traced from the program high-level requirements. Establish baseline
and threshold values for the performance metrics to be achieved at each Key Decision Point (KDP),
as appropriate. In addition, document the mission success criteria associated with the program-level
requirements that, if not met, trigger consideration of a Termination Review.
Tightly coupled and single-project programs also develop and maintain the status of a set of
programmatic and technical leading indicators to ensure proper progress and management of the
program. Status and trends of leading indicators should be presented at LCRs and KDPs. These
leading indicators include:
Requirement Trends (percent growth, TBD/TBR closures, number of requirement changes).
Interface Trends (percent ICD approval, TBD/TBR burn down, number of interface
requirement changes).
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 105 of 147
NPR 7120.5F -- AppendixG Page 105 of 147
requirement changes).
Verification Trends (closure burn down, number of deviations/waivers approved/open).
Review Trends (RID/RFA/Action Item burn down per review).
Software Unique Trends (number of requirements per build/release versus plan).
Problem Report/Discrepancy Report Trends (number open, number closed).
Cost Trends (Plan vs. actual, UFE, EVM).
Schedule Trends (critical path slack/float, critical milestone dates).
Staffing Trends (FTE/WYE plan vs. actual).
Technical Performance Measures (Mass margin, power margin).
Manufacturing Trends (Number of nonconformance/corrective actions (open/
closed/resolved)).
Additional program-specific indicators, as needed.
These indicators are further explained in the NASA Space Flight Program and Project Management
Handbook, NASA/SP-20220009501; the NASA Project Planning and Control Handbook,
NASA/SP-2016-3424; and the NASA Common Leading Indicators Detailed Reference Guide at
https://nodis3.gsfc.nasa.gov/OCE_rep/OCE_list.cfm.
Describe how constituent projects will periodically report performance. Describe mitigation
approach if projects are exceeding their development cost documented in the ABC to enable
corrective action prior to triggering the 30 percent breach threshold. Describe how projects will
support a baseline review in the event the Decision Authority (DA) directs one. Describe how the
program will implement the Système Internationale (SI) and other systems of measurement and the
identification of units of measure in all product documentation. Where full implementation of the SI
system of measurement is not practical, hybrid configurations (i.e., a controlled mix of SI and
non-SI system elements) may be used to support maximum practical use of SI units for design,
development, and operations. Where hybrid configurations are used, describe the specific
requirements established to control interfaces between elements using different measurement
systems. (See NPR 7120.5, Section 3.7, for SI assessment timing requirement.)
Describe the program's implementation of Technical Authority (Engineering, Safety and Mission
Assurance, and Health and Medical).
For single-project programs, describe the program's EVMS (see Appendix H, Section 3.1); For
tightly coupled programs, describe the program's EVMS, if EVM requirements are to be levied at
the program level. For loosely coupled or uncoupled programs, describe the EVM requirements
flowed down to the projects. Include plan for flow down of EVM requirements and reporting to
support project EVM.
Describe any additional specific tools the program will use to implement the program control
processes (e.g., the requirements management system, the program scheduling system, or the
program information management systems).
Describe how the program will monitor and control the integrated master schedule (IMS).
Describe how the program will utilize its technical and schedule margins and Unallocated Future
Expense (UFE) to control the Management Agreement.
Describe how the program plans to report technical, schedule, and cost status to the MDAA,
including frequency and the level of detail.
Describe how the program will address technical waivers and deviations and how Formal Dissents
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 106 of 147
NPR 7120.5F -- AppendixG Page 106 of 147
will be handled.
3.2 Safety and Mission Assurance Plan
Develop a program Safety and Mission Assurance (SMA) Plan as required by NPR 8705.2,
Human-Rating Requirements for Space Systems for crewed missions and NPR 8705.4, Risk
Classification for NASA Payloads for un-crewed missions and payloads.
The SMA Plan reflects a program life-cycle SMA process perspective, addressing areas including:
SMA domain management and integration (e.g., for safety, reliability, maintainability, quality,
planetary protection, etc.) with other engineering and management functions (e.g., concept and
design trade-studies; risk analysis and risk assessments; risk-informed decision making; fault
tolerance and contingency planning; knowledge capture; hardware and software design assurance;
supply chain risk management and procurement; hardware and software design verification, and
test; manufacturing process design and control; manufacturing and product quality assurance; system
verification and test; pre-flight verification and test; operations; maintenance; logistics planning;
maintainability and sustainability; operational reliability and availability; decommissioning; and
disposal).
Describe how the program will develop and manage a Closed-Loop Problem Reporting and
Resolution System. Describe how the program develops, tracks, and resolves problems. The process
should include a well-defined data collection system and process for hardware and software
problems and anomaly reports, problem analysis, and corrective action.
Identify the program’s approach to flow down requirements as appropriate to external developers
and suppliers in acquisitions (e.g., contracts and purchase orders).
Describe how the program will develop, evaluate, and report indications of SMA program maturity
and effectiveness at life cycle or other executive reviews, including through the use of metrics and
indicators that are not otherwise included in formal life cycle review deliverables or are not
elements of the certification of flight readiness (COFR) process (e.g., satisfactory progress towards
human rating).
3.3 Risk Management Plan
Develop a Risk Management Plan that includes the content required by NPR 8000.4, Agency Risk
Management Procedural Requirements. Summarize how the program will implement the NASA risk
management process (including risk-informed decision making (RIDM) and continuous risk
management (CRM) in accordance with NPR 8000.4, Agency Risk Management Procedural
Requirements. Include the initial Significant Risk List and appropriate actions to mitigate each risk.
Programs with international or other U.S. Government agency contributions need to plan for, assess,
and report on risks due to international or other government partners and plan for contingencies.
3.4 Acquisition Strategy
The program Acquisition Strategy is developed by the program manager, supported by the Office of
Procurement, and needs to be consistent with NPD 1000.5, Policy for NASA Acquisition, the results
of the Agency strategic acquisition process, and the ASM. The elements of the program Acquisition
Strategy should be reflected in any resulting Procurement Strategy Meeting (PSM) for individual
procurement activity supporting the program Acquisition Strategy. It documents an integrated
acquisition strategy that enables the program to meet its mission objectives and provides the best
value to NASA. The Acquisition Strategy should include, but is not limited to, the following:
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 107 of 147
NPR 7120.5F -- AppendixG Page 107 of 147
Identify all major proposed acquisitions (such as engineering design study, hardware and software
development, mission and data operations support, and sustainment) in relation to the program
WBS. Provide summary information on each such proposed acquisition, including a Contract WBS;
major deliverable items; recommended type of procurement (competitive, AO for instruments); type
of contract (cost-reimbursable, fixed-price); source (institutional, contractor, other U.S. Government
agency, or international organization); procuring activity; and surveillance approach. Identify those
major procurements that require a PSM.
Describe completed or planned studies supporting make-or-buy decisions, considering NASA’s
in-house capabilities and the maintenance of NASA’s core competencies, as well as cost and best
overall value to NASA.
Describe the state of the industrial base capability and identify potential critical and single-source
suppliers needed to design, develop, produce, support, and, if appropriate, restart an acquisition
program or project. The acquisition strategy should promote sufficient program/project stability to
encourage industry to invest, plan, and bear their share of risk. Describe the internal and external
mechanisms and procedures used to identify, monitor, and mitigate industrial base and supply chain
risks. Include data reporting relationships to allow continuous surveillance of the entire supply chain
that provides for timely notification and mitigation of potential risks associated with the industrial
base or supply chain. Describe the process for reporting industrial base and supply chain risks to the
MDAA.
Identify the program’s approach to strengthen safety and mission assurance in the contract.
Describe all agreements, memoranda of understanding, barters, in-kind contributions, and other
arrangements for collaborative and/or cooperative relationships. Include partnerships created
through mechanisms other than those prescribed in the FAR and the NFS. List all such agreements
(the configuration control numbers, the date signed or projected dates of approval, and associated
record requirements) necessary for program success. Include or reference all agreements concluded
with the authority of the program manager and reference agreements concluded with the authority of
the MDAA and above. Include the following:
(1) NASA agreements (e.g., space communications, launch services, and inter-Center memoranda of
agreement).
(2) Non-NASA agreements:
(a) Domestic (e.g., U.S. Government agencies).
(b) International (e.g., memoranda of understanding).
Describe intellectual property considerations and goals for advanced technologies to protect core
NASA interests during the program life cycle; the process for respecting and protecting privately
developed intellectual property; the process for ensuring acquisition strategies, proposals, and
contract awards reflect intellectual property considerations established for the program; the approach
for ensuring that the intellectual property strategy promotes competition for post-production
sustainment/modernization contracts; the approach for seeking flexible and creative solutions to
intellectual property issues that meet the desires of the parties and reflect NASA’s investment; the
approach for ensuring procurement contracts specify both (1) the delivery of necessary technical
data and computer software and (2) the license rights necessary for technical data and computer
software; and the approach for ensuring the delivery of technical data and computer software under
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 108 of 147
NPR 7120.5F -- AppendixG Page 108 of 147
procurement contracts is marked in accordance with the contract at the time of delivery.
3.5 Technology Development Plan
Describe the technology assessment, development, management, and acquisition strategies
(including intellectual property considerations) needed to achieve the program’s mission objectives.
Describe how the program will assess its technology development requirements, including how the
program will evaluate the feasibility, availability, readiness, cost, risk, and benefit of the new
technologies. The approach should include timely reporting of new technologies to the Center
Technology Transfer Office and supporting technology transfer activities as described in NPR
7500.2, NASA Technology Transfer Requirements.
Describe how the program will identify opportunities for leveraging on-going technology efforts.
Describe how the program will transition technologies from the development stage to the
manufacturing and production phases. Identify the supply chain needed to manufacture the
technology and any costs and risks associated with the transition to the manufacturing and
production phases. Develop and document appropriate mitigation plans for the identified risks.
Describe the program's strategy for ensuring that there are alternative development paths available
if/when technologies do not mature as expected. (Refer to NPR 7123.1 for TRL definitions and
SP-20205003605, Technology Readiness Assessment Best Practices Guide for technology readiness
assessment best practices. The Technology Readiness Assessment Best Practices Guide can be
found in NODIS on the OCE tab under the “Other NASA-Level Documents” menu.)
Describe how the program will remove technology gaps, including maturation, validation, and
insertion plans, performance measurement at quantifiable milestones, off-ramp decision gates, and
resources required.
Describe briefly how the program will ensure that all planned technology exchanges, contracts, and
partnership agreements comply with all laws and regulations regarding export control and the
transfer of sensitive and proprietary information.
Describe how the program will transition technologies from the development stage to manufacturing,
production, and insertion into the end system. Identify any potential costs and risks associated with
the transition to manufacturing, production, and insertion. Develop and document appropriate
mitigation plans for the identified risks.
3.6 Systems Engineering Management Plan
Develop a SEMP that includes the content required by NPR 7123.1, NASA Systems Engineering
Processes and Requirements. Include descriptions of the program’s overall approach for systems
engineering, to include system design and product realization processes (implementation and/or
integration, verification and validation, and transition), as well as the technical management
processes.
3.7 Verification and Validation Plan
Summarize the approach for performing verification and validation of the program products. Indicate
the methodology to be used in the verification/validation (test, analysis, inspection, or
demonstration) as defined in NPR 7123.1, NASA Systems Engineering Processes and
Requirements.
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 109 of 147
NPR 7120.5F -- AppendixG Page 109 of 147
3.8 System Security Plan
Identify and prepare a System Security Plan for each information system. The System Security Plan
is a formal document that provides an overview of the security requirements for an information
system and describes the security controls in place or planned for meeting those requirements.
System Security Plans are generated and stored within the NASA Risk Information and Security
Compliance System (RISCS) at https://riscs-info.nasa.gov/. Multiple systems may be covered under
a single System Security Plan. Controls selected within the System Security Plan are included as
system requirements for the system or systems covered by the plan.
Document the program's approach to implementing cybersecurity requirements in accordance with
NPR 2810.1, Security of Information and Information Systems, if there are requirements outside the
scope of the System Security Plan(s).
3.9 Review Plan
Summarize the program’s approach for conducting a series of reviews, including internal reviews
and program life-cycle reviews. In accordance with Center best practices, Mission Directorate
review requirements, and the requirements in NPR 7123.1, NASA Systems Engineering Processes
and Requirements and NPR 7120.5, NASA Space Flight Program and Project Management
Requirements, provide the names, purposes, content, and timing of the life-cycle reviews.
Identify any deviations from these documents that the program is planning or waivers that have
been granted, including tailoring to accommodate aspects of acquisition strategies. Specify the
considerations that will be used to trigger a discussion on the need for a PIR with the NASA AA.
(See Section 2.2.4.2 and the NASA Space Flight Program and Project Management Handbook,
Section 5.11.3.) Provide the technical, scientific, schedule, cost, and other criteria that will be
utilized in the consideration of a Termination Review.
For single-project programs that plan continuing operations and production, including integration of
capability upgrades, with an unspecified Phase E end point, define the initial capability in the
Review Plan for KDP B if the initial capability is not the first operational mission flight.
For tightly coupled programs that involve multiple Centers, document the program life-cycle review
requirements on the supporting projects that represent an integrated review process for the various
projects and take into consideration the participating Centers’ review process best practices. For each
program life-cycle review and KDP, document the sequencing of the associated project life-cycle
reviews and KDPs, i.e., whether the associated project life-cycle reviews and KDPs precede or
follow the program life-cycle review and KDP. In addition, document which projects should proceed
to their KDPs together, which projects should proceed to their KDPs simultaneously with the
program KDP, and which projects may proceed to their KDPs as individual projects.
The sequencing of project life-cycle reviews and KDPs with respect to program life-cycle reviews
and KDPs is especially important for project PDR life-cycle reviews that precede KDP Cs. At KDP
C, the Agency makes project technical, cost, and schedule commitments to its external stakeholders
at the established JCL in accordance with NPR 7120.5 requirements. Since changes to one project
can easily impact other projects’ technical, cost, schedule, and risk baselines, projects and their
program may need to proceed to KDP C/KDP I together.
3.10 Mission Operations Plan
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 110 of 147
NPR 7120.5F -- AppendixG Page 110 of 147
Describe the activities required to perform the mission. Describe how the program will implement
the associated facilities, hardware, software, and procedures required to complete the mission.
Describe mission operations plans, rules, and constraints. Describe the Mission Operations System
(MOS) and Ground Data System (GDS) in the following terms:
MOS and GDS human resources and training requirements.
Procedures to ensure that operations are conducted in a reliable, consistent, and controlled
manner using lessons learned during the program and from previous programs.
Facilities requirements (offices, conference rooms, operations areas, simulators, and test beds).
Hardware (ground-based communications and computing hardware and associated
documentation).
Software (ground-based software and associated documentation).
3.11 NEPA Compliance Plan
Describe the level of NEPA analysis planned to comply with NPR 8580.1, Implementing the
National Environmental Policy Act, and Executive Order 12114. The NEPA Compliance Plan
should be prepared based on consultation with the appropriate NEPA manager (Center NEPA
Manager or Mission Direction NEPA Liaison) and describe the program's NEPA strategy at all
affected Centers, including decisions regarding programmatic NEPA documents. Insert into the
program schedule the critical NEPA milestones if preparation of an Environmental Assessment or
Environmental Impact Statement is planned.
3.12 Integrated Logistics Support Plan
Describe how the program will implement NPD 7500.1, Program and Project Life-Cycle Logistics
Support Policy, including a maintenance and support concept; participation in the design process to
enhance supportability; supply support; maintenance and maintenance planning; packaging,
handling, and transportation; technical data and documentation; support and test equipment; training;
manpower and personnel for Integrated Logistics Support (ILS) functions; facilities required for ILS
functions; and logistics information systems for the life of the program.
3.13 Science Data Management Plan
Describe how the program will manage the scientific data generated and captured by the operational
mission(s) and any samples collected and returned for analysis. Include descriptions of how data will
be generated, processed, distributed, analyzed, and archived, as well as how any samples will be
collected, stored during the mission, and managed when returned to Earth. The Plan should include
definitions of data rights and services and access to samples, as appropriate. Identify where the
preliminary science data requirements will be documented (these requirements should be
documented by SRR). The Plan should be developed in consultation with the Mission Directorate
data leads and the Office of the Chief Information Officer (OCIO) early in the program life-cycle to
ensure that metadata standards and data formats are appropriately considered and that infrastructure
and security requirements are addressed.
Explain how the program will accomplish the information management and disposition in NPD
2200.1, Management of NASA Scientific and Technical Information; NPR 2200.2, Requirements for
Documentation, Approval and Dissemination of Scientific and Technical Information; and NPR
1441.1, NASA Records Management Program Requirements, as applicable to program science data.
Explain how the program will implement NASA sample handling, curation, and planetary protection
directives and rules, including NPR 8715.24, Planetary Protection Provisions for Robotic
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 111 of 147
NPR 7120.5F -- AppendixG Page 111 of 147
Extraterrestrial Missions.
3.14 Configuration Management Plan
Describe the configuration management (CM) approach that the program team will implement.
Describe the CM planning and management function including the CM organization and tools to be
used. Describe the methods and procedures to be used for configuration identification, configuration
control, interface management, configuration change management, configuration verification and
audit, and configuration status accounting and communications. Describe how CM will be audited
and how contractor CM processes will be integrated with the program. Configuration Management
should address hardware, software, and firmware. Additional information on configuration
management is provided in NPR 7123.1 and SAE/EIA 649, Standard for Configuration
Management.
3.15 Security Plan
Describe the program's plans for ensuring security, including:
Security Requirements: Describe the program's approach for planning and implementing the
requirements for physical, personnel, and industrial security, and for security awareness/education
requirements in accordance with NPR 1600.1, NASA Security Program Procedural Requirements.
Emergency Response Requirements: Describe the program's emergency response plan in accordance
with NPR 1040.1, NASA Continuity of Operations (COOP) Planning Procedural Requirements and
define the range and scope of potential crises and specific response actions, timing of notifications
and actions, and responsibilities of key individuals.
3.16 Technology Transfer (formerly Export) Control Plan
Describe how the program will implement the export control requirements specified in
NPR 2190.1, NASA Export Control Program.
3.17 Communications Plan
Develop a Communications Plan in collaboration with the Associate Administrator for the Office of
Communications or their designee that identifies key program milestones that will be of interest to
the general public, the media, and other key stakeholders and plans to engage these audiences via
audio and real and/or near real-time high resolution video and/or imagery for each milestone
including during full mission operations. Summarize how these efforts will promote understanding
of and engagement with program objectives, elements, benefits, and contributions to overarching
NASA goals. In collaboration with the Associate Administrator for the Office of Communications or
their designee, identify resources and technical requirements for implementation of communications
for the general public, media, and other key stakeholders. (See the Communications Plan Template
(on the Web site for the Office of Communications,
http://communications.nasa.gov/content/nasa-comm-guidelines.)
3.18 Knowledge Management Plan
Describe the program's approach to creating the program's knowledge management strategy and
processes. Strategy should include practices for examining the lessons learned database for relevant
lessons that can be reflected in the program early in the planning process to avoid known issues;
identifying, capturing, and transferring knowledge; and continuously capturing and documenting
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 112 of 147
NPR 7120.5F -- AppendixG Page 112 of 147
lessons learned throughout the program life cycle in accordance with NPD 7120.4, NASA
Engineering and Program/Project Management Policy and as described in NPD 7120.6, Knowledge
Policy for Programs and Projects and other appropriate requirements and standards documentation.
3.19 Human-Rating Certification Package
For human space flight missions, develop a Human-Rating Certification Package per
NPR 8705.2, Human-Rating Requirements for Space Systems. Human-rating certification focuses
on the integration of the human into the system, preventing catastrophic events during the mission,
and protecting the health and safety of humans involved in or exposed to space activities,
specifically the public, crew, passengers, and ground personnel.
3.20 Quality Assurance Surveillance Plan
Develop a consolidated set of detailed instructions for the performance of Government contract
quality assurance review and evaluation for the program. The plan might include contractor
documents, data, and records; products and product attributes; processes; quality system
elements/attributes; and requirements related to quality data analysis, nonconformance reporting and
corrective action tracking/resolution, and final product acceptance. (See NASA-STD-8709.22,
Safety and Mission Assurance Acronyms, Abbreviations, and Definitions.)
3.21 Orbital Collision Avoidance Plan
Describe how the program implements the design considerations and preparation for operations to
avoid in-space collisions. The plan ensures the space flight mission meets the requirements of NPR
8079.1, NASA Spacecraft Conjunction Analysis and Collision Avoidance for Space Environment
Protection. Include in the plan a project overview including a concept of operation, how orbit
selection was performed, the spacecraft's ascent and descent plan, how the spacecraft's location
tracking data will be generated, and whether there will be any autonomous flight control. Discuss
how the spacecraft's design will enable it to be acquired and tracked by the Space Surveillance
Network and be cataloged by the U.S. Space Command. Describe the process to routinely coordinate
with other operator(s) for maneuvering. Appendix D of the NPR provides a template for this plan.
(See NPR 8079.1, NASA Spacecraft Conjunction Analysis and Collision Avoidance for Space
Environment Protection for more detail and plan template.)
3.22 Human Systems Integration Approach
Tightly coupled and single-project programs develop a Human Systems Integration (HSI) approach
in accordance with NPR 7123.1. (See the NASA Human Systems Integration (HSI) Handbook,
NASA/SP-20210010952, for additional information.)
4.0 WAIVERS OR DEVIATIONS LOG
Identify NPR 7120.5 requirements for which a waiver or deviation has been requested and approved
consistent with program characteristics such as scope, complexity, visibility, cost, safety, and
acceptable risk, and provide rationale and approvals.
5.0 CHANGE LOG
Record changes in the Program Plan.
6.0 APPENDICES
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 113 of 147
NPR 7120.5F -- AppendixG Page 113 of 147
Appendix A. Acronyms
Appendix B . Definitions
Appendix C. Compliance Matrix for this NPR
NPR 7120.5F -- AppendixG
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 114 of 147
NPR 7120.5F -- AppendixG Page 114 of 147
Appendix H. Project Plan Template
H.1 Template Instructions
H.1.1 The Project Plan is an agreement among the project manager, program manager, Center
Director, and the Mission Directorate Associate Administrator (MDAA). Other Center Directors
providing a significant contribution to the project also concur with the Project Plan to document their
commitment to provide required Center resources. It defines, at a high level, the scope of the
project, the implementation approach, the environment within which the project operates, and the
baseline commitments of the program and project. The Project Plan is consistent with the Program
Plan. The Project Plan is updated and approved during the project life cycle in response to changes
in program requirements on the project or the baseline commitments.
H.1.2 In this Project Plan template, all subordinate plans, collectively called control plans, are
required unless they are not applicable or are marked as “Best Practice” in the applicable table in
Appendix I (i.e., I-Table). (The expectation is that products marked as “Best Practice” will be
developed per the I-Table as part of normal project management activities.) They are based on
requirements in NASA Policy Directives (NPDs) and NASA Procedural Requirements (NPRs) that
affect program/project planning. If a control plan is not applicable to a particular project, indicate
that by stating it is not applicable in the appropriate section and provide a rationale. Control plans
can either be a part of the Project Plan or separate stand-alone documents referenced in the
appropriate part of the Project Plan. Considerations for determining if a control plan should be a
stand-alone document include a requirement that the control plan be stand-alone in the NPR that
requires the control plan; differences between when the control plan is baselined and when the
Project Plan is baselined; how frequently the control plan will be updated since updates to the
Project Plan require signatures; and how long the control plan is. When the control plan is a
stand-alone document, the Project Plan contains a reference to the stand-alone document.
H.1.3 Each section of the Project Plan template is required. If a section is not applicable to a
particular project, indicate by stating that in the appropriate section and provide a rationale. If a
section is applicable but the project desires to omit the section or parts of a section, then a waiver or
deviation needs to be obtained in accordance with the requirement tailoring process for
NPR 7120.5. If the format of the completed Project Plan differs from this template, a cross-reference
table indicating where the information for each template paragraph is needs to be provided with the
document when it is submitted for MDAA signature. Approvals are documented in Part 4.0, Waivers
or Deviations Log, of the Project Plan. In addition, the project’s Compliance Matrix for this NPR is
attached to the Project Plan.
H.1.4 The approval signatures of the MDAA, the Center Director, program manager, and project
manager certify that the Project Plan implements all the Agency’s applicable institutional
requirements or that the authority responsible for those requirements (e.g., Safety and Mission
Assurance) have agreed to the modification of those requirements contained in the Project Plan.
H.1.5 Single-project programs may combine the Program and Project Plans into a single document if
the MDAA agrees.
H.2 Project Plan Title Page
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 115 of 147
NPR 7120.5F -- AppendixH Page 115 of 147
H.3 Project Plan Template
[Project Name] PROJECT PLAN
[short title or acronym]
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 116 of 147
NPR 7120.5F -- AppendixH Page 116 of 147
1.0 PROJECT OVERVIEW
1.1 Introduction
Briefly describe the background of the project and its current status, including results of Formulation
activities, decisions, and documentation. Document the project’s category and NASA payload
development risk classification (see NPR 8705.4, Risk Classification for NASA Payloads), as stated
in the program requirements on the project.
Specify if there are plans for continuing operations and production, including integration of
capability upgrades, with an unspecified Phase E end point.
1.2 Objectives
State the specific project objectives and high-level performance goals levied on the project by the
program. Include performance, schedule, cost, and technology development objectives, as
applicable. Identify program requirements and constraints on the project. Provide clear traceability
to applicable Agency strategic goals.
1.3 Mission Description and Technical Approach
Describe briefly the mission and the mission design. Include mission objectives and goals, mission
success criteria, and driving ground rules and assumptions affecting the mission and mission design.
Identify key characteristics of the mission, such as launch date(s), flight plans, and the key phases
and events on the mission timeline, including end of mission. For projects that plan continuing
operations and production, including integration of capability upgrades, with an unspecified Phase E
end point, define the scope of the initial capability. Use drawings, figures, charts, etc., for
clarification. Describe planned mission results, data archiving, and reporting.
Provide a brief description of the technical approach, including constituent launch, flight, and
ground systems, operations concepts, and logistics concepts. Describe the systems to be developed
(hardware and software), legacy systems, system interfaces, and facilities. Identify driving technical
ground rules and assumptions, and major constraints affecting system development (e.g., cost,
launch window, required launch vehicle, mission planetary environment, fuel/engine design, human
systems integration, and international partners).
1.4 Project Authority, Governance Structure, Management Structure, and Implementation
Approach
Describe the governance structure based on the project category. Specifically identify the Decision
Authority and governing PMC responsible for oversight of the project and any delegated Decision
Authority and delegated governing PMC, per Section 2.3 of NPR 7120.5, NASA Space Flight
Program and Project Management Requirements.
Identify the Center where the project manager resides. Describe other Centers’ responsibilities, if
any. Describe the chain of accountability and decision path that outlines the roles and
responsibilities of the project manager, program manager, Center Director, principal investigator,
and project scientist, as appropriate, and other authorities as required per the project’s
categorization.
Define the relationships among various elements and organizations within the project structure,
including all stakeholders, team members, and supporting organizations. (This includes Technical
Authorities.) Describe the project’s approach for fostering effective upward and downward
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 117 of 147
NPR 7120.5F -- AppendixH Page 117 of 147
communication of critical management, technical, risk, and safety information. (This includes the
Formal Dissent process.) Describe the process that the project will follow to communicate with the
Center Management Council (CMC) and the Integrated Center Management Council (ICMC) if
applicable. Describe briefly the process for problem reporting and subsequent decision making,
clearly describing the roles and responsibilities of all organizations. Describe any use of special
boards and committees.
Describe the project management structure consistent with the project Work Breakdown Structure
(WBS), including organization and responsibilities, its integration with the parent program
management structure, and NASA Center(s) participation. Describe clear lines of authority within
the project team and between the project, the program office, the primary Center, the Mission
Directorate, other participating Centers, and other participating organizations. Illustrate the
organization graphically.
Describe briefly the implementation approach of the project, including any applicable guidance or
direction from the Acquisition Strategy Meeting (ASM) review, the acquisition strategy (e.g.,
in-house, NASA Centers, and contractor primes), partners, and partner contributions, including
acquisition approaches such as commercial or other partners that will develop end products that are
not owned by NASA but are provided as services to NASA, if appropriate. Describe briefly other
program/project dependencies with NASA, other U.S. Government agencies, and international
activities, studies, and agreements. Include make-or-buy decision plans and trade studies.
Identify and document concurrence for any investments, divestments, acquisition strategies,
procurements, agreements, and changes to capability portfolio capability components in accordance
with requirements and strategic guidance included in NPR 8600.1, NASA Capability Portfolio
Management Requirements. (See Appendix A for definitions of capability portfolio and capability
component.)
Document the agreements on the use of implementation policies and practices between the project
manager and contributing NASA Centers in this section (or in appendices to the document), along
with the project’s approach to ensuring that interfaces do not increase risk to mission success.
1.5 Stakeholder Definition
Describe the stakeholders of the project (e.g., principal investigator (PI), science community,
technology community, public, education community, parent program, and Mission Directorate
sponsor) and the process to be used within the project to ensure stakeholder advocacy.
2.0 PROJECT BASELINES
Project baselines consist of a set of requirements, cost (including project-held UFE), schedule, and
technical content that forms the foundation for program/project execution and reporting done as part
of NASA’s performance assessment and governance process. (For more detail, see
NPR 7120.5, Section 2.4, on baseline policy and documentation.)
2.1 Requirements Baseline
List or reference the requirements levied on the project by the program in the Program Plan and
discuss how these are flowed down to lower levels by summarizing the requirements allocation
process. Reference requirements documents used by the project.
2.2 WBS Baseline
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 118 of 147
NPR 7120.5F -- AppendixH Page 118 of 147
Provide the project’s WBS and WBS dictionary to the Level 2 elements in accordance with the
standard template below and guidance provided by the NASA Work Breakdown Structure (WBS)
Handbook, NASA/SP-2010-3404, which can be found on the OCE tab under the “Other
NASA-Level Documents” menu in NODIS. The WBS will support cost and schedule allocation
down to a work package level; integrate both government and contracted work; integrate well with
the EVMS approach; allow for unambiguous cost reporting; and be designed to allow project
managers to monitor and control work package/product deliverable costs and schedule.
Figure H-2 Standard Level 2 WBS Elements for Space Flight Projects
2.3 Schedule Baseline
Present a summary of the project’s IMS, including all critical milestones, major events, life-cycle
reviews, and KDPs throughout the project life cycle. The summary of the master schedule should
include the logical relationships (interdependencies) for the various project elements and critical
paths, as appropriate. Identify driving ground rules, assumptions, and constraints affecting the
schedule baseline.
2.4 Resource
Present the project funding requirements by fiscal year. State the New Obligation Authority (NOA)
in real-year dollars for all years—prior, current, and remaining. The funding requirements are to be
consistent with the project WBS and include funding for all cost elements required by the Agency’s
full-cost accounting procedures. Provide a breakdown of the project’s funding requirements to the
WBS Level 2 elements. Throughout the Implementation Phase, cost and schedule baselines are to be
based on and maintained consistent with the approved joint cost and schedule confidence level, as
applicable, in accordance with NPD 1000.5 and NPR 7120.5.
Present the project’s workforce requirements by fiscal year, consistent with the project funding
requirements and WBS. The workforce estimate is to encompass all work required to achieve project
objectives. Include the actual full-cost civil service and support contractor workforce by the
organizations providing them for any prior fiscal years. Include full-cost civil service and support
contractor workforce requirements by the organizations providing them for the current fiscal year
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 119 of 147
NPR 7120.5F -- AppendixH Page 119 of 147
and remaining fiscal years.
Describe the project’s infrastructure requirements (acquisition, renovations, and/or use of real
property/facilities, aircraft, personal property, and information technology). Identify means of
meeting infrastructure requirements through synergy with other existing and planned programs and
projects to avoid duplication of facilities and capabilities. Identify necessary upgrades or new
developments, including those needed for environmental compliance.
Identify driving ground rules, assumptions, and constraints affecting the resource baseline.
2.5 Joint Cost and Schedule Confidence Level
For projects with an estimated life-cycle cost (LCC) initial capability cost greater than $250M,
document the project’s joint cost and schedule confidence level approved by the Decision Authority
(DA) at KDP C. For projects with an estimated life-cycle cost greater than or equal to $1B, update
the joint cost and schedule confidence level at CDR and at KDP D (if applicable).
3.0 PROJECT CONTROL PLANS
3.1 Technical, Schedule, and Cost Control Plan
This control plan documents the following:
Describe the plan to monitor and control the project requirements, technical design, schedule, and
cost of the project to ensure that the high-level requirements levied on the project are met. (If this
information is best documented in other control plans (e.g., the Systems Engineering Management
Plan) then reference those control plans.)
Describe the project’s performance measures in objective, quantifiable, and measurable terms and
document how the measures are traced from the program requirements on the project. In addition,
document the minimum mission success criteria associated with the program requirements on the
project that, if not met, trigger consideration of a Termination Review.
The project also develops and maintains the status of a set of programmatic and technical leading
indicators to ensure proper progress and management of the project. Status and trend of leading
indicators should be presented at LCRs and KDPs. These leading indicators include:
• Requirement Trends (percent growth, TBD/TBR closures, number of requirement changes).
Interface Trends (percent ICD approval, TBD/TBR burn down, number of interface
requirement changes).
Verification Trends (closure burn down, number of deviations/waivers approved/open).
Review Trends (RID/RFA/Action Item burn down per review).
Software Unique Trends (number of requirements per build/release versus plan).
Problem Report/Discrepancy Report Trends (number open, number closed).
Cost Trends (Plan vs. actual, UFE, EVM).
Schedule Trends (critical path slack/float, critical milestone dates).
Staffing Trends (FTE/WYE plan vs. actual).
Technical Performance Measures (Mass margin, power margin).
Manufacturing Trends (Number of nonconformance/corrective actions (open/
closed/resolved)).
Additional project-specific indicators as needed.
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 120 of 147
NPR 7120.5F -- AppendixH Page 120 of 147
These indicators are further explained in the NASA Space Flight Program and Project Management
Handbook, NASA/SP-20220009501; the NASA Project Planning and Control Handbook,
NASA/SP-2016-3424; and the NASA Common Leading Indicators Detailed Reference Guide at
https://nodis3.gsfc.nasa.gov/OCE_rep/OCE_list.cfm.
Describe the approach to monitor and control the project's Agency Baseline Commitment (ABC).
Describe how the project will periodically report performance. Describe mitigation approach if the
project is exceeding the development cost documented in the ABC to take corrective action prior to
triggering the 30 percent breach threshold. Describe how the project will support a rebaseline review
in the event the Decision Authority directs one.
Describe the project’s implementation of Technical Authority (Engineering, Health and Medical,
and Safety and Mission Assurance).
Describe how the project will implement the SI and other systems of measurement and the
identification of units of measure in all product documentation. Where full implementation of the SI
system of measurement is not practical, hybrid configurations (i.e., a controlled mix of SI and
non-SI system elements) may be used to support maximum practical use of SI units for design,
development, and operations. Where hybrid configurations are used, describe the specific
requirements established to control interfaces between elements using different measurement
systems. (See NPR 7120.5, Section 3.7, for SI assessment timing requirement.)
Describe the project’s implementation of Earned Value Management (EVM) including:
How the PMB will be developed and maintained for the project and how UFE will be
established and controlled;
The methods the project will use to authorize the work and to communicate changes for the
scope, schedule, and budget of all suppliers; how the plan is updated as make-buy decisions
and agreements are made;
The process to be used by the project to communicate the time-phased levels of funding that
have been forecast to be made available to each supplier;
For the class of suppliers not required to use EVM, the schedule and resource information
required of the suppliers to establish and maintain a baseline and to quantify schedule and cost
variances; how contractor performance reports will be required; and
How the cost and schedule data from all partners/suppliers will be integrated to form a total
project-level assessment of cost and schedule performance.
Describe any additional specific tools necessary to implement the project’s control processes (e.g.,
the requirements management system, project scheduling system, project information management
systems, budgeting, and cost accounting system).
Describe the process for monitoring and controlling the IMS.
Describe the process for utilizing the project’s technical and schedule margins and UFE to meet the
Management and Commitment Baselines.
Describe how the project plans to report technical, schedule, and cost status to the program manager,
including the frequency and level of detail of reporting.
Describe the project’s internal processes for addressing technical waivers and deviations and
handling Formal Dissents.
Describe the project’s descope plans, including key decision dates and savings in cost and schedule,
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 121 of 147
NPR 7120.5F -- AppendixH Page 121 of 147
Describe the project’s descope plans, including key decision dates and savings in cost and schedule,
and show how the descopes are related to the project’s threshold performance requirements.
Include a description of the systems engineering organization and structure and how the Project
Chief Engineer (PCE) executes the overall systems engineering functions.
3.2 Safety and Mission Assurance Plan
Develop a project Safety and Mission Assurance (SMA) Plan as required by NPR 8705.2,
Human-Rating Requirements for Space Systems for crewed missions and NPR 8705.4, Risk
Classification for NASA Payloads for un-crewed missions and payloads.
The SMA Plan reflects a project life-cycle SMA process perspective, addressing areas including:
SMA domain management and SMA domain integration (e.g., for safety, reliability, maintainability,
quality, planetary protection, etc.) with other engineering and management functions (e.g., concept
and design trade-studies, risk analysis and risk assessments, risk-informed decision making, fault
tolerance and contingency planning, knowledge capture, hardware and software design assurance,
supply chain risk management and procurement, hardware and software design verification and test,
manufacturing process design and control, manufacturing and product quality assurance, system
verification and test, pre-flight verification and test, operations, maintenance, logistics planning,
maintainability and sustainability, operational reliability and availability, decommissioning, and
disposal).
Describe how the project will develop and manage a Closed-Loop Problem Reporting and
Resolution System. Describe how the project develops, tracks, and resolves problems. The process
should include a well-defined data collection system and process for hardware and software
problems and anomaly reports, problem analysis, and corrective action.
Identify the project’s approach to flow down requirements as appropriate to external developers and
suppliers in acquisitions (e.g., contracts and purchase orders).
Describe how the project will develop, evaluate, and report indications of SMA program maturity
and effectiveness at life cycle or other executive reviews, including through the use of metrics and
indicators that are not otherwise included in formal life-cycle review deliverables or are not
elements of the certification of flight readiness (COFR) process (e.g., satisfactory progress towards
human rating).
3.3 Risk Management Plan
Develop a Risk Management Plan that includes the content required by NPR 8000.4, Agency Risk
Management Procedural Requirements. Summarize how the project will implement a risk
management process (including risk-informed decision making (RIDM) and continuous risk
management (CRM) in accordance with NPR 8000.4, Agency Risk Management Procedural
Requirements). Include the initial Significant Risk List and appropriate actions to mitigate each risk.
Projects with international or other U.S. Government agency contributions need to plan for, assess,
and report on risks due to international or other government partners and plan for contingencies.
3.4 Acquisition Strategy
The project Acquisition Strategy is developed by the project manager, supported by the host
Center’s Procurement Officer, and needs to be consistent with NPD 1000.5, Policy for NASA
Acquisition, the results of the Agency strategic acquisition process, and the ASM. It documents an
integrated acquisition strategy that enables the project to meet its mission objectives and provides
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 122 of 147
NPR 7120.5F -- AppendixH Page 122 of 147
integrated acquisition strategy that enables the project to meet its mission objectives and provides
the best value to NASA. The Acquisition Strategy should include, but is not limited to, the
following:
Identify all major proposed acquisitions (such as engineering design study, hardware and software
development, mission and data operations support, and sustainment) in relation to the project WBS.
Provide summary information on each such proposed acquisition, including a Contract WBS; major
deliverable items; recommended type of procurement (competitive, AO for instruments); type of
contract (cost-reimbursable, fixed-price); source (institutional, contractor, other U.S. Government
agency, or international organization); procuring activity; and surveillance approach. Identify those
major procurements that require a PSM.
Describe completed or planned studies supporting make-or-buy decisions, considering NASA’s
in-house capabilities and the maintenance of NASA’s core competencies, as well as cost and best
overall value to NASA.
Describe the supply chain and identify potential critical and single-source suppliers needed to
design, develop, produce, support, and, if appropriate, restart an acquisition program or project. The
acquisition strategy should promote sufficient program/project stability to encourage industry to
invest, plan, and bear their share of risk. Describe the internal and external mechanisms and
procedures used to identify, monitor, and mitigate supply chain risks. Include data reporting
relationships to allow continuous surveillance of the supply chain that provides for timely
notification and mitigation of potential risks. Describe the process for reporting supply chain risks to
the program.
Identify the project’s approach to strengthen safety and mission assurance in contracts.
Describe all agreements, memoranda of understanding, barters, in-kind contributions, and other
arrangements for collaborative and/or cooperative relationships. Include partnerships created
through mechanisms other than those prescribed in the FAR and NFS. List all such agreements (the
configuration control numbers, the date signed or projected dates of approval, and associated record
requirements) necessary for project success. Include or reference all agreements concluded with the
authority of the project manager and reference agreements concluded with the authority of the
program manager and above. Include the following:
(1) NASA agreements (e.g., space communications, launch services, and inter-Center memoranda of
agreement).
(2) Non-NASA agreements:
(a) Domestic (e.g., U.S. Government agencies).
(b) International (e.g., memoranda of understanding).
Describe intellectual property considerations and goals for advanced technologies to protect core
NASA interests during the project life cycle; the process for respecting and protecting privately
developed intellectual property; the process for ensuring acquisition strategies, proposals, and
contract awards reflect intellectual property considerations established for the project; the approach
for ensuring that the intellectual property strategy promotes competition for post-production
sustainment/modernization contracts; the approach for seeking flexible and creative solutions to
intellectual property issues that meet the desires of the parties and reflect NASA’s investment; the
approach for ensuring procurement contracts specify both (1) the delivery of necessary technical
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 123 of 147
NPR 7120.5F -- AppendixH Page 123 of 147
data and computer software and (2) the license rights necessary for technical data and computer
software; and the approach for ensuring the delivery of technical data and computer software under
procurement contracts is marked in accordance with the contract at the time of delivery.
3.5 Technology Development Plan
Describe the technology assessment, development, management, and acquisition strategies
(including intellectual property considerations) needed to achieve the project’s mission objectives.
Describe how the project will assess its technology development requirements, including how the
project will evaluate the feasibility, availability, readiness, cost, risk, and benefit of the new
technologies. The approach should include timely reporting of new technologies to the Center
Technology Transfer Office and supporting technology transfer activities as described in NPR
7500.2, NASA Technology Transfer Requirements.
Describe how the project will identify opportunities for leveraging on-going technology efforts.
Describe how the project will transition technologies from the development stage to the
manufacturing and production phases. Identify the supply chain needed to manufacture the
technology and any costs and risks associated with the transition to the manufacturing and
production phases. Develop and document appropriate mitigation plans for the identified risks.
Describe the project’s strategy for ensuring that there are alternative development paths available
if/when technologies do not mature as expected. (Refer to NPR 7123.1 for TRL definitions and
SP-20205003605, Technology Readiness Assessment Best Practices Guide. The Technology
Readiness Assessment Best Practices Guide can be found in NODIS on the OCE tab under the
“Other NASA-Level Documents” menu.)
Describe how the project will remove technology gaps, including maturation, validation, and
insertion plans, performance measurement at quantifiable milestones, off-ramp decision gates, and
resources required.
Describe briefly how the project will ensure that all planned technology exchanges, contracts, and
partnership agreements comply with all laws and regulations regarding export control and the
transfer of sensitive and proprietary information.
Describe how the project will transition technologies from the development stage to manufacturing,
production, and insertion into the end system. Identify any potential costs and risks associated with
the transition to manufacturing, production, and insertion. Develop and document appropriate
mitigation plans for the identified risks.
3.6 Systems Engineering Management Plan
Develop a SEMP that includes the content required by NPR 7123.1, NASA Systems Engineering
Processes and Requirements. Include descriptions of the project’s overall approach for systems
engineering to include system design and product realization processes (implementation and/or
integration, verification and validation, and transition), as well as the technical management
processes.
3.7 System Security Plan
Identify and prepare a System Security Plan for each information system. The System Security Plan
is a formal document that provides an overview of the security requirements for an information
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 124 of 147
NPR 7120.5F -- AppendixH Page 124 of 147
system and describes the security controls in place or planned for meeting those requirements.
System Security Plans are generated and stored within the NASA Risk Information and Security
Compliance System (RISCS) at https://riscs-info.nasa.gov/. Multiple systems may be covered under
a single System Security Plan. Controls selected within the System Security Plan are included as
system requirements for the system or systems covered by the plan.
Document the project's approach to implementing cybersecurity requirements in accordance with
NPR 2810.1, Security of Information and Information Systems, if there are requirements outside the
scope of the System Security Plan(s).
3.8 Software Management Plan
Develop a Software Management Plan that includes the content required by NPR 7150.2, Software
Engineering Requirements. Additional information on the plan can be found in NASA-STD-8739.8,
Software Assurance and Software Safety Standard. Summarize how the project will develop and/or
manage the acquisition of software required to achieve project and mission objectives. The Software
Management Plan should be coordinated with the Systems Engineering Management Plan.
3.9 Verification and Validation Plan
Summarize the approach for performing verification and validation of the project products. Indicate
the methodology to be used in the verification/validation (test, analysis, inspection, or
demonstration), as defined in NPR 7123.1, NASA Systems Engineering Processes and
Requirements.
3.10 Review Plan
Summarize the project’s approach for conducting a series of reviews, including internal reviews and
project life-cycle reviews. In accordance with Center best practices, program review requirements,
and the requirements in NPR 7123.1, NASA Systems Engineering Processes and Requirements and
NPR 7120.5, NASA Space Flight Program and Project Management Requirements, provide the
names, purposes, content, and timing of the life-cycle reviews.
Identify any deviations from these documents that the project is planning or waivers that have been
granted, including tailoring to accommodate aspects of acquisition strategies. Provide the technical,
scientific, schedule, cost, and other criteria that will be utilized in the consideration of a Termination
Review.
For projects that plan continuing operations and production, including integration of capability
upgrades, with an unspecified Phase E end point, define the initial capability in the Review Plan for
KDP B if the initial capability is not the first operational mission flight.
For projects that are part of tightly coupled programs, project life-cycle reviews and KDPs should be
planned in accordance with the project life cycle and KDP sequencing guidelines in the Program
Plan. Document the sequencing of each project life-cycle review and KDP with respect to the
associated Program life-cycle review and KDP. In addition, document which project KDPs should
be conducted simultaneously with other projects’ KDPs and which project KDPs should be
conducted simultaneously with the associated program KDPs.
The sequencing of project life-cycle reviews and KDPs with respect to program life-cycle reviews
and KDPs is especially important for project PDR life-cycle reviews that precede KDP Cs. At KDP
C, the Agency makes project technical, cost, and schedule commitments to its external stakeholders
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 125 of 147
NPR 7120.5F -- AppendixH Page 125 of 147
at the established JCL in accordance with NPR 7120.5 requirements. Since changes to one project
can easily impact other projects’ technical, cost, schedule, and risk baselines, projects and their
program may need to proceed to KDP C/KDP I together.
3.11 Mission Operations Plan
Describe the activities required to perform the mission. Describe how the project will implement the
associated facilities, hardware, software, and procedures required to complete the mission. Describe
mission operations plans, rules, and constraints. Describe the Mission Operations System (MOS)
and Ground Data System (GDS) in the following terms:
MOS and GDS human resources and training requirements.
Procedures to ensure that operations are conducted in a reliable, consistent, and controlled
manner using lessons learned during the program and from previous programs.
Facilities requirements (offices, conference rooms, operations areas, simulators, and test beds).
Hardware (ground-based communications and computing hardware and associated
documentation).
Software (ground-based software and associated documentation).
3.12 NEPA Compliance Plan
Describe the level of NEPA analysis planned to comply with NPR 8580.1, Implementing the
National Environmental Policy Act, and Executive Order 12114. The NEPA Compliance Plan
should be prepared based on consultation with the appropriate NEPA manager (Center NEPA
Manager or Mission Direction NEPA Liaison) and describe the project’s NEPA strategy at all
affected Centers, including decisions regarding programmatic NEPA documents. Insert into the
project schedule the critical NEPA milestones if preparation of an Environmental Assessment or
Environmental Impact Statement is planned.
3.13 Integrated Logistics Support Plan
Describe how the project will implement NPD 7500.1, Program and Project Life-Cycle Logistics
Support Policy, including a maintenance and support concept; participation in the design process to
enhance supportability; supply support; maintenance and maintenance planning; packaging,
handling, and transportation; technical data and documentation; support and test equipment; training;
manpower and personnel for ILS functions; facilities required for ILS functions; and logistics
information systems for the life of the project.
3.14 Science Data Management Plan
Describe how the project will manage the scientific data generated and captured by the operational
mission(s) and any samples collected and returned for analysis. Include descriptions of how data will
be generated, processed, distributed, analyzed, and archived, as well as how any samples will be
collected, stored during the mission, and managed when returned to Earth. The Plan should include
definition of data rights and services and access to samples, as appropriate. Identify where the
preliminary science data requirements will be documented (these requirements should be
documented by SRR). The Plan should be developed in consultation with the Directorate data leads
and the Office of the Chief Information Officer (OCIO) early in the project life-cycle to ensure that
metadata standards and data formats are appropriately considered and that infrastructure and security
requirements are addressed.
Explain how the project will accomplish the information management and disposition in NPD
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 126 of 147
NPR 7120.5F -- AppendixH Page 126 of 147
2200.1, Management of NASA Scientific and Technical Information; NPR 2200.2, Requirements for
Documentation, Approval and Dissemination of Scientific and Technical Information; and NPR
1441.1, NASA Records Management Program Requirements, as applicable to project science data.
Explain how the project will implement NASA sample handling, curation, and planetary protection
directives and rules, including NPR 8715.24, Planetary Protection Provisions for Robotic
Extraterrestrial Missions.
3.15 Integration Plan
Prepare an integration plan that defines the configuration of expected aggregates of system elements
and the order of assembly of these aggregates to carry out efficient verification and validation
actions. The integration plan is structured to bring the elements together to assemble each subsystem
and to bring all the subsystems together to assemble the system/product. The primary purposes of the
integration plan are: (1) to describe this coordinated integration effort that supports the
implementation strategy, (2) to describe for the participants what needs to be done in each
integration step, and (3) to identify the required resources and when and where they will be needed.
3.16 Configuration Management Plan
Describe the configuration management (CM) approach that the project team will implement.
Describe the CM planning and management function including the CM organization and tools to be
used. Describe the methods and procedures to be used for configuration identification, configuration
control, interface management, configuration change management, configuration verification and
audit, and configuration status accounting and communications. Describe how CM will be audited
and how contractor CM processes will be integrated with the project. Configuration Management
should address hardware, software, and firmware. Additional information on configuration
management is provided in NPR 7123.1 and SAE/EIA 649, Standard for Configuration
Management.
3.17 Security Plan
Describe the project’s plans for ensuring security, including:
Security Requirements: Describe the project’s approach for planning and implementing the
requirements for physical, personnel, and industrial security and for security awareness/education
requirements in accordance with NPR 1600.1, NASA Security Program Procedural Requirements.
Emergency Response Requirements: Describe the project’s emergency response plan in accordance
with NPR 1040.1, NASA Continuity of Operations (COOP) Planning Procedural Requirements and
define the range and scope of potential crises and specific response actions, timing of notifications
and actions, and responsibilities of key individuals.
3.18 Project Protection Plan
Ensure that a Project Protection Plan is completed according to the schedule identified in product
maturities, as documented in Appendix I of NPR 7120.5. The Project Protection Plan is approved by
the Mission Directorate's designated approval authority, and the implementing Center's engineering
Technical Authority.
The Project Protection Plan assesses applicable adversarial threats to the project or system (including
support systems, development environments, and external resources), identifies system
susceptibilities, potential vulnerabilities, countermeasures, resilience strategies, and risk mitigations.
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 127 of 147
NPR 7120.5F -- AppendixH Page 127 of 147
The results inform the project or system’s design and concept of operations, in context with the
project’s or system’s requirements. The Project Protection Plan addresses NASA-STD-1006, Space
System Protection Standard, in accordance with NPR 1058.1, NASA Enterprise Protection Program,
and includes inputs from threat intelligence, candidate protection strategies provided by OCE, and
other applicable standards. The project team assesses adversarial threats with support from the
Office of Protective Services’ Intelligence Division and the Office of the Chief Engineer and
requires access to Classified National Security Information.
Since protection measures can be implemented either by designing the project’s or system’s
architecture to be more resilient or by enhancing the capabilities provided by institutional security
providers, it is important that the document identify to institutional security providers (both internal
and external to NASA) the critical nodes and single points-of-failure in the project or system. The
project System Security Plan (see Section 3.7 above) and Security Plan (see Section 3.17) should
address how institutional security measures are implemented on each project to protect its critical
nodes.
Risk scenarios emerging from the Project Protection Plan analysis are tracked in accordance with the
project's Risk Management Plan. (See Section 3.3 above.)
Project Protection Plans provide technical information on NASA space systems to specific
commands and agencies in the Department of Defense and Intelligence Community to assist those
organizations in providing timely support to NASA in the event of an incident involving a NASA
mission.
3.19 Technology Transfer (formerly Export) Control Plan
Describe how the project will implement the export control requirements specified in
NPR 2190.1, NASA Export Control Program.
3.20 Knowledge Management Plan
Describe the project’s approach to creating the knowledge management strategy and processes.
Strategy should include practices for identifying, capturing and transferring knowledge and
capturing and documenting lessons learned throughout the project life cycle as authorized in NPD
7120.4, NASA Engineering and Program/Project Management Policy and as described in NPD
7120.6, Knowledge Policy for Programs and Projects and other appropriate requirements and
standards documentation.
3.21 Human-Rating Certification Package
For human space flight missions, develop a Human-Rating Certification Package per NPR 8705.2,
Human-Rating Requirements for Space Systems. Human-rating certification focuses on the
integration of the human into the system, preventing catastrophic events during the mission, and
protecting the health and safety of humans involved in or exposed to space activities, specifically the
public, crew, passengers, and ground personnel.
3.22 Planetary Protection Plan
Prepare a plan that specifies management aspects of the planetary protection activities of the project.
Planetary protection encompasses: (1) the control of terrestrial microbial contamination associated
with space vehicles intended to land, orbit, flyby, or otherwise encounter extraterrestrial solar
system bodies, and (2) the control of contamination of the Earth by extraterrestrial material collected
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 128 of 147
NPR 7120.5F -- AppendixH Page 128 of 147
and returned by missions. The scope of the plan contents and level of detail will vary with each
project based upon the requirements in NASA policies NPR 8715.24, Planetary Protection
Provisions for Robotic Extraterrestrial Missions, and NPD 8020.7, Biological Contamination Control
for Outbound and Inbound Planetary Spacecraft.
3.23 Nuclear Launch Authorization Plan
Prepare a nuclear launch authorization plan for any U.S. space mission involving the use of
radioactive materials. Procedures and levels of review and analysis required for nuclear launch
authorization vary with the quantity of radioactive material planned for use and potential risk to the
general public and the environment. NPR 8715.26, Nuclear Flight Safety specifies the safety
guidelines for the launch of spacecraft containing space nuclear systems.
3.24 Range Safety Risk Management Process Documentation
Develop documentation that details a vehicle program’s Range Safety Risk Management process in
accordance with NPR 8715.5, Range Flight Safety Program. This applies to launch and entry vehicle
programs, scientific balloons, sounding rockets, drones and Unmanned Aircraft Systems. This does
not apply to programs developing a payload that will fly on board a vehicle. The range flight safety
concerns associated with a payload are addressed by the vehicle’s range flight safety process. The
focus is on the protection of the public, workforce, and property during range flight operations.
3.25 Payload Safety Process Deliverables
Develop the payload safety process deliverables in accordance with NPR 8715.7, Payload Safety
Program. This applies to NASA projects involving design, fabrication, testing, integration,
processing, launch, and recovery of payloads and the design of ground support equipment (GSE)
used to support payload-related operations during prelaunch operations and during recovery.
Included are items such as free-flying automated spacecraft, Space Launch System payloads, Space
Station payloads, expendable launch vehicle payloads, flight hardware and instruments designed to
conduct experiments, and payload support equipment. NASA-STD-8719.24, NASA Expendable
Launch Vehicle Payload Safety Requirements, provides more details on payload processing for
launch.
3.26 Communications Plan
Develop a Communications Plan in collaboration with the Associate Administrator for the Office of
Communications or their designee that identifies key project milestones that will be of interest to the
general public, the media, and other key stakeholders and plans to engage these audiences via audio
and real and/or near real-time high resolution video and/or imagery for each milestone including
during full mission operations. Summarize how these efforts will promote understanding of and
engagement with project objectives, elements, benefits, and contributions to overarching NASA
goals. In collaboration with the Associate Administrator for the Office of Communications or their
designee, identify resources and technical requirements for implementation of communications for
the general public, media, and other key stakeholders. (See the Communications Plan Template (on
the Web site for the Office of Communications,
http://communications.nasa.gov/content/nasa-comm-guidelines.)
3.27 Quality Assurance Surveillance Plan
Develop a consolidated set of detailed instructions for the performance of Government contract
quality assurance review and evaluation for the project. The plan might include contractor
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 129 of 147
NPR 7120.5F -- AppendixH Page 129 of 147
documents, data, and records; products and product attributes; processes; quality system
elements/attributes; and requirements related to quality data analysis, nonconformance reporting and
corrective action tracking/resolution, and final product acceptance. (See NASA-STD-8709.22,
Safety and Mission Assurance Acronyms, Abbreviations, and Definitions.)
3.28 Orbital Collision Avoidance Plan
Describe how the project implements the design considerations and preparation for operations to
avoid in-space collisions. The plan ensures the space flight mission meets the requirements of NPR
8079.1, NASA Spacecraft Conjunction Analysis and Collision Avoidance for Space Environment
Protection. Include in the plan a project overview including a concept of operation, how orbit
selection was performed, the spacecraft’s ascent and descent plan, how the spacecraft’s location
tracking data will be generated, and whether there will be any autonomous flight control. Discuss
how the spacecraft’s design will enable it to be acquired and tracked by the Space Surveillance
Network and be cataloged by the U.S. Space Command. Describe the process to routinely coordinate
with other operator(s) for maneuvering. Appendix D of the NPR provides a template for this plan.
(See NPR 8079.1, NASA Spacecraft Conjunction Analysis and Collision Avoidance for Space
Environment Protection for more detail and plan template.)
3.29 Human Systems Integration Approach
Develop a Human Systems Integration (HSI) approach in accordance with NPR 7123.1. (See the
NASA Human Systems Integration (HSI) Handbook, NASA/SP-20210010952, for additional
information.)
4.0 WAIVERS OR DEVIATIONS LOG
Identify NPR 7120.5 requirements for which a waiver or deviation has been requested and approved
consistent with project characteristics such as scope, complexity, visibility, cost, safety, and
acceptable risk, and provide rationale and approvals.
5.0 CHANGE LOG
Track and document changes to the Project Plan.
6.0 APPENDICES
Appendix A. Acronyms
Appendix B. Definitions
Appendix C. Compliance Matrix for this NPR
NPR 7120.5F -- AppendixH
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 130 of 147
NPR 7120.5F -- AppendixH Page 130 of 147
Appendix I. Program and Project Products by Phase
I.1 Product Owner and Requirement or Best Practice:
a. The Product Owner for each product is indicated in the column titled "Product Owner/Requirement or Best Practice."
b. Products listed in the I-Tables are either requirements or best practices.
c. “R” in the Product Owner/Requirement or Best Practice column indicates that a product is a requirement. Products that are requirements are included in the Compliance Matrix in Appendix C.
d. “BP” in the Product Owner/Requirement or Best Practice column indicates that the product is considered a best practice. The expectation is that the product will be developed in accordance with the I-Table as part of
normal program management activities.
I.2 For non-configuration-controlled documents, the following terms and definitions are used in tables I-1 through I-7:
a. “Initial” is applied to products that are continuously developed and updated as the program or project matures.
b. “Final” is applied to products that are expected to exist in this final form (e.g., minutes and final reports).
c. “Summary” is applied to products that synthesize the results of work accomplished.
d. “Plan” is applied to products that capture work to be performed in the following phases.
e. “Update” is applied to products that are expected to evolve as the formulation and implementation processes evolve. Only expected updates are indicated. However, any document may be updated as needed.
I.3 For configuration-controlled documents, the following terms and definitions are used in tables I-1 through I-7:
a. “Preliminary” is the documentation of information as it stabilizes but before it goes under configuration control. It is the initial development leading to a baseline. Some products will remain in a preliminary state for
multiple LCRs. The initial preliminary version is likely to be updated at subsequent LCRs but remains preliminary until baselined.
b. “Baseline” indicates putting the product under configuration control so that changes can be tracked, approved, and communicated to the team and any relevant stakeholders. The expectation on products labeled
“baseline” is that they will be at least final drafts going into the designated LCR and baselined coming out of the LCR. Baselining of products that will eventually become part of the Program or Project Plan indicates that the
product has the concurrence of stakeholders and is under configuration control. Updates to baselined documents require the same formal approval process as the original baseline.
c. “Approve” is used for a product, such as Concept Documentation, that is not expected to be put under classic configuration control but still requires that changes from the “Approved” version are documented at each
subsequent “Update.”
d. “Update” is applied to products that are expected to evolve as the formulation and implementation processes evolve. Only expected updates are indicated. However, any document may be updated as needed. Updates to
baselined documents require the same formal approval process as the original baseline.
I.4 Control Plans (Tables I-1 (Program Plan Control Plans), I-3, I-5, and I-7):
a. Control plans can either be part of the Program or Project Plan or separate stand-alone documents referenced in the appropriate part of the Program or Project Plan.
b. Considerations for determining if a control plan should be a stand-alone document include a requirement that the control plan be stand-alone in the NPR that requires the control plan; differences between when the control
plan is baselined and when the Program or Project Plan is baselined; how frequently the control plan will be updated since updates to the Program or Project Plan require signatures; and how long the control plan is.
c. When the control plan is a stand-alone document, the Program or Project Plan contains a reference to the stand-alone document.
1.5 Formats for Non-Control Plan I-Table Products
a. Unless a specific form, format, document, or document template is identified by the NPR that requires an I-Table product, the documentation format is flexible (e.g., LCR or KDP presentation charts or as part of a
document such as the Program or Project Plan).
Table I-1 Uncoupled and Loosely Coupled Program
Milestone Products and Control Plans Maturity Matrix
Products
Product
Owner/Requirement
or Best Practice
Pre-Formulation
Formulation Implementation
KDP I1 KDP II - n
SRR SDR PIR
1. FAD
[Required per
NPR 7120.5]
NASA AA/R Baseline
2. PCA
[Required per
NPR 7120.5]
NASA AA/R Preliminary Baseline
3. Program Plan
[Required per
NPR 7120.5]
NASA AA/R Preliminary Baseline Update
3.a. Mission
Directorate
requirements
and constraints
[Required per
NPR 7123.1]
OCE/R Baseline Update
3.b. Traceability
of program-level
requirements on
projects to the
Agency strategic
goals and
Mission
Directorate
requirements
and constraints
[Required per
NPR 7123.1]
OCE/R Preliminary Baseline
3.c.
Documentation
of driving
ground rules and
assumptions on
the program
[Required per
NPR 7120.5}
NASA AA/R Preliminary Baseline
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 131 of 147
NPR 7120.5F -- AppendixI Page 131 of 147
4. Interagency
and international
agreements
NASA AA/R Preliminary Baseline
5. ASM
Decision
Memorandum
[additional
information in
NPD 1000.5]
NASA AA/R Final
6. Risk
mitigation plans
and resources for
significant risks
[Required by
NPR 7120.5]
NASA AA/R Initial Update Update
7. Documented
Cost and
Schedule
Baselines
[Required per
NPR 7120.5]
OCFO-SID/R Preliminary Baseline Update
8.
Documentation
of Basis of
Estimate (cost
and schedule)
[Required per
NPR 7120.5]
OCFO-SID/R Preliminary Baseline Update
9.
Documentation
of performance
against
plan/baseline,
including
status/closure of
formal actions
from previous
KDP [Required
by NPR 7120.5]
NASA AA/R Summary Summary Summary
10. Industrial
Base and Supply
Chain Risk
Management
(SCRM)
Strategy and
Status [Required
per NPR 8735.2]
OSMA/R Preliminary Baseline Update
Program Plan
Control Plans
1. Technical,
Schedule, and
Cost Control
Plan [Required
per NPR 7120.5]
NASA AA/R Preliminary Baseline
2. Safety and
Mission
Assurance Plan
[Required per
NPRs 8705.2
and 8705.4]
OSMA/R Preliminary Baseline
3. Risk
Management
Plan [Required
per NPR 8000.4]
OSMA/R Preliminary Baseline
4. Acquisition
Strategy
[Required per
NPD 1000.5]
NASA AA/R Preliminary Baseline
5. Technology
Development
Plan [additional
information in
NPR 7500.2,
NPR 7123.1,
and NPR 7120.5]
OCE/BP Preliminary Baseline
6. Systems
Engineering
Management
Plan [Required
per NPR 7123.1]
OCE/R Preliminary Baseline
7. System
Security Plan
[Required per
NPR 2810.1]
OCIO/R Preliminary Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 132 of 147
NPR 7120.5F -- AppendixI Page 132 of 147
8. Review Plan
[Required per
NPR 7120.5]2
NASA AA/R Baseline Update
9. NEPA
Compliance Plan
[Required per
NPR 8580.1]
OSI-EMD/R Baseline
10.
Configuration
Management
Plan [Required
per NPR 7120.5;
additional
information in
NPR 7123.1 and
SAE/EIA 649]
OCE/R Baseline
11. Security Plan
[Required per
NPR 1040.1 and
NPR 1600.1]
OPS/R Baseline
12. Technology
Transfer
(formerly
Export) Control
Plan [Required
per NPR 2190.1]
OIIR/R Baseline
13.
Communications
Plan [additional
information in
NPR 7120.5]
OComm/BP Preliminary Baseline
14. Knowledge
Management
Plan [additional
information in
NPD 7120.4 and
NPD 7120.6]
OCE/BP Preliminary Baseline
15. Quality
Assurance
Surveillance
Plan [Required
per NPR 8735.2
and NASA FAR
Supplement part
1837.604]
OSMA/R Preliminary Baseline Update
1 If desired, the Decision Authority may request a KDP 0 be performed generally following SRR.
2 Review Plan should be baselined before the first review.
Table I-2 Tightly Coupled Program Milestone Products Maturity Matrix
Products
Product
Owner/Requirement
or Best Practice
Pre-
Formulation
Formulation Implementation
KDP 0 KDP I KDP II KDP III KDP n
SRR SDR PDR CDR SIR ORR MRR/FRR DR
1. FAD
[Required per
NPR 7120.5]
NASA AA/R Baseline
2. PCA
[Required per
NPR 7120.5]
NASA AA/R Preliminary Baseline
3. Program
Plan [Required
per NPR
7120.5]
NASA AA/R Preliminary Baseline Update Update Update Update Update Update
3.a. Mission
Directorate
requirements
and constraints
[Required per
NPR 7123.1]
OCE/R Baseline Update Update
3.b.
Traceability of
program-level
requirements
on projects to
the Agency
strategic goals
and Mission
Directorate
requirements
and constraints
[Required per
NPR 7123.1]
OCE/R Preliminary Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 133 of 147
NPR 7120.5F -- AppendixI Page 133 of 147
3.c.
Documentation
of driving
ground rules
and
assumptions on
the program
[Required per
NPR 7120.5]
NASA AA/R Preliminary Baseline Update Update Update
4. Interagency
and
international
agreements
NASA AA/R Preliminary Baseline Update
5. ASM
Decision
Memorandum
[additional
information in
NPD 1000.5]
NASA AA/R Final
6. Risk
mitigation
plans and
resources for
significant
risks [Required
by NPR
7120.5]
NASA AA/R Initial Update Update Update Update Update Update Update
7. Documented
Cost and
Schedule
Baselines
[Required per
NPR 7120.5]
OCFO-SID/R Preliminary Preliminary Baseline Update Update Update Update Update
8.
Documentation
of Basis of
Estimate (cost
and schedule)
[Required per
NPR 7120.5]
OCFO-SID/R Preliminary Preliminary Baseline Update Update Update Update Update
9. CADRe
[Required by
NPR 7120.5]
OCFO-SID/R Baseline Update Update Update Update
Update1
Update
10. Shared
Infrastructure2,
Staffing, and
Scarce Material
Requirements
and Plans
NASA AA/R Initial Update Update Update
11.
Documentation
of performance
against
plan/baseline,
including
status/closure
of formal
actions from
previous KDP
[Required by
NPR 7120.5]
NASA AA/R Summary Summary Summary Summary Summary Summary Summary
12. Industrial
Base and
Supply Chain
Risk
Management
(SCRM)
Strategy and
Status
[Required per
NPR 8735.2]
OSMA/R Preliminary Baseline Update Update
1 The CADRe for MRR/FRR is considered the “Launch CADRe” to be completed after the launch.
2 Shared infrastructure includes facilities that are required by more than one of the program’s projects.
Table I-3 Tightly Coupled Program Plan Control Plans Maturity Matrix
(See Appendix G
Template for Control
Plan Details.)
Product
Owner/Requirement or
Best Practice
Formulation Implementation
KDP 0 KDP I KDP II KDP III KDP n
SRR SDR PDR CDR SIR ORR MRR/FRR DR
1. Technical, Schedule,
and Cost Control Plan
[Required per NPR
7120.5]
NASA AA/R Preliminary Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 134 of 147
NPR 7120.5F -- AppendixI Page 134 of 147
2. Safety and Mission
Assurance Plan
[Required per NPRs
8705.2 and 8705.4]
OSMA/R Preliminary Baseline Update Update
Update
(SMSR)
3. Risk Management
Plan [Required per NPR
8000.4]
OSMA/R Preliminary Baseline Update
4. Acquisition Strategy
[Required per NPD
1000.5]
NASA AA/R
Preliminary
Strategy
Baseline Update
5. Technology
Development Plan
[additional information
in NPR 7500.2, NPR
7123.1, and NPR
7120.5]
OCE/BP Preliminary Baseline Update
6. Systems Engineering
Management Plan
[Required per NPR
7123.1]
OCE/R Preliminary Baseline
7. Verification and
Validation Plan
[Required per NPR
7120.5, additional
information in NPR
7123.1]
OCE/R Preliminary Baseline Update Update
8. System Security Plan
[Required per NPR
2810.1]
OCIO/R Preliminary Update Baseline Update Update
9. Review Plan
[Required per NPR
7120.5]1
NASA AA/R Baseline Update Update
10. Mission Operations
Plan [Required per NPR
7120.5]
OCE/R Preliminary Baseline Update
11. NEPA Compliance
Plan [Required per NPR
8580.1]
OSI-EMD/R Preliminary Baseline Update
12. Integrated Logistics
Support Plan [Required
per NPD 7500.1]
OSI-LMD/R Preliminary Baseline Update
13. Science Data
Management Plan
[additional information
in NPD 2200.1 and
NPRs 2200.2, 1441.1,
and 8715.24]
SMD/BP
Preliminary
Science Data
Requirements
Preliminary Baseline Update
14. Configuration
Management Plan
[Required per NPR
7120.5; additional
information in NPR
7123.1 and SAE/EIA
649]
OCE/R Preliminary Baseline Update
15. Security Plan
[Required per NPR
1040.1 and NPR 1600.1]
OPS/R Preliminary Baseline
Update
Annually
16. Technology Transfer
(formerly Export)
Control Plan [Required
per NPR 2190.1]
OIIR/R Preliminary Baseline Update
17. Communications
Plan [additional
information in NPR
7120.5]
OComm/BP Preliminary Baseline Update Update
18. Knowledge
Management Plan
[additional information
in NPD 7120.4 and
NPD 7120.6]
OCE/BP Preliminary Baseline Update Update
19. Human-Rating
Certification Package
[Required per NPR
8705.2]
OSMA/R Initial Update Update Update Update
Approve
Certification
20. Quality Assurance
Surveillance Plan
[Required per NPR
8735.2 and NASA FAR
Supplement part
1837.604]
OSMA/R Preliminary Baseline Update Update Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 135 of 147
NPR 7120.5F -- AppendixI Page 135 of 147
21. Orbital Collision
Avoidance Plan
[Required per NPR
8079.1]
OCE/R Baseline Update
22. Human Systems
Integration Approach
[additional information
in
NASA/SP-20210010952
NASA HSI Handbook
and NPR 7123.1]
OCE-OSMA-OCHMO/R Baseline Update Update Update
1 Review Plan should be baselined before the first review.
Table I-4 Project Milestone Products Maturity Matrix
Products
Product
Owner/
Requirement
or Best
Practice
Pre-Phase A
KDP A
Phase A
KDP B
Phase B
KDP C
Phase C
KDP D
Phase D
KDP E
Phase E
KDP F
Phase F
MCR SRR SDR/MDR PDR CDR SIR ORR MRR/FRR DR DRR
Headquarters and Program Products1
1. FAD [Required per NPR
7120.5]
NASA AA/R Baseline
2. Program Plan [Required
per NPR 7120.5]
NASA AA/R Baseline
2.a. Applicable Agency
strategic goals [Required
per NPR 7123.1]
NASA AA/R Baseline Update Update
2.b. Documentation of
program-level requirements
and constraints on the
project (from the Program
Plan) and stakeholder
expectations, including
mission objectives/goals
and mission success criteria
[Required per NPR
7123.1]
OCE/R Preliminary Baseline Update Update
2.c. Documentation of
driving mission, technical,
and programmatic ground
rules and assumptions
[Required per NPR 7120.5]
NASA AA/R Preliminary Preliminary Baseline Update Update Update
3. Partnerships and
interagency and
international agreements
NASA AA/R Preliminary Update
Baseline U.S.
partnerships
and
agreements
Baseline
international
agreements
4. ASM Decision
Memorandum [additional
information in NPD 1000.5]
NASA AA/R Final
5. Mishap Preparedness
and Contingency Plan
[Required per NPR 8621.1]
OSMA/R Preliminary Update
Baseline
(SMSR)
Update Update
Project Technical Products
2
1. Concept Documentation
[Required per NPR 7123.1]
OCE/R Approve Update Update Update
2. Mission, Spacecraft,
Ground, and Payload
Architectures [Required per
NPR 7123.1]
OCE/R
Preliminary
mission and
spacecraft
architecture(s)
with key
drivers
Baseline
mission and
spacecraft
architecture,
preliminary
ground and
payload
architectures.
Classify
payload(s)
by risk per
NPR 8705.4.
Update
mission and
spacecraft
architecture,
baseline
ground and
payload
architectures
Update
mission,
spacecraft,
ground and
payload
architectures
3. Project-Level, System,
and Subsystem
Requirements [Required
per NPR 7123.1]
OCE/R
Preliminary
project-level
requirements
Baseline
project-level
and
system-level
requirements
Update
Project-level
and
system-level
requirements,
Preliminary
subsystem
requirements
Update
project-level
and
system-level
requirements.
Baseline
subsystem
requirements
4. Design Documentation
[Required per NPR 7123.1]
OCE/R Preliminary Baseline Update Update
5. Operations Concept
Documentation [Required
per NPR 7120.5]
OCE/R Preliminary Preliminary Preliminary Baseline
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 136 of 147
NPR 7120.5F -- AppendixI Page 136 of 147
6. Technology Readiness
Assessment Documentation
[Required per NPR 7120.5
Appendix F FA Template]
OCE/R Initial Update Update Update Update
7. Engineering
Development Assessment
Documentation [Required
per NPR 7120.5 Appendix
F FA Template]
OCE/R Initial Update Update Update
8. Heritage Assessment
Documentation [Required
per NPR 7120.5 Appendix
F FA Template]
OCE/R Initial Update Update Update
9. Systems Safety Analyses
(e.g., safety data packages)
[Baseline at CDR]
[Required per NPR 8715.3]
OSMA/R Preliminary Baseline Update Update Update
10. Payload Safety Process
Deliverables [Required per
NPR 8715.7]
OSMA/R Preliminary Preliminary Baseline
11. Verification and
Validation Report
[Required per NPR 7123.1]
OCE/R Prelim-inary Baseline
12. Operations Handbook
[additional information in
NPR 7120.5 Appendix A]
OCE/R Preliminary Baseline Update Update
13. Orbital Debris
Assessment [Required per
NPR 8715.6; additional
information in
NASA-STD-8719.14]
OSMA/R
Initial
Assessment
Preliminary
design ODAR
Detailed
design
ODAR
Final
ODAR
(SMSR)
14. End of Mission Plans
[Required per NPR 8715.6;
additional information in
NASA-STD-8719.14, App
B]
OSMA/R
Baseline
(SMSR)
Update
per
8715.6
Update
15. Final Mission Report
[additional information in
NPR 7120.5 Appendix A]
OCE/BP Final
16.
Decommissioning/Disposal
Plan [Required per NPR
7123.1]
OCE/R Baseline Update
Update
Dispos-al
portions
17. Industrial Base and
Supply Chain Risk
Management (SCRM)
Strategy and Status
[Required per NPR 8735.2]
OSMA/R Preliminary Update Update Baseline Update
18. Criticality
Identification Method for
Hardware [Required per
NPR 8735.2]
OSMA/R Preliminary Update Update Baseline Update
19. Hardware Quality Data
Management Analytics
[additional information in
NPR 8735.2]
OSMA/BP Preliminary Update Update Baseline Update Update Update Update
Project Management, Planning, and Control Products
1. Formulation Agreement
[Required per NPR 7120.5]
NASA AA/R
Baseline for
Phase A;
Preliminary
for Phase B
Baseline for
Phase B
2. Project Plan [Required
per NPR 7120.5]
NASA AA/R Preliminary Baseline
3. Documentation of
performance against
Formulation Agreement
(see #1 above) or against
plans for work to be
accomplished during
Implementation life-cycle
phase, including
performance against
baselines and status/closure
of formal actions from
previous KDP [Required
by NPR 7120.5]
NASA AA/R Summary Summary Summary Summary Summary Summary Summary Summary
4.Project Baselines
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 137 of 147
NPR 7120.5F -- AppendixI Page 137 of 147
4.a. Top technical, cost,
schedule and safety risks,
risk mitigation plans, and
associated resources
[Required by NPR 7120.5]
NASA AA/R Initial Update Update Update Update Update Update Update Update Update
4.b. Staffing requirements
and plans [Required by
NPR 7120.5]
NASA AA/R Initial Update Update Update Update Update
4.c.i Infrastructure
requirements and plans
[Required per NPR 9250.1,
NPD 8800.14 and NPR
8820.2]
Business case analysis for
infrastructure [Required per
NPR 8800.15.]
OSI-FRED/R Initial Update Update Update Update
4.c.ii Capitalization
Determination Form (CDF)
(NASA Form 1739)
[Required per NPR 9250.1]
OCFO/R Initial Update Update Update Update
4.d. Schedule [Required per
NPR 7120.5]
OCFO-SID/R
Risk informed
at project
level with
preliminary
Phase D
completion
ranges
Risk
informed at
system level
with
preliminary
Phase D
completion
ranges
Risk informed
at subsystem
level with
preliminary
Phase D
completion
ranges or high
and low
schedule
values with
JCL 3.
Preliminary
Integrated
Master
Schedule
Risk informed
and cost-
loaded.
Baseline
Integrated
Master
Schedule
Update
IMS
Update
IMS
Update IMS
Update
IMS
Update
IMS
Update
IMS
4.e. Cost Estimate
[Required per NPR 7120.5]
OCFO-SID/R
Preliminary
Range
estimate
Update
Risk-informed
range estimate
or high and
low-cost
values with
JCL 3
Risk-informed
Baseline
Update Update Update Update Update Update
4.f. Basis of Estimate (cost
and schedule) [Required per
NPR 7120.5]
OCFO-SID/R
Initial (for
range)
Update (for
range)
Update (for
range or high
and low
values with
JCL3)
Update for
cost and
schedule
estimate
Update Update Update Update Update Update
4.g. Confidence Level(s)
and supporting
documentation [Required
per NPR 7120.5]
OCFO-SID/R
Preliminary
cost
confidence
level and
preliminary
schedule
confidence
level or JCL 3
Baseline Joint
Cost and
Schedule
Confidence
Level
Update4 Update5
4.h. External Cost and
Schedule Commitments
[Required per NPR 7120.5]
OCFO-SID/R
Preliminary
for ranges or
high and low
values with
JCL 3
Baseline
4.i. CADRe [Required per
NPR 7120.5]
OCFO-SID/R Baseline Update Update Update Update Update6 Update
4.j PMB [Required per
NPR 7120.5 and NASA
EVM Capability Process
Documentation]
OCFO-SID/R Baseline Update Update Update Update
1 These products are developed by the Mission Directorate.
2 These document the work of the key technical activities performed in the associated phases.
3 Projects with LCC or initial capability cost of $1B or over develop high and low values for cost and schedule with the corresponding JCL values at KDP B per Section 2.4.3.1.a.
4 Projects with LCC or initial capability cost of $1B or over update the JCL at CDR per Section 2.4.3.3.
5 Projects with LCC or initial capability cost of $1B or over update the JCL at KDP D per Section 2.4.3.4 if current development costs exceed development ABC cost by 5 percent or more.
6 The CADRe for MRR/FRR is considered the “Launch CADRe” to be completed after the launch.
Table I-5 Project Plan Control Plans Maturity Matrix
(See Appendix H
Template for Control
Plan Details.)
Product
Owner/Requirement or
Best Practice
Pre-Phase
A
Phase A
KDP B
Phase B
KDP C
Phase C
KDP D
Phase D
KDP E
Phase
E KDP
F
MCR SRR SDR/MDR PDR CDR SIR ORR MRR/ FRR DR
1. Technical, Schedule,
and Cost Control Plan
[Required per NPR
7120.5]
NASA AA/R
Approach
for
managing
schedule
and cost
during
Phase A1
Preliminary Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 138 of 147
NPR 7120.5F -- AppendixI Page 138 of 147
2. Safety and Mission
Assurance Plan
[Required per NPRs
8705.2 and 8705.4]
OSMA/R Baseline Update Update Update
Update
(SMSR)
Update
3. Risk Management
Plan [Required per NPR
8000.4]
OSMA/R
Approach
for
managing
risks during
Phase A 1
Baseline Update Update
4. Acquisition Strategy
[Required per NPD
1000.5]
NASA AA/R
Preliminary
Strategy
Baseline Update Update
5. Technology
Development Plan (may
be part of Formulation
Agreement) [additional
information in NPR
7500.2, NPR 7123.1,
and NPR 7120.5]
OCE/BP Baseline Update Update Update
6. Systems Engineering
Management Plan
[Required per NPR
7123.1]
OCE/R Preliminary Baseline Update Update
7. System Security Plan
[Required per NPR
2810.1]
OCIO/R Preliminary Update Baseline Update Update
8. Software
Management Plan(s)
[Required per NPR
7150.2; additional
information in
NASA-STD-8739.8]
OCE/R Preliminary Baseline Update
9. Verification and
Validation Plan
[Required per NPR
7120.5, additional
information in NPR
7123.1]
OCE/R
Preliminary
Approach2
Preliminary Baseline Update Update
10. Review Plan
[Required per NPR
7120.5]3
NASA AA/R Preliminary Baseline Update Update
11. Mission Operations
Plan [Required per NPR
7120.5]
OCE/R Preliminary Baseline Update
12. NEPA Compliance
Plan [Required per NPR
8580.1]
OSI-EMD/R Baseline
13. Integrated Logistics
Support Plan [Required
per NPD 7500.1]
OSI-LMD/R
Approach
for
managing
logistics 2
Preliminary Preliminary Baseline Update
14. Science Data
Management Plan
[additional information
in NPD 2200.1 and
NPRs 2200.2, 1441.1,
and 8715.24]
SMD/BP
Preliminary
Science Data
Requirements
Preliminary Baseline Update
15. Integration Plan
[Required per NPR
7120.5]
OCE/R
Preliminary
approach2
Preliminary Baseline Update
16. Configuration
Management Plan
[Required per NPR
7120.5; additional
information in NPR
7123.1 and SAE/EIA
649]
OCE/R Baseline Update Update
17. Security Plan
[Required per NPR
1040.1 and NPR 1600.1]
OPS/R Preliminary Baseline
Update
annually
18. Project Protection
Plan [Required per NPR
1058.1, additional
information in
NASA-STD-1006]
OCE/R Preliminary Baseline Update Update Update Update
Update
annually
19. Technology Transfer
(formerly Export)
Control Plan [Required
per NPR 2190.1]
OIIR/R Preliminary Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 139 of 147
NPR 7120.5F -- AppendixI Page 139 of 147
20. Knowledge
Management Plan
[additional information
in NPD 7120.4 and
NPD 7120.6]
OCE/BP
Approach
for
managing
during
Phase A 1
Preliminary Baseline Update
21. Human-Rating
Certification Package
[Required per NPR
8705.2]
OSMA/R
Preliminary
approach2
Initial Update Update Update Update
Approve
Certification
22. Planetary Protection
Plan [Required per NPD
8020.7 and NPR
8715.24]
OSMA/R
Planetary
Protection
Categorization
(if applicable)
Baseline
23. Nuclear Launch
Authorization Plan
[additional information
in NPR 8715.26]
OSMA/R
Baseline
(mission has
nuclear
materials)
24. Range Safety Risk
Management Process
Documentation
[Required per NPR
8715.5]
OSMA/R Preliminary Preliminary Baseline
25. Communications
Plan [additional
information in NPR
7120.5]
OComm/BP Preliminary Baseline Update Update
26. Quality Assurance
Surveillance Plan
[Required per NPR
8735.2 and NASA FAR
Supplement part
1837.604]
OSMA/R Preliminary Baseline Update Update Update
27. Orbital Collision
Avoidance Plan
[Required per NPR
8079.1]
OCE/R Baseline Update
28. Human Systems
Integration Approach
[additional information
in
NASA/SP-20210010952
NASA HSI Handbook
and NPR 7123.1]
OCE-OSMA-OCHMO/R Preliminary Baseline Update Update Update
1 Not the Plan, but documentation of high-level process. May be documented in MCR briefing package.
2 Not the Plan, but documentation of considerations that might impact the cost and schedule baselines. May be documented in MCR briefing package.
3 Review Plan should be baselined before the first review.
Table I-6 Single-Project Program Milestone Products Maturity Matrix
Products
Product
Owner/Requirement
or Best Practice
Pre-Phase A
KDP A
Phase A
KDP B
Phase B
KDP C
Phase C
KDP D
Phase D
KDP E
Phase E
KDP F
Phase F
MCR SRR SDR/MDR PDR CDR SIR ORR MRR/FRR DR DRR
Headquarters Products
1
1. FAD [Required per NPR
7120.5]
NASA AA/R Baseline
2. PCA [Required per NPR
7120.5]
NASA AA/R Preliminary Baseline
3. Traceability of Agency
strategic goals and Mission
Directorate requirements
and constraints to
program/project-level
requirements and
constraints. [Required per
NPR 7123.1]
OCE/R Preliminary Baseline Update Update
4. Documentation of
driving mission, technical,
and programmatic ground
rules and assumptions
[Required per NPR 7120.5]
NASA AA/R Preliminary Preliminary Baseline Update Update Update
5. Partnerships and
inter-agency and
international agreements
NASA AA/R Preliminary Update
Baseline U.S.
partnerships
and
agreements
Baseline
international
agreements
6. ASM Decision
Memorandum [additional
information in NPD 1000.5]
NASA AA/R Final
7. Mishap Preparedness
and Contingency Plan
[Required per NPR 8621.1]
OSMA/R Preliminary Update
Baseline
(SMSR)
Update Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 140 of 147
NPR 7120.5F -- AppendixI Page 140 of 147
Single-Project Program Technical Products
2
1. Concept Documentation
[Required per NPR 7123.1]
OCE/R Approve Update Update Update
2. Mission, Spacecraft,
Ground, and Payload
Architectures [Required per
NPR 7123.1]
OCE/R
Preliminary
mission and
spacecraft
architecture(s)
with key
drivers
Baseline
mission and
spacecraft
architecture,
preliminary
ground and
payload
architectures.
Classify
payload(s)
by risk per
NPR 8705.4.
Update
mission and
spacecraft
architecture,
baseline
ground and
payload
architectures
Update
mission,
spacecraft,
ground, and
payload
architectures
3. Project-Level, System,
and Subsystem
Requirements [Required
per NPR 7123.1]
OCE/R
Preliminary
project-level
requirements
Baseline
project-level
and
system-level
requirements
Update
Project-level
and
system-level
requirements,
Preliminary
subsystem
requirements
Update
project-level
and
system-level
requirements.
Baseline
subsystem
requirements
4. Design Documentation
[Required per NPR 7123.1]
OCE/R Preliminary Baseline Update Update
5. Operations Concept
Documentation [Required
per NPR 7120.5]
OCE/R Preliminary Preliminary Preliminary Baseline
6. Technology Readiness
Assessment Documentation
[Required per NPR 7120.5
Appendix F FA Template]
OCE/R Initial Update Update Update Update
7. Engineering
Development Assessment
Documentation [Required
per NPR 7120.5 Appendix
F FA Template]
OCE/R Initial Update Update Update
8. Heritage Assessment
Documentation [Required
per NPR 7120.5 Appendix
F FA Template]
OCE/R Initial Update Update Update
9. Systems Safety Analyses
(e.g., safety data packages)
[Baseline at CDR]
[Required per NPR 8715.3]
OSMA/R Preliminary Baseline Update Update Update
10. Payload Safety Process
Deliverables [Required per
NPR 8715.7]
OSMA/R Preliminary Preliminary Baseline
11. Verification and
Validation Report
[Required per NPR 7123.1]
OCE/R Prelim-inary Baseline
12. Operations Handbook
[additional information in
NPR 7120.5 Appendix A]
OCE/R Preliminary Baseline Update Update
13. Orbital Debris
Assessment [Required per
NPR 8715.6; additional
information in
NASA-STD-8719.14]
OSMA/R
Initial
Assessment
Preliminary
design ODAR
Detailed
design
ODAR
Final
ODAR
(SMSR)
14. End of Mission Plans
[Required per NPR 8715.6;
additional information in
NASA-STD-8719.14, App
B]
OSMA/R
Baseline
(SMSR)
Update
per
8715.6
Update
15. Final Mission Report
[additional information in
NPR 7120.5 Appendix A]
OCE/BP Final
16.
Decommissioning/Disposal
Plan [Required per NPR
7123.1]
OCE/R Baseline Update
Update
disposal
portions
17. Industrial Base and
Supply Chain Risk
Management (SCRM)
Strategy and Status
[Required per NPR 8735.2]
OSMA/R Preliminary Update Update Baseline Update
18. Criticality
Identification Method for
Hardware [Required per
NPR 8735.2]
OSMA/R Preliminary Update Update Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 141 of 147
NPR 7120.5F -- AppendixI Page 141 of 147
19. Hardware Quality Data
Management Analytics
[additional information in
NPR 8735.2]
OSMA/BP Preliminary Update Update Baseline Update Update Update Update
Single-Project Program Management, Planning, and Control Products
1. Formulation Agreement
[Required per NPR 7120.5]
NASA AA/R
Baseline for
Phase A;
Preliminary
for Phase B
Baseline for
Phase B
2. Program Plan [Required
per NPR 7120.5] 3
NASA AA/R Preliminary Baseline
3. Project Plan [Required
per NPR 7120.5] 3
NASA AA/R Preliminary Baseline
4. Documentation of
performance against
Formulation Agreement
(see #1 above) or against
plans for work to be
accomplished during
Implementation life-cycle
phase, including
performance against
baselines and status/closure
of formal actions from
previous KDP [Required
per NPR 7120.5]
NASA AA/R Summary Summary Summary Summary Summary Summary Summary Summary
5.Project Baselines
5.a. Top technical, cost,
schedule and safety risks,
risk mitigation plans, and
associated resources
[Required per NPR 7120.5]
NASA AA/R Initial Update Update Update Update Update Update Update Update Update
5.b. Staffing requirements
and plans [Required by
NPR 7120.5]
NASA AA/R Initial Update Update Update Update Update
5.c.i. Infrastructure
requirements and plans
[Required per NPR 9250.1,
NPD 8800.14, and NPR
8820.2]
Business case analysis for
infrastructure [Required per
NPR 8800.15.]
OSI-FRED/R Initial Update Update Update Update
5.c.ii Capitalization
Determination Form (CDF)
(NASA Form 1739)
[Required per NPR 9250.1]
OCFO/R Initial Update Update Update Update
5.d. Schedule [Required per
NPR 7120.5]
OCFO-SID/R
Risk informed
at project
level with
preliminary
Phase D
completion
ranges
Risk
informed at
system level
with
preliminary
Phase D
completion
ranges
Risk informed
at subsystem
level with
preliminary
Phase D
completion
ranges or high
and low
schedule
values with
JCL. 4
Prelim-inary
IMS
Risk informed
and cost-
loaded.
Baseline
Integrated
Master
Schedule
Update
IMS
Update
IMS
Update IMS
Update
IMS
Update
IMS
Update
IMS
5.e. Cost Estimate
[Required per NPR 7120.5]
OCFO-SID/R
Preliminary
Range
estimate
Update
Risk-informed
range estimate
or high and
low-cost
values with
JCL 4
Risk-informed
baseline
Update Update Update Update Update Update
5.f. Basis of Estimate (cost
and schedule) [Required per
NPR 7120.5]
OCFO-SID/R
Initial (for
range)
Update (for
range)
Update (for
range or high
and low
values with
JCL4)
Update for
cost and
schedule
estimate
Update Update Update Update Update Update
5.g. Confidence Level(s)
and supporting
documentation [Required
per NPR 7120.5]
OCFO-SID/R
Preliminary
cost
confidence
level and
preliminary
schedule
confidence
level or JCL 4
Baseline
Joint Cost and
Schedule
Confidence
Level
Update5 Update6
5.h. External Cost and
Schedule Commitments
[Required per NPR 7120.5]
OCFO-SID/R
Preliminary
for ranges or
JCL 4
Baseline
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 142 of 147
NPR 7120.5F -- AppendixI Page 142 of 147
5.i. CADRe [Required per
NPR 7120.5]
OCFO-SID/R Baseline Update Update Update Update Update7 Update
5.j. PMB [Required per
NPR 7120.5 and NASA
EVM Capability Process
Documentation]
OCFO-SID/R Baseline Update Update Update Update
1 These products are developed by the Mission Directorate.
2 These document the work of the key technical activities performed in the associated phases.
3 The Program Plan and Project Plans may be combined with the approval of the MDAA.
4 Single-project programs with LCC or initial capability cost of $1B or over develop high and low values for cost and schedule with corresponding JCL values at KDP B per Section 2.4.3.1.a.
5 Single-project programs with LCC or initial capability cost of $1B or over update the JCL at CDR per Section 2.4.3.3.
6 Projects with LCC or initial capability cost of $1B or over update the JCL at KDP D per Section 2.4.3.4 if current development costs exceed development ABC cost by 5 percent or more.
7 The CADRe for MRR/FRR is considered the “Launch CADRe” to be completed after the launch.
Table I-7 Single-Project Program Plan Control Plans Maturity Matrix
(See Templates in
Appendices G and H
for Control Plan
Details)
Product
Owner/Requirement or
Best Practice
Pre-Phase
A
Phase A
KDP B
Phase B
KDP C
Phase C
KDP D
Phase D
KDP E
Phase
E
KDP F
MCR SRR SDR/MDR PDR CDR SIR ORR MRR/ FRR DR
1. Technical, Schedule,
and Cost Control Plan
[Required per NPR
7120.5]
NASA AA/R
Approach
for
managing
schedule
and cost
during
Phase A 1
Preliminary Baseline Update
2. Safety and Mission
Assurance Plan
[Required per NPRs
8705.2 and 8705.4]
OSMA/R Baseline Update Update Update
Update
(SMSR)
Update
3. Risk Management
Plan [Required per NPR
8000.4]
OSMA/R
Approach
for
managing
risks during
Phase A 1
Baseline Update Update
4. Acquisition Strategy
[Required per NPD
1000.5]
NASA AA/R
Preliminary
Strategy
Baseline Update Update
5. Technology
Development Plan (may
be part of Formulation
Agreement) [additional
information in NPR
7500.2, NPR 7123.1,
and NPR 7120.5]
OCE/BP Baseline Update Update Update
6. Systems Engineering
Management Plan
[Required per NPR
7123.1]
OCE/R Preliminary Baseline Update Update
7. System Security Plan
[Required per NPR
2810.1]
OCIO/R Preliminary Update Baseline Update Update
8. Software
Management Plan(s)
[Required per NPR
7150.2; additional
information in
NASA-STD-8739.8]
OCE/R Preliminary Baseline Update
9. Verification and
Validation Plan
[Required per NPR
7120.5, additional
information in NPR
7123.1]
OCE/R
Preliminary
Approach2
Preliminary Baseline Update Update
10. Review Plan
[Required per NPR
7120.5]3
NASA AA/R Preliminary Baseline Update Update
11. Mission Operations
Plan [Required per NPR
7120.5]
OCE/R Preliminary Baseline Update
12. NEPA Compliance
Plan [Required per NPR
8580.1]
OSI-EMD/R Baseline
13. Integrated Logistics
Support Plan [Required
per NPD 7500.1]
OSI-LMD/R
Approach
for
managing
logistics 2
Preliminary Preliminary Baseline Update
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 143 of 147
NPR 7120.5F -- AppendixI Page 143 of 147
14. Science Data
Management Plan
[additional information
in NPD 2200.1 and
NPRs 2200.2, 1441.1,
and 8715.24]
SMD/BP
Preliminary
Science Data
Requirements
Preliminary Baseline Update
15. Integration Plan
[Required per NPR
7120.5]
OCE/R
Preliminary
approach2
Preliminary Baseline Update
16. Configuration
Management Plan
[Required per NPR
7120.5; additional
information in NPR
7123.1 and SAE/EIA
649]
OCE/R Baseline Update Update
17. Security Plan
[Required per NPR
1040.1 and NPR 1600.1]
OPS/R Preliminary Baseline
Update
annually
18. Project Protection
Plan [Required per NPR
1058.1, additional
information in
NASA-STD-1006]
OCE/R Preliminary Baseline Update Update Update Update
Update
annually
19. Technology Transfer
(formerly Export)
Control Plan [Required
per NPR 2190.1]
OIIR/R Preliminary Baseline Update
20. Knowledge
Management Plan
[additional information
in NPD 7120.4 and
NPD 7120.6]
OCE/BP
Approach
for
managing
during
Phase A 1
Preliminary Baseline Update
21. Human-Rating
Certification Package
[Required per NPR
8705.2]
OSMA/R
Preliminary
approach2
Initial Update Update Update Update
Approve
Certification
22. Planetary Protection
Plan [Required per NPD
8020.7 and NPR
8715.24]
OSMA/R
Planetary
Protection
Categorization
(if applicable)
Baseline
23. Nuclear Launch
Authorization Plan
[additional information
in NPR 8715.26]
OSMA/R
Baseline
(mission has
nuclear
materials)
24. Range Safety Risk
Management Process
Documentation
[Required per NPR
8715.5]
OSMA/R Preliminary Preliminary Baseline
25. Communications
Plan [additional
information in NPR
7120.5]
OComm/BP Preliminary Baseline Update Update
26. Quality Assurance
Surveillance Plan
[Required per NPR
8735.2 and NASA FAR
Supplement part
1837.604]
OSMA/R Preliminary Baseline Update Update Update
27. Orbital Collision
Avoidance Plan
[Required per NPR
8079.1]
OCE/R Baseline Update
28. Human Systems
Integration Approach
[additional information
in
NASA/SP-20210010952
NASA HSI Handbook
and NPR 7123.1]
OCE-OSMA-OCHMO/R Preliminary Baseline Update Update Update
1 Not the Plan, but documentation of high-level process. May be documented in MCR briefing package.
2 Not the Plan, but documentation of considerations that might impact the cost and schedule baselines. May be documented in MCR briefing package.
3 Review Plan should be baselined before the first review.
NPR 7120.5F -- AppendixI
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 144 of 147
NPR 7120.5F -- AppendixI Page 144 of 147
Appendix J. References
a. Declaration of Policy, 15 U.S.C. §205b, reference: Metric Conversion Act, Pub. L. No. 94-168,
December 23, 1975, as amended by the Omnibus Trade and Competitiveness Act of 1988, Pub. L.
No. 100-418.
b. Metric Usage in Federal Government Programs, Exec. Order No. 12770, dated July 25, 1991.
c. Federal Participation in the Development and Use of Voluntary Consensus Standards and in
Conformity Assessment Activities, OMB Circular No. A-119.
d. NPD 1200.1, NASA Internal Control.
e. NPD 1210.2, NASA Surveys, Audits, and Reviews Policy.
f. NPD 1440.6, NASA Records Management.
g. NPD 1600.2, NASA Security Policy.
h. NPD 2200.1, Management of NASA Scientific and Technical Information.
i. NPD 2800.1, Managing Information Technology.
j. NPD 7120.6, Knowledge Policy for Programs and Projects.
k. NPD 8010.3, Notification of Intent to Decommission or Terminate Operating Space Systems and
Terminate Missions.
l. NPD 8600.1, Capability Portfolio Management.
m. NPD 8700.1, NASA Policy for Safety and Mission Success.
n. NPD 8720.1, NASA Reliability and Maintainability (R&M) Program Policy.
o. NPD 8730.5, NASA Quality Assurance Program Policy.
p. NPD 8800.14, Policy for Real Estate Management.
q. NPD 8900.5, NASA Health and Medical Policy for Human Space Exploration.
r. NPR 1441.1, NASA Records Management Program Requirements.
s. NPR 2200.2, Requirements for Documentation, Approval and Dissemination of Scientific and
Technical Information.
t. NPR 7120.7, NASA Information Technology Program and Project Management Requirements.
u. NPR 7120.8, NASA Research and Technology Program and Project Management Requirements.
v. NPR 7120.11, NASA Health and Medical Technical Authority (HMTA) Implementation.
w. NPR 7500.2, NASA Technology Transfer Requirements.
x. NPR 8621.1, NASA Procedural Requirements for Mishap and Close Call Reporting,
Investigating, and Recordkeeping
NPR 7120.5F -- AppendixJ
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 145 of 147
NPR 7120.5F -- AppendixJ Page 145 of 147
y. NPR 8705.5, Technical Probabilistic Risk Assessment (PRA) Procedures for Safety and Mission
Success for NASA Programs and Projects.
z. NPR 8705.6, Safety and Mission Assurance (SMA) Audits, Reviews, and Assessments.
aa. NPR 8715.26, Nuclear Flight Safety.
bb. NPR 8715.3, NASA General Safety Program Requirements.
cc. NPR 8715.5, Range Flight Safety Program.
dd. NPR 8715.6, NASA Procedural Requirements for Limiting Orbital Debris and Evaluating the
Meteoroid and Orbital Debris Environments.
ee. NPR 8715.7, Payload Safety Program.
ff. NPR 8735.2, Hardware Quality Assurance Program Requirements for Programs and Projects.
gg. NPR 8800.15, Real Estate Management Program.
hh. NPR 8820.2, Facility Project Requirements.
ii. NPR 8900.1, NASA Health and Medical Requirements for Human Space Exploration.
jj. NPR 9250.1, Property, Plant, and Equipment and Operating Materials and Supplies.
kk. NPR 9420.1, Budget Formulation.
ll. NPR 9470.1, Budget Execution.
mm. NASA-STD-1006, Space System Protection Standard.
nn. NASA-STD-8709.22, Safety and Mission Assurance Acronyms, Abbreviations, and Definitions.
oo. NASA-STD-8719.14, Process for Limiting Orbital Debris.
pp. NASA-STD-8719.24, NASA Expendable Launch Vehicle Payload Safety Requirements.
qq. NASA-STD-8729.1, NASA Reliability and Maintainability (R&M) Standard for Spaceflight and
Support Systems.
rr. NASA-STD-8739.8, Software Assurance and Software Safety Standard.
ss. NASA/SP-2016-6105 Rev 2, NASA Systems Engineering Handbook.
https://ntrs.nasa.gov/api/citations/20170001761/downloads/20170001761.pdf
tt. NASA/SP-2011-3422, NASA Risk Management Handbook.
https://ntrs.nasa.gov/api/citations/20120000033/downloads/20120000033.pdf
uu. NASA/SP-20220009501, NASA Space Flight Program and Project Management Handbook.
https://ntrs.nasa.gov/api/citations/20220009501/downloads/20220009501.pdf
vv. NASA/SP-20230001306, NASA Standing Review Board Handbook.
https://ntrs.nasa.gov/citations/20230001306
ww. NASA/SP-2016-3404, NASA Work Breakdown Structure (WBS) Handbook.
https://ntrs.nasa.gov/api/citations/20200000300/downloads/20200000300.pdf
NPR 7120.5F -- AppendixJ
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 146 of 147
NPR 7120.5F -- AppendixJ Page 146 of 147
https://ntrs.nasa.gov/api/citations/20200000300/downloads/20200000300.pdf
xx. NASA/SP-2016-3424, NASA Project Planning and Control Handbook.
https://www.nasa.gov/content/project-planning-control-handbook
yy. SP-20205003605, Technology Readiness Assessment Best Practices Guide.
zz. NASA/SP-20210010952, NASA Human Systems Integration (HSI) Handbook.
aaa. NASA-HDBK-2203, NASA Software Engineering and Assurance Handbook.
https://swehb.nasa.gov/display/SWEHBVC
bbb. NASA Cost Estimating Handbook, version 4.
https://www.nasa.gov/pdf/263676main_2008-NASA-Cost-Handbook-FINAL_v6.pdf
ccc. NC 1000.46, NASA Program/Project Management Board Charter.
https://nodis3.gsfc.nasa.gov/OPD_docs/NC_1000_46_.pdf.
ddd. NASA Program Management Improvement and Accountability Act (PMIAA) Implementation
Plan.
eee. "Changes to the NASA Dissenting Opinion Process," NASA AA Memo, June 18, 2020.
fff. SAE/EIA 649 Standard for Configuration Management.
https://standards.nasa.gov/configuration-management-standard
ggg. NASA Common Leading Indicators Detailed Reference Guide.
https://nodis3.gsfc.nasa.gov/OCE_rep/OCE_list.cfm
NPR 7120.5F -- AppendixJ
This document does not bind the public, except as authorized by law or as
incorporated into a contract. This document is uncontrolled when printed. Check
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
Page 147 of 147
NPR 7120.5F -- AppendixJ Page 147 of 147