ORLANDO / SAN DIEGO
I WAIVED WHAT?
What it Means to Contractually Waive Consequential Damages
By: Mark T. Snelson
i
Effective risk management in the
construction industry begins with properly
drafting a contract that shields away the
unanticipated consequences of a project
gone wrong. No matter where your
company lies in the hierarchy of a
construction project (owner, design
professional, design subconsultant, general
or prime contractor, subcontractor, sub-
subcontractor, or material supplier), you
are no doubt aware that the rights and
remedies enjoyed by you and the party
with whom you have contracted are
primarily determined by the terms of your
contract. One of the quintessential risk
management provisions often included in
construction contracts is a waiver of the
right to recover consequential damages in
claims between the contracting parties.
You have almost certainly seen such
provisions (commonly used AIA contract
forms include clauses waiving
consequential damages), and you may have
signed contracts containing them in the
past. However, have you ever wondered
what exactly a “consequential damage” is,
and, therefore, what you were agreeing to
give up in the event your contractual
relationship sours? The purpose of this
article is to explain the differences
between “direct” or “general” damages
and consequential damages, and to identify
certain categories of damages typically
considered to be consequential, so that
you can be fully informed before agreeing
or disagreeing to these often-arising
contract provisions.
In Florida and many other jurisdictions,
parties are generally free to contractually
limit or waive claims for certain damages
that may arise as a result of a breach of
their contract, including claims for
consequential damages.
ii
A typical example
of a contractual waiver of consequential
damages may read as follows:
The Contractor and Owner
waive Claims against each other
for consequential damages
arising out of or relating to this
Contract.
Many times the contract will then list
specific examples or categories of damages
being waived. Such provisions are not the
exclusive province of owner-contractor
agreements; consequential damage waivers
frequently appear in contracts between
ORLANDO / SAN DIEGO
owners and design professionals and
between general contractors and
subcontractors.
An important question, then, is “What is a
consequential damage?” To answer that
question we have to understand the nature
of “direct” or “general” damages that flow
from a breach of contract. Direct or
general damages are those costs that
immediately and necessarily follow the
violation of a contract. They “are
commonly defined as those damages
which are the direct, natural, logical, and
necessary consequences of the injury.”
iii
These are expenses that “follow
immediately upon the act done” and
“naturally and necessarily flow” from the
breach of contract.
iv
Examples of direct
or general damages are easy to understand.
An owner and a contractor agree to a
contract that requires the contractor to
replace the windows in the owner’s
building for a price of $15,000. The
contractor mobilizes, removes the
windows on the front of the building, and
begins installing new windows. After the
contractor has installed the first new
window the contractor leaves the job and
never returns to finish. The owner then
hires a replacement contractor to finish
the project at a price of $20,000. In this
example the owner has direct or general
damages of $5,000, the difference between
the amount he would have paid to the
original contractor to perform the job as
contracted and the higher amount he had
to pay the replacement contractor.
There are many other examples in the
context of deficient construction services.
Let’s say a hotel owner retains a pool
building contractor to expand and
renovate the hotel pool, and, after
completion and full payment to the
contractor, the parties discover that the
renovated pool leaks. Assuming the leak
was a result of an act or omission on the
part of the contractor, the hotel owner’s
direct damage would be the cost to repair
the leak.
By contrast, consequential damages are
defined as damages that “do not flow
directly and immediately from the act of
the party, but only from some of the
consequences or results of such act.”
v
While they are the result or consequence
of a breach of contact, they do not
immediately spring from the breach
because, to some extent, their existence
depends on both the breach of contract
and other circumstances. Florida courts
have defined consequential damages as
those expenses that are specific to the
non-breaching party which typically stem
from losses incurred by that party’s
dealings with third parties that were
reasonably foreseeable by the breaching
party at the time of contracting.
vi
It is
evident from the definitions attached by
legal authorities and commentators that,
ORLANDO / SAN DIEGO
next to the directness, immediacy, and
necessity of the expense, a key factor in
segregating consequential damages from
general damages is whether the expense
arose, at least in part, due to the
involvement of a third party or
circumstances other than the wrongful act
itself. For instance, in the construction
context, delay damages such as material
escalation costs and additional interest and
finance charges are typically classified as
consequential damages.
vii
The
classification is to be expected considering
these types of damages arise due to the
impositions or requirements of parties that
are outsiders to the breached contract.
For instance, while the owner of a
construction project has to pay more in
interest to its lender as a result of its
general contractor’s breach of contract
and delay in completing the job, the
requirement to pay that interest is imposed
by the terms of the agreement between the
lender and owner.
Going back to the previous examples, if a
storm came through between the time the
original window installation contractor left
the job and the replacement contractor
started, and the storm caused water
infiltration which ruined the hardwood
floors in the owner’s building, the costs to
repair the floors would be the owner’s
consequential damages. If the hotel pool
could not be used during the time it was
leaking and the hotel lost guests and
revenue as a result, the lost revenue or
profits would be the hotel owner’s
consequential damages.
It is difficult to identify all forms of
damages that are classified as
consequential, and the facts of each case
and the other terms in the contract will
influence whether a certain cost is
ultimately determined to be a direct or
consequential damage. However, as a
general proposition, typical examples of
consequential damages in the construction
context include lost rents, rental costs for
replacement property, damages to
business reputation or the loss of
goodwill, down time or idle time, material
escalations, home office overhead costs,
additional energy costs, increased
construction management/supervision
costs, and additional interest and finance
charges. If you sign a contract waiving
claims for consequential damages, these
are the types of expenses you will not be
able to recover from the party that
breaches the contract. Now that you
know what is at stake you can decide
whether agreeing to a contract containing
a waiver of consequential damages is
prudent for your business.
i
Mark Snelson is a Partner with the law firm Wright,
Fulford, Moorhead & Brown, P.A. in Altamonte
Springs, Florida. Mr. Snelson’s practice is devoted to
construction law. He has experience representing all
tiers of the construction industry, including owners,
design professionals, general contractors,
subcontractors, and material suppliers. He can be
ORLANDO / SAN DIEGO
reached at (407) 425-0234, or
ii
See Doctor Diabetic Supply, Inc. v. POAP Corp., 41 So. 3d
916 (Fla. 3d DCA 2010) (enforcing a contractual
provision barring the recovery of consequential
damages); Action Orthopedics, Inc., v. Techmedica, Inc., 759
F.Supp. 1566, 1568 (M.D. Fla. 1991) (contracts may
limit damages recoverable for breach of contract, and if
such provisions are made, greater damages may not be
awarded); Marriott Corp. v. Dasta Constr. Co., 26 F.3d
1057, 1067 n.17 (11th Cir. 1994) (no damage for delay
clauses in construction contracts are enforceable under
Florida law); Hardwick Properties, Inc. v. Newbern, 711 So.
2d 35, 38 (Fla. 1st DCA 1998) (commenting that
parties unquestionably enjoy the freedom to reasonably
limit their respective remedies under a contract).
iii
Florida Power Corp. v. Zenith Industries Company, 377 So.
2d 203, 205 (Fla. 2d DCA 1979).
iv
Black’s Law Dictionary (6th ed. 1991); Hardwick
Props., 711 So. 2d at 39.
v
Black’s Law Dictionary (6th ed. 1991)
vi
Hardwick Props., 711 So. 2d at 40; Saey v. Xerox Corp.,
31 F.Supp.2d 692 (E.D. Mo. 1998) (defining
“consequential damages” as “such damage, loss or
injury as does not flow directly from the act of a party,
but only from some of the consequences or results of
such act”); Trimed, Inc. v. Sherwood Medical Co., 977 F.2d
885, 893 n. 7 (D. Mass. 1990) (same). Florida’s
Uniform Commercial Code defines consequential
damages resulting from a seller’s breach to include
“[a]ny loss resulting from general or particular
requirements and needs of which the seller at the time
of contracting had reason to know and which could not
reasonably be prevented by cover or otherwise.”
§672.715, Florida Statutes.
vii
See Kenneth M. Block, Time is Money: Contractual
Treatment of Delay Damages, New York Law Journal
(Aug. 29, 2007) (“More often than not, consequential
damages in the construction context result from delays
in construction and can include . . . material escalation,
additional increased interest costs, consultant expenses
and lost profits.”); see also Jason L. Richey and William
D. Wickard, Consequential Damages in Today’s Construction
Industry, Constructioneer (May 5, 2008) <available at
http://www.klgates.com/files/Publication/d2f0d5fa-
7ebb-4c2c-9d96-
94577868f2d7/Presentation/PublicationAttachment/3
5e1a2c8-ef0c-466d-aea0-
9cd6af9dd6ca/constructioneer_article_richey.pdf>