the resources to be assigned to their projects. Ideally, resources should be
identified prior to the project kick-off meeting in the initiation phase so that
they may participate and provide input early in the project. As these
individuals are identified, they should be documented in the project plan in
place of generic role placeholders (i.e. Application Developer, Technical
Analyst, etc…). A consideration in creating the project schedule and staffing
plan is that they are very interdependent. The availability of additional
resources may translate into a shortened project schedule. Conversely,
scarce resources may extend the project schedule. If there are dates in the
project schedule that are immovable, then resources must be allocated
accordingly to meet the required schedule. In the absence of hard
scheduling requirements, the project manager should adjust the project
schedule to fit the resources available to the project.
--Estimating effort for tasks : Once the WBS is defined, the project team
must estimate the effort needed to perform the tasks identified. Usually
there will already be a higher-level estimate that has been prepared as part
of the Project Proposal. While this estimate may be used as a reference, it
should not be the basis for the estimates in the project plan. The project
manager should develop the task effort estimates based on the team’s
knowledge of the project requirements, prior experience and the advice of
others on the project team and in the department. It is best to get
estimates from the team members that will be doing the work.
--Scheduling : Once the work has been defined and the required effort has
been estimated, the project manager will create the project schedule. The
project schedule should be developed by determining target start and
completion dates for the tasks and deliverables in the project plan.
--Financial planning: The financial plan details the project costs for external
resources, equipment, software, and expenses (such as travel and any other
project expenditures). For most ITPC projects an initial plan will be entered
into Clarity from the project proposal by the PMO. Actual expenditures will
be entered into Clarity to track against the budget by the PMO. These are
derived from general ledger detail reports on a monthly basis. For very large
projects, a separate detailed cost tracking spreadsheet may be used. The
PMO will provide help developing and maintaining spreadsheets like these
for large projects.
--Critical Path : Once the project plan is developed, the project manager
should identify the critical path in the project. The critical path is the
sequence of tasks/deliverables in a project where none of the
tasks/deliverables can be delayed without affecting the final project end
date. By identifying the critical path in a project, the project manager can
pay particular attention to and take needed actions toward the
tasks/deliverables on the critical path to avoid delays to the overall project
schedule. The critical path is driven by the project task dependencies and
milestones in the plan. A PMO team member will assist the project manager
in determining the project critical path if needed.